GILBERTSVILLE-MT. UPTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-02-02-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          K-12 Building:
92-0399   New Construction             0-012-001  12/10/92  NO CHANGE ORDERS ON ELECTRONIC FILE
08-0409   Additions and Alterations    0-012-003  03/27/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001           165,920                  02/16/10   04/16/10    DELUXE ROOFING & SHEET METAL CORP   
                                                            001            75,300                  02/16/10   04/16/10    RIDLEY ELECTRIC CO INC              
                                                            001          -193,744                  02/16/10   04/16/10    MURNANE BUILDING CONTRACTORS INC    
                                                            001           -52,000                  02/16/10   04/16/10    H.J. BRANDELES CORP                 
                                                            001           -21,000                  02/16/10   04/16/10    LOUIS N PICCIANO AND SON INC        
                                                            002            88,135                  02/16/10   04/16/10    COBLESKILL STONE PRODUCTS INC       
                                                            002           107,071                  02/16/10   04/16/10    MURNANE BUILDING CONTRACTORS INC    
                                                            002            -2,000                  02/16/10   04/16/10    Ridley Electric Co Inc              
                                                            003            32,161                  02/16/10   04/16/10    DELUXE ROOFING & SHEET METAL CORP   
                                                            003            -4,000                  02/16/10   04/16/10    LOUIS N PICCIANO AND SON INC        
                                                            003            57,346                  02/16/10   04/16/10    COBELSKILL STONE PRODUCTS INC       
                                                            003           -39,170                  02/16/10   04/16/10    RIDLEY ELECTRIC CO INC              
                                                            003             5,000                  02/16/10   04/16/10    MURNANE BUILDING CONTRACTORS INC    
                                                            003           -30,564                  02/16/10   04/16/10    H.J. BRANDELES CORP                 
                                                            004                 0                  02/16/10   04/16/10    RIDLEY ELECTRIC CO INC              
                                                            004           -71,416                  02/16/10   04/16/10    MURNANE BUILDING CONTRACTORS INC    
                                                            004                 0                  06/23/10   08/25/10    H.J. BRANDELES CORP                 
                                                            004                 0                  06/14/10   08/26/10    LOUIS N PICCIANO AND SON INC        
                                                            004                 0                  09/01/10   09/28/10    COBLESKILL STONE PRODUCTS INC       
                                                            004                 0                  05/06/11   05/20/11    DELUXE ROOFING & SHEET METAL CORP   
                                                            005                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            005                 0                  06/04/10   07/28/10    H.J. BRANDELES CORP                 
                                                            005           127,385                  09/01/10   09/28/10    COBLESKILL STONE PRODUCTS INC       
                                                            005                 0                  12/02/10   12/28/10    LOUIS N PICCIANO AND SON INC        
                                                            005            24,501                  05/06/11   05/20/11    DELUXE ROOFING & SHEET METAL CORP   
                                                            006                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            006                 0                  06/23/10   08/25/10    RIDLEY ELECTRIC CO INC              
                                                            006                 0                  10/08/10   10/29/10    COBLESKILL STONE PRODUCTS INC       
                                                            006                 0                  12/02/10   12/28/10    LOUIS N PICCIANO AND SON INC        
                                                            006                 0                  12/02/10   12/28/10    H.J. BRANDELES CORP                 
                                                            007                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            007            11,869                  06/23/10   08/25/10    RIDLEY ELECTRIC CO INC              
                                                            007                 0                  09/01/10   09/28/10    COBLESKILL STONE PRODUCTS INC       
                                                            007            -4,319                  02/07/11   02/24/11    H.J. BRANDELES CORP                 
                                                            008                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            008                 0                  06/23/10   08/25/10    RIDLEY ELECTRIC CO INC              
                                                            009                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            009                 0                  09/01/10   09/28/10    COBLESKILL STONE PRODUCTS INC       
                                                            009          -127,385                  10/08/10   10/29/10    COBLESKILL STONE PRODUCTS INC       
                                                            009            10,939                  04/06/11   04/29/11    RIDLEY ELECTRIC CO INC              
                                                            010                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            010             5,081                  10/08/10   10/29/10    COBLESKILL STONE PRODUCTS INC       
                                                            011                 0                  05/12/10   07/23/10    MURNANE BUILDING CONTRACTORS INC    
                                                            012                 0                  06/04/10   07/28/10    MURNANE BUILDING CONTRACTORS INC    
                                                            013           -15,499                  06/23/10   08/27/10    MURNANE BUILDING CONTRACTORS INC    
                                                            014             1,529                  09/01/10   09/28/10    MURNANE BUILDING CONTRACTORS INC    
                                                            015             1,495                  12/02/10   12/28/10    MURNANE BUILDING CONTRACTORS INC    
 
11-1431   Reconstruction               0-012-004  07/27/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001           -17,200                  04/24/13   07/09/13    BLANDING ELECTRIC INC               
                                                            002           -15,394                  04/24/13   07/09/13    BLANDING ELECTRIC INC               
                                                            003             6,126                  04/24/13   07/09/13    BLANDING ELECTRIC INC               
                                                            004            16,250                  05/07/13     /  /      Blanding Electric, Inc.             
 
13-0046   Reconstruction               0-012-005  08/27/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            5,000                  01/14/14   03/04/14    Nelcorp Electrical Contracting Corp.
                                                            EC-2               12                  05/12/14   05/30/14    Nelcorp Electrical Contracting Corp.
 
16-0057   Reconstruction               0-012-006  01/04/17  NO CHANGE ORDERS ON ELECTRONIC FILE
13-1268   Reconstruction               0-012-007  08/05/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           23,700                  12/17/14   01/12/15    A. Treffeisen & Son, LLC            
                                                            EC-2              622                  05/04/15   05/20/15    A. Treffeisen & Son, LLC            
                                                            EC-3            1,358                  06/29/15   08/05/15    A. Treffeisen & Son, LLC            
 
14-1502   Reconstruction               0-012-008  06/16/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1             -208                  05/27/16   06/03/16    BLANDING ELECTRIC                   
 
15-1439   Reconstruction               0-012-009  05/19/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            5,687                  06/26/17   07/05/17    A. Treffeisen & Son, LLC            
 
16-0058   Reconstruction               0-012-010  01/04/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            2,850                  05/22/17   06/07/17    Blanding Electric, inc.             
                                                            EC-2             -232                  05/22/17   06/07/17    Blanding Electric, Inc.             
                                                            GC-1          100,000                  05/22/17   06/01/17    Murnane Building Contractors, Inc.  
                                                            GC-10            -661                  01/29/18   02/02/18    Murnane Building Contractors, Inc.  
                                                            GC-11           3,220                  03/01/18   03/13/18    Murnane Building Contractors, Inc.  
                                                            GC-13           2,046                  03/01/18   03/13/18    Murnane Building Contractors, Inc.  
                                                            GC-15               0                  08/22/18   09/06/18    -4500                               
                                                            GC-2          123,000                  05/22/17   06/01/17    Murnane Building Contractors, Inc.  
                                                            GC-3           25,000                  05/22/17   06/01/17    Murnane Building Contractors, Inc.  
                                                            GC-4           12,000                  05/22/17   06/01/17    Murnane Building Contractors, Inc.  
                                                            GC-5            8,800                  07/21/17   07/27/17    Murnane Building Contractors, Inc.  
                                                            GC-6            4,872           4,872  09/27/17   10/05/17    Murnane Building Contractors, Inc.  
                                                            GC-7            2,552                  11/06/17   11/16/17    Murnane Building Contractors, Inc.  
                                                            GC-8           19,794                  12/21/17   01/29/18    Murnane Building Contractors, Inc.  
                                                            GC-9            4,678                  12/21/17   01/29/18    Murnane Building Contractors, Inc.  
                                                            GC14            5,055                  06/25/18   07/24/18    MURNANE BUILDING CONTRACTORS INC    
                                                            MC-1           -8,936                  12/21/17   01/23/18    H.J. Brandeles Corp.                
                                                            PC-04           8,417                  12/21/17   01/23/18    H.J. Brandeles Corp.                
                                                            PC-05          -1,977                  12/21/17   01/23/18    H.J. Brandeles Corp.                
                                                            PC-1           16,900                  05/22/17   06/07/17    H.J. Brandeles Corp.                
                                                            PC-6            2,604                  05/07/18   05/10/18    H.J. Brandeles Corp.                
 
16-1659   Reconstruction               0-012-012  06/23/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1             -807                  07/23/18   08/06/18    NELCORP ELECTRICAL CONTRACTING CORP 
 
17-0416   Reconstruction               0-012-013  03/14/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-1           -3,500                  12/12/19   01/09/20    MURNANE BUILDING CONTRACTORS, INC.  
 
18-1916   Reconstruction               0-012-014  06/10/19  NO CHANGE ORDERS ON ELECTRONIC FILE
20-1737   Reconstruction               0-012-015  06/22/21  NO CHANGE ORDERS ON ELECTRONIC FILE
21-1924   Reconstruction               0-012-016  10/27/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-1392   Reconstruction               0-012-017  03/22/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-2317   Reconstruction               0-012-018  07/03/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1649FP Reconstruction               0-012-FP1  05/21/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage:
92-0400   New Construction             5-013-001  12/10/92  NO CHANGE ORDERS ON ELECTRONIC FILE
08-0410   Additions and Alterations    5-013-002  03/27/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001           -33,000                  02/16/10   04/16/10    LOUIS N PICCIANO AND SON INC        
                                                            002           103,735                  02/16/10   04/16/10    COBLESKILL STONE PRODUCTS INC       
                                                            002           209,000                  02/16/10   04/16/10    DELUXE ROOFING & SHEET METAL CORP   
                                                            002            24,000                  02/16/10   04/16/10    RIDLEY ELECTRIC CO INC              
                                                            002             6,000                  02/16/10   04/16/10    H.J. BRANDELES CORP                 
                                                            002            43,000                  02/16/10   04/16/10    LOUIS N PICCIANO AND SON INC        
                                                            003           233,000                  02/16/10   04/16/10    MURNANE BUILDING CONTRACTORS INC    
                                                            005                 0                  02/16/10   04/16/10    RIDLEY ELECTRIC CO INC              
                                                            005            34,153                  12/02/10   12/28/10    LOUIS N PICCIANO AND SON INC        
                                                            015             8,531                  12/02/10   12/28/10    MURNANE BUILDING CONTRACTORS INC    
                                                            016            -1,320                  02/07/11   02/24/11    MURNANE BUILDING CONTRACTORS INC    
 
16-0059   Reconstruction               5-013-004  01/04/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-3            1,536                  05/22/17   06/26/17    Blanding Electric, Inc.             
                                                            GC-12             759                  03/01/18   03/13/18    Murnane Building Contractors, Inc.  
                                                            PC-2           -1,634                  07/21/17   09/06/17    H.J. Brandeles Corp.                
                                                            PC-3           15,316                  11/06/17   12/01/17    H.J. Brandeles Corp.                
 
17-2022   Reconstruction               5-013-006  09/25/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            6,487                  07/11/19   07/12/19    A. TREFFEISEN & SON,LLC             
 

          Press Box:
08-1375   New Construction             7-017-001  03/27/09  NO CHANGE ORDERS ON ELECTRONIC FILE

EDMESTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-05-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Central School:
93-1112   Reconstruction               0-001-003  05/06/94  NO CHANGE ORDERS ON ELECTRONIC FILE
98-1296   Additions and Alterations    0-001-004  07/15/99  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-2             2,074                  01/05/01   12/01/03    Edgeline Elec.                      
                                                            T-1            -5,537                  11/16/01   01/08/02    Express Systems Integration         
 
03-1318   Additions and Alterations    0-001-008  08/20/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ACM-001           770                  04/12/06   03/14/07    Midlantic environmental             
                                                            ACM-002         1,380                  11/23/05   12/06/05    Midlantic Environmental             
                                                            E-001         -51,950                  02/07/05   03/14/07    M gleason and Sons of Binghamton    
                                                            E-002          -2,100                  02/07/05   03/17/05    M Gleason and Son of Binghamton of N
                                                            E-003          -2,100                  02/14/05   03/17/05    M Gleason and Sons of Binghamton    
                                                            E-004               0                  04/04/05   04/15/05    M Gleason Sons of Binghamton        
                                                            E-005           9,360                  04/20/05   06/21/05    M Gleason and Sons                  
                                                            E-006               0                  08/10/05   06/05/06    M Gleason and Sons                  
                                                            E-007               0                  03/10/06     /  /      M Gleason and Sons of Binghamton    
                                                            E-007               0                  06/13/07   06/18/07    M Gleason and Sons                  
                                                            E-008             472                  01/30/06   07/24/06    M Gleason and Sons                  
                                                            FS-001              0                  06/13/07   06/18/07    B and W Supply Co                   
                                                            FS-002              0                  07/25/05     /  /      B and W Supply Co                   
                                                            FS-002              0                  03/13/07   06/18/07    B and W Supply Co                   
                                                            FS-003         -6,392                  07/20/06   08/09/06    B and W Supply                      
                                                            FS-004         -4,860                  01/02/07   01/23/07    B and W Supply                      
                                                            GC-001        -10,000                  11/03/04   11/23/04    Simmons Contraction                 
                                                            GC-002          4,967                  01/04/05   01/10/05    Simmons Construction                
                                                            GC-003              0                  02/24/05   03/25/05    Simmons Construction                
                                                            GC-004              0                  04/12/06   03/14/07    simmons Construction                
                                                            GC-005              0                  07/25/05     /  /      Simmons construction                
                                                            GC-005              0                  06/13/07   06/18/07    Simmon Construction                 
                                                            GC-006              0                  04/12/06   06/05/06    simmons construction                
                                                            GC-007              0                  11/23/05   12/06/05    Simmons Construction                
                                                            GC-008        192,463                  04/12/06   03/14/07    simons Construction                 
                                                            GC-009              0                  11/23/05   12/06/05    Simmons construction                
                                                            GC-010              0                  12/21/05   01/06/06    Simmons Construction                
                                                            GC-011              0                  03/20/06   06/05/06    Simmson Construction                
                                                            GC-012              0                  03/20/06   06/05/06    simmons Construction                
                                                            GC-013        -64,579                  07/26/06   08/25/06    Simmons Construction                
                                                            GC-014         58,898                  12/21/06   01/19/07    Simmons Construction                
                                                            H-001               0                  02/07/05   08/09/06    Hj brandeles Corp                   
                                                            H-002               0                  07/25/05     /  /      HJ Brandeles Corp                   
                                                            H-002               0                  06/13/07   06/18/07    HJ Brandeles Corp                   
                                                            H-003               0                  08/10/05   08/09/06    HJ Brandeles Corp                   
                                                            H-004               0                  04/12/06   05/26/06    Hj Brandeles Corp                   
                                                            H-005               0                  11/23/05   11/30/05    H.J. Brandeles Corporation          
                                                            H-006               0                  03/20/06   05/25/06    Hj brandeles Corp                   
                                                            H-007          -1,841                  03/20/06   05/25/06    Hj brandeles Corp                   
                                                            P-001           3,766                  11/22/04   12/17/04    HJ Brandeles                        
                                                            P-002          -4,310                  03/06/06   08/09/06    HJ Brandeles Corp                   
                                                            P-003          -4,310                  11/27/05   05/24/06    HJ Brandeles Corp                   
                                                            P-004          -1,100                  03/06/06   06/30/06    HJ Brandeles Corp                   
                                                            R-001         -28,850                  11/03/04   11/23/04    Pulver Roofing Co                   
                                                            R-002           1,215                  02/14/05   03/17/05    Pulver Roofing Company              
                                                            R-003               0                  11/23/05   12/06/05    Pulver Roofing Co                   
                                                            R-004          -8,556                  01/30/06   07/24/06    pulver Roofing                      
                                                            R-005          13,560                  03/13/07   05/09/07    Pulver Roofing Co                   
 
08-0406   Reconstruction               0-001-009  04/03/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-002          39,500                  12/10/09   01/21/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-003           4,610                  12/10/09   01/21/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-004           2,486                  12/10/09   01/21/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-005             570                  12/10/09   01/21/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-006           2,853                  12/10/09   01/21/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-007             945                  12/10/09   01/21/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-008             853                  01/04/10   02/25/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-009          -2,467                  02/10/10   05/03/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-010           2,991                  02/10/10   04/27/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-011           5,720                  02/10/10   04/27/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-012             661                  02/10/10   04/27/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-013           4,023                  02/10/10   04/27/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-014          -1,970                  09/03/10   09/27/10    RIDLEY ELECTRIC COMPANY INC         
                                                            E-015          -2,550                  06/14/11   06/20/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-017          -8,299                  06/14/11   06/20/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-019             176                  02/04/11   03/03/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-021             729                  02/22/11   05/03/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-022          -8,995                  06/29/11   07/18/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-023            -900                  06/29/11   07/18/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-024         -49,684                  06/23/11   08/05/11    RIDLEY ELECTRIC COMPANY INC         
                                                            GC-001         37,975                  12/10/09   01/21/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-003          2,100                  12/10/09   01/21/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-004          1,400                  12/10/09   01/21/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-005            917                  01/04/10   03/12/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-006         -2,467                  02/10/10   04/27/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-007          5,127                  02/10/10   04/27/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-008          5,930                  03/05/10   04/28/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-009             87                  02/10/10   04/27/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-009 R           87                  03/05/10   04/28/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-010 R        3,992                  03/05/10   04/28/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-012          1,766                  05/26/10   07/20/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-013          3,220                  05/26/10   07/21/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-014          3,617                  05/26/10     /  /      PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-015          3,666                  06/21/10   08/16/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-017          1,402                  06/21/10   08/16/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-017          4,092                  06/21/10   08/16/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-018         11,328                  06/21/10   08/16/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-019          1,213                  08/20/10   09/13/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-020          2,827                  08/20/10   09/13/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-021          8,883                  09/24/10   10/04/10    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-022         14,490                  04/11/11   05/13/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-023         14,700                  04/11/11   05/13/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-024         24,502                  04/11/11   05/16/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-025R        16,975                  05/02/11     /  /      PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-026          4,805                  05/26/11   06/08/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-027          8,995                  05/26/11   06/08/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-028         -1,485                  05/26/11   06/08/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-029              0                  05/26/11   06/08/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-030              0                  05/26/11   06/08/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            GC-031         -6,851                  05/26/11   06/08/11    PUTRELO BUILDING ENTERPRISES INC    
                                                            M-001           2,524                  12/10/09   01/21/10    H.J. BRANDELES CORPORATION          
                                                            M-002         -47,500                  12/10/09   01/21/10    H.J. BRANDELES CORPORATION          
                                                            M-004           6,830                  12/10/09     /  /      H.J. BRANDELES CORPORATION          
                                                            M-005           5,556                  12/10/09   01/21/10    H.J. BRANDELES CORPORATION          
                                                            M-006           5,200                  12/10/09   01/21/10    H.J. BRANDELES CORPORATION          
                                                            M-007          11,470                  12/10/09   02/22/12    H.J. BRANDELES CORPORATION          
                                                            M-008           1,947                  12/10/09   01/21/10    H.J. BRANDELES CORPORATION          
                                                            M-009           3,769                  02/10/10   04/27/10    H.J. BRANDELES CORPORATION          
                                                            M-010          -2,467                  02/10/10   04/27/10    H.J. BRANDELES CORPORATION          
                                                            M-011           1,432                  02/10/10   04/27/10    H.J. BRANDELES CORPORATION          
                                                            M-012           1,782                  02/10/10   04/27/10    H.J. BRANDELES CORPORATION          
                                                            M-013            -756                  03/05/10   04/28/10    H.J. BRANDELES CORPORATION          
                                                            M-014           2,550                  02/23/10   03/25/10    H.J. BRANDELES CORPORATION          
                                                            M-015           6,171                  04/06/10   06/16/10    H.J. BRANDELES CORPORATION          
                                                            M-016             871                  04/06/10   06/16/10    H.J. BRANDELES CORPORATION          
                                                            M-017          20,900                  05/06/10   07/20/10    H.J. BRANDELES CORPORATION          
                                                            M-018          15,625                  07/07/10   08/23/10    H.J. BRANDELES CORPORATION          
                                                            M-019           6,037                  06/11/10   08/26/10    H.J. BRANDELES CORPORATION          
                                                            M-020            -584                  09/10/10   09/28/10    H.J. BRANDELES CORPORATION          
                                                            M-021            -654                  05/02/11     /  /      H.J. BRANDELES CORPORATION          
                                                            P-001           2,745                  12/10/09   01/21/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            P-002         -17,200                  12/10/09   01/21/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            P-003           3,988                  12/30/09   01/21/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            P-004             665                  02/10/10   04/27/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            P-005          27,602                  03/05/10   04/28/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
 
12-0610   Reconstruction               0-001-010  07/18/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-01           -2,675                  05/01/14   05/16/14    Nelcorp Electrical Contracting Corpo
                                                            E-02                0                  05/01/14   05/16/14    Nelcorp Electrical Contracting Corpo
                                                            E-03                0                  10/31/14   11/12/14    Nelcorp Electrical Construction Corp
                                                            E-04                0                  10/31/14   11/12/14    Nelcorp Electrical Construction Corp
                                                            E-05                0                  11/20/14   11/21/14    Nelcorp Electrical Contracting Corp 
                                                            E-06             -683                  11/20/14   11/21/14    Nelcorp Electrical Contracting Corp 
                                                            GC-01               0                  02/21/14   03/21/14    Bunkoff General Contractors         
                                                            GC-02          -2,256                  03/21/14   04/15/14    Bunkoff General Contractors         
                                                            GC-03               0                  06/20/14   08/01/14    BUNKOFF GENERAL CONTRACTORS         
                                                            GC-04               0                  06/20/14   08/01/14    BUNKOFF GENERAL CONTRACTORS         
                                                            GC-05               0                  09/17/14   09/23/14    Bunkoff General Contractors         
                                                            GC-06               0                  09/17/14   09/23/14    Bunkoff General Contractors         
                                                            GC-07               0                  11/10/14   11/14/14    Bunkoff General Contractors         
                                                            GC-08               0                  11/10/14   11/14/14    Bunkoff General Contractors         
                                                            GC-09            -522                  11/10/14   11/14/14    Bunkoff General Contractors         
                                                            H-01                0                  07/16/14   08/15/14    H.J. Brandeles, Corp.               
                                                            H-02            5,174                  10/31/14   11/12/14    H.J. Brandeles, Corp.               
                                                            P-01                0                  07/16/14     /  /      H.J. Brandeles, Corp.               
                                                            P-02                0                  09/10/14   09/12/14    H.J. Brandeles, Corp.               
                                                            P-03           -3,629                  09/10/14   09/16/14    H.J. Brandeles, Corp.               
                                                            P-04           -1,852                  12/09/14   12/15/14    H.J. Brandeles, Corp.               
 
14-1669   Reconstruction               0-001-011  07/16/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  04/11/16   12/28/16    J.J. Curran & Son, Inc.             
                                                            GC-02          -1,200                  04/11/16   12/28/16    J.J. Curran & Son, Inc.             
 
15-1864   Reconstruction               0-001-012  06/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            H-01           -2,400                  03/20/17   03/24/17    H.J. Brandeles, Corp.               
 
17-0055   Reconstruction               0-001-013  01/08/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HVAC-01             0                  05/01/18   06/01/18    H.J. Brandeles Corp.                
 
18-0110   Reconstruction               0-001-014  08/13/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01          -4,150                  05/31/19   06/05/19    MURNANE BUILDING CONTRACTORS, INC.  
                                                            GC-02          -4,000                  05/31/19   06/05/19    MURNANE BUILDING CONTRACTORS, INC.  
 
18-1951   Reconstruction               0-001-015  06/19/19  NO CHANGE ORDERS ON ELECTRONIC FILE
19-0088   Reconstruction               0-001-016  09/05/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  07/29/20   10/26/20    MURNANE BUILDING CONTRACTORS        
                                                            GC-02          -3,710                  07/29/20   10/26/20    MURNANE BUILDING CONTRACTORS        
 
19-1114   Reconstruction               0-001-017  03/30/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01               0                  01/29/21   03/24/21    BAGNALL ELECTRIC, INC.              
                                                            GC-01               0                  10/21/20   01/08/21    WILLIAM H. LANE, INC.               
                                                            GC-02               0                  10/21/20   01/08/21    WILLIAM H. LANE, INC.               
                                                            GC-03               0                  10/04/21   12/02/22    William Lane, Inc                   
                                                            GC-04               0                  10/04/21   12/02/22    William lane, Inc                   
                                                            GC-05               0                  02/16/21   04/15/21    WILLIAM H. LANE, INC.               
                                                            GC-06               0                  10/04/21   12/02/22    William Lane, Inc                   
                                                            GC-07               0                  10/25/21   12/06/22    William Lane, Inc                   
                                                            GC-08               0                  10/15/21   12/06/22    William Lane, Inc                   
                                                            HVAC-01          -985                  01/29/21   03/24/21    A. TREFFEISEN & SON, LLC            
                                                            HVAC-02        -2,500                  01/29/21   03/24/21    A. TREFFEISEN & SON, LLC            
                                                            ROOF-01       -15,000                  10/29/20   01/22/21    AB CONSTRUCTION & ROOFING, INC.     
 
20-0066   Reconstruction               0-001-018  08/26/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            S-01                0                  06/29/21   04/04/22    Rifanburgs Lawn And Landscape       
                                                            S-02            3,740                  06/29/21   04/04/22    Rifanburgs Lawn and Landscape       
                                                            S-03            5,380                  06/29/21   04/04/22    Rifanburgs Lawn and Landscape       
 
21-1572FC Reconstruction               0-001-019  06/15/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HC-01          85,559                  02/13/23   12/11/23    H.J. BRANDELES CORP                 
                                                            HC-02               0                  09/19/23     /  /      H.J BRANDELES CORP                  
 
21-1678   Reconstruction               0-001-020  08/24/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-0787   Reconstruction               0-001-021  12/23/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-2054   Reconstruction               0-001-022  06/19/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-2040FP Reconstruction               0-001-FP1  10/06/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          IndustrialArts/Shop/TechnologyBldg:
93-1113   Reconstruction               0-003-001  05/06/94  NO CHANGE ORDERS ON ELECTRONIC FILE
98-1297   Reconstruction               0-003-002  07/15/99  NO CHANGE ORDERS ON ELECTRONIC FILE
12-0611   Reconstruction               0-003-004  07/18/13  NO CHANGE ORDERS ON ELECTRONIC FILE
19-1115   Reconstruction               0-003-005  03/30/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-02             845                  01/29/21   03/24/21    BAGNALL ELECTRIC, INC.              
 

          Bus Garage:
08-0408   Reconstruction               5-004-002  04/03/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-018           1,856                  02/22/11   05/03/11    RIDLEY ELECTRIC COMPANY INC         
                                                            E-020             471                  02/22/11   05/03/11    RIDLEY ELECTRIC COMPANY INC         
                                                            GC-011             47                  05/03/10   07/15/10    PUTRELO BUILDING ENTERPRISES INC    
 
18-1599   Reconstruction               5-004-003  03/08/19  NO CHANGE ORDERS ON ELECTRONIC FILE
19-1116   Reconstruction               5-004-004  03/30/20  NO CHANGE ORDERS ON ELECTRONIC FILE
21-0003   Reconstruction               5-004-005  07/31/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01          12,000                  06/27/22     /  /      Rifanburg Lawn&Landscape LLC        
 
22-0283   Reconstruction               5-004-006  10/05/22  NO CHANGE ORDERS ON ELECTRONIC FILE

          District-Wide:
17-1394   Reconstruction               7-999-001  05/08/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  06/22/18   08/01/18    WHITTON CONSTRUCTION LLC            
                                                            GC-02           1,259                  03/20/19   04/25/19    WHITTON CONSTRUCTION                
 

LAURENS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-08-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Building:
91-0123   Reconstruction               0-001-005  08/14/91  NO CHANGE ORDERS ON ELECTRONIC FILE
95-1575   Reconstruction               0-001-007  10/16/96  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1157   Reconstruction               0-001-009  05/10/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            R-5             6,415                  07/25/02   10/28/02    WeatherGuard Roofing                
 
06-0462   Additions and Alterations    0-001-010  05/09/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ACM-001        19,600                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            ACM-002        18,608                  04/24/08   08/06/08    EXCEL INSULATION COMPANY, INC.      
                                                            ACM-003         4,401                  09/04/08   10/24/08    EXCEL INSULATION COMPANY, INC.      
                                                            ACM-004         3,963                  09/04/08   10/24/08    EXCEL INSULATION COMPANY, INC.      
                                                            ACM-005           598                  06/11/09   08/19/09    EXCEL INSULATION COMPANY            
                                                            ACM-006         8,477                  06/11/09   08/18/09    EXCEL INSULATION COMPANY,INC        
                                                            ACM-007        16,524                  10/14/09   11/09/09    EXCEL INSULATION COMPANY INC        
                                                            ACM-008         7,121                  10/14/09   11/09/09    EXCEL INSULATION COMPANY INC        
                                                            AETS-002        1,470                  05/20/10   05/25/10    NICKERSON CORP                      
                                                            AETS-002          572                  05/20/10   05/25/10    NICKERSON CORP                      
                                                            E-001         -15,450                  06/19/08     /  /      Nelcorp Electrical Contracting      
                                                            E-002         -12,985                  06/19/08   02/11/09    Nelcorp Electrical Contracting      
                                                            E-003          -6,792                  06/19/08   02/11/09    Nelcorp Electrical Contracting      
                                                            E-004         -25,000                  01/25/10   03/09/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-005           1,773                  02/12/10   04/30/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-006           5,325                  02/12/10   04/30/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-007           4,660                  02/12/10   04/30/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-008           4,123                  07/16/10   09/13/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-009           4,151                  07/16/10   09/13/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-010           4,747                  07/16/10   09/13/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-011           3,962                  07/16/10   09/13/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-012           3,453                  07/16/10   09/13/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-013           7,018                  07/16/10   09/10/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E-014         -35,785                  07/28/10   09/07/10    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            FS-001         -5,700                  09/21/07   11/26/07    JOSEPH FLIHAN COMPANY               
                                                            FS-002          6,900                  05/21/08     /  /      JOSPEH FILHAN COMPANY               
                                                            FS-003              0                  05/21/08     /  /      JOSEPH FLIHAN COMPANY               
                                                            FS-003              0                  05/21/08     /  /      JOSEPH FILHAN COMPANY               
                                                            FS-004              0                  03/27/09   06/25/09    JOSEPH FLIHAN COMPANY               
                                                            FS-005         -4,507                  03/27/09   06/25/09    JOSEPH FILHAN COMPANY               
                                                            GC-001        -15,566                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-002         -5,181                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-003        -35,000                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-004        -12,200                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-005              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-006              0                  02/15/08   03/08/08    SIMMONS CONSTRUCTION                
                                                            GC-007        -43,558                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-008              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-009              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-010              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-011              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-012              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-013              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-014         80,000                  02/15/08   03/19/08    SIMMONS CONTRACTING                 
                                                            GC-015              0                  02/15/08   03/19/08    SIMMONS CONSTRUCTION                
                                                            GC-016              0                  03/21/08   08/07/08    SIMMONS CONSTRUCTION                
                                                            GC-017              0                  03/21/08   03/31/08    SIMMONS CONSTRUCTION                
                                                            GC-018              0                  03/21/08   04/08/08    SIMMONS CONSTRUCTION                
                                                            GC-019              0                  03/21/08   03/31/08    SIMMONS CONSTRUCTION                
                                                            GC-020              0                  03/21/08   03/31/08    SIMMONS CONSTRUCTION                
                                                            GC-021              0                  03/21/08     /  /      SIMMONS CONSTRUCTION                
                                                            GC-022              0                  03/21/08   03/31/08    SIMMONS CONSTRUCTION                
                                                            GC-023              0                  03/25/08   08/07/08    Simmons Construction                
                                                            GC-024              0                  03/25/08   08/07/08    SIMMONS CONSTRUCTION                
                                                            GC-026              0                  04/24/08   08/07/08    SIMMONS CONSTRUCTION                
                                                            GC-027              0                  05/21/09     /  /      SIMMONS CONSTRUCTION                
                                                            GC-028              0                  06/19/08   08/26/08    Simmons Construction                
                                                            GC-029              0                  06/19/08   08/26/08    Simmons Construction                
                                                            GC-030              0                  09/04/08   10/24/08    SIMMONS CONSTRUCTION                
                                                            GC-031              0                  09/04/08   10/24/08    SIMMONS CONTSTRUCTION               
                                                            GC-032              0                  09/04/08   10/24/08    SIMMONS CONSTRUCTION                
                                                            GC-033              0                  09/04/08   10/24/08    SIMMONS CONSTRUCTION                
                                                            GC-034              0                  09/04/08   10/24/08    SIMMONS CONSTRUCTION                
                                                            GC-035              0                  10/20/08   11/10/08    SIMMONS CONSTRUCTION                
                                                            GC-036              0                  10/20/08   11/10/08    SIMMONS CONSTRUCITION               
                                                            GC-037              0                  10/20/08   11/10/08    SIMMONS CONSTRUCTION                
                                                            GC-038              0                  12/15/08   02/12/09    SIMMONS CONSTRUCTION                
                                                            GC-039          2,149                  07/28/10   09/07/10    SIMMONS CONSTRUCTION                
                                                            GC-040              0                  12/15/08   02/12/09    SIMMONS CONSTRUCTION                
                                                            GC-041              0                  01/28/09   04/03/09    SIMMONS CONTRUCTION                 
                                                            GC-042              0                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-043          4,744                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-044          5,905                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-045          6,926                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-046          3,281                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-047          5,124                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-048          9,506                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-049          5,284                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-050          5,750                  01/28/09   04/03/09    SIMMONS CONSTRUCTION                
                                                            GC-052          7,937                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-053          9,596                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-054         13,753                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-055          7,640                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-056            527                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-057          8,213                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-058          5,918                  03/27/09   06/25/09    SIMMONS CONSTRUCTION                
                                                            GC-059            707                  03/27/09     /  /      SIMMONS CONSTRUCTION                
                                                            GC-060          9,574                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-061         32,280                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-062          4,632                  06/11/09   07/15/09    SIMMONS CONSTRUCTION                
                                                            GC-063          8,852                  11/30/11   02/23/12    SIMMONS CONSTRUCTION                
                                                            GC-064          8,110                  11/30/11   02/23/12    SIMMONS CONSTRUCTION                
                                                            GC-065            452                  11/30/11   02/23/12    SIMMONS CONSTRUCTION                
                                                            GC-066            720                  10/14/09   11/09/09    SIMMONS CONSTRUCTION                
                                                            GC-067          4,652                  11/30/11   02/23/12    SIMMONS CONSTRUCTION                
                                                            GC-068          6,311                  10/14/09   11/09/09    SIMMONS CONSTRUCTION                
                                                            GC-069          5,212                  10/14/09   11/09/09    SIMMONS CONSTRUCTION                
                                                            GC-070          1,563                  10/14/09   11/09/09    SIMMONS CONSTRUCTION                
                                                            GC-071          3,550                  10/14/09   11/09/09    SIMMONS CONSTRUCTION                
                                                            GC-072          6,317                  10/14/09   11/09/09    SIMMONS CONSTRUCTION                
                                                            GC-073          2,205                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-074          3,366                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-075          4,793                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-076          3,605                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-077          3,162                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-078          4,079                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-079          1,428                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-080          1,374                  10/14/09   11/13/09    SIMMONS CONSTRUCTION                
                                                            GC-081            631                  10/14/09   11/13/09    SIMMONS CONTRUCTION                 
                                                            GC-082          1,317                  01/25/10   03/09/10    SIMMONS CONSTRUCTION                
                                                            GC-083          4,648                  06/17/10   08/10/10    SIMMONS CONSTRUCTION                
                                                            GC-084          1,211                  06/17/10   08/10/10    SIMMONS CONSTRUCTION                
                                                            GC-085           -286                  03/22/10   05/14/10    SIMMONS CONSTRUCTION                
                                                            GC-086          2,476                  03/22/10   05/14/10    SIMMONS CONSTRUCTION                
                                                            GC-087          6,310                  04/14/10   06/04/10    SIMMONS CONSTRUCTION                
                                                            GC-088          4,922                  04/14/10   06/04/10    SIMMONS CONSTRUCTION                
                                                            GC-089          3,172                  04/14/10   06/04/10    SIMMONS CONSTRUCTION                
                                                            GC-090          5,499                  04/20/10   08/05/10    SIMMONS CONSTRUCTION                
                                                            GC_025              0                  04/24/08   08/07/08    SIMMONS CONSTRUCTION                
                                                            L-001          -8,000                  02/15/08   03/19/08    RITTER & PARATORE CONTRACTING, INC  
                                                            L-002          70,700                  02/15/08   03/19/08    RITTER & PARATORE CONTRACTING, INC. 
                                                            L-003               0                  03/21/08   08/07/08    RITTER & PARATORE CONTRACTING, INC. 
                                                            L-004               0                  03/21/08     /  /      RITTER & PARATORE CONTRACTING, INC. 
                                                            L-005               0                  03/21/08   08/07/08    RITTER & PARATORE CONTRACTING, INC. 
                                                            L-006               0                  10/20/08   11/10/08    RITTER & PARATORE CONTRACTING, INC. 
                                                            L-007               0                  10/20/08   11/10/08    RITTER & PARATORE CONTRACTING, INC. 
                                                            L-008               0                  12/15/08   02/12/09    RITTER & PARATORE CONTRACTING       
                                                            L-009            -448                  06/17/10   08/10/10    RITTER & PARATORE CONTRACTING INC   
                                                            LE-001         31,616                  02/22/08   03/08/08    BRODART COMPANY                     
                                                            LE-002          8,244                  03/05/10   04/28/10    BRODART COMPANY                     
                                                            LE-003         -5,000                  03/05/10   04/28/10    BRODART COMPANY                     
                                                            LKR-001         4,653                  11/12/09   12/08/09    NICKERSON CORPORATION               
                                                            LKR-002          -347                  10/20/10   10/29/10    NICKERSON CORPORATION               
                                                            LKR-003        -1,379                  04/12/11   05/10/11    NICKERSON CORPORATION               
                                                            M-001         -11,000                  02/15/08   04/04/08    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            M-002          -8,000                  02/15/08   04/04/08    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            M-003          -5,426                  02/15/08   04/04/08    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            M-004               0                  05/05/08   06/12/08    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            M-005               0                  05/05/08   06/12/08    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            M-006               0                  05/05/08   06/12/08    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            M-007               0                  05/05/08   06/12/08    PICCIRILLI-SLAVIK & VINCENT         
                                                            M-008               0                  09/04/08   02/20/09    PICCIRILLI - SALVIK & VINCENT PLUMBI
                                                            M-009           1,358                  06/11/10   08/26/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-010               0                  10/20/08   11/10/08    PICCIRILLI - SLAVIK & VINCENT PLUMBI
                                                            M-011               0                  12/15/08   07/06/09    PICCIRILLI-SALVIK & VINCENT PLUMBING
                                                            M-012          10,371                  07/28/10   09/07/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-013               0                  08/24/11   02/10/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-014               0                  08/24/11   02/16/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-015           5,442                  07/21/09   09/24/09    PICCIRILLI-SLAVIK & VINCENT         
                                                            M-016               0                  07/21/09     /  /      PICCIRILLI-SLAVIK & VINCENT         
                                                            M-017               0                  07/21/09     /  /      PICCIRILLI-SLAVIK & VINCENT         
                                                            M-018               0                  08/24/11   02/08/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-019           4,042                  04/14/10   06/04/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-020           2,591                  10/18/10   11/05/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-021            -286                  08/24/11   02/08/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-022               0                  08/24/11   02/08/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-023               0                  08/24/11   02/08/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-024          16,858                  09/03/10   09/27/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-025           6,242                  09/03/10   09/27/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-026           1,305                  11/12/10   11/22/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-027           1,722                  01/27/11   02/28/11    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            M-028          -5,000                  08/24/11   02/08/12    PICIRILLI-SLAVIK & VINCENT P/H INC  
                                                            MC-001         -2,500                  10/20/08   11/10/08    NORTHEAST INTERIOR SYSTEMS, INC.    
                                                            MC-002              0                  10/20/08   11/10/08    NORTHEAST INTERIOR SYSTEMS, INC.    
                                                            MC-003              0                  10/20/08   11/10/08    NORTHEAST INTERIOR SYSTEMS, INC.    
                                                            MC-004         -7,897                  09/03/10   09/27/10    NORTHEAST INTERIOR SYSTEMS INC      
                                                            P-001         -41,250                  10/01/07   10/23/07    LOUIS N. PICCIANO & SONS, INC.      
                                                            P-002         -38,700                  10/01/07   10/23/07    LOUIS N. PICCIANO & SONS, INC.      
                                                            P-003               0                  02/15/08   04/04/08    LOUIS N. PICCIANO & SON, INC        
                                                            P-004               0                  03/21/08   08/07/08    LOUIS N. PICCIANO & SONS, INC.      
                                                            P-005               0                  03/21/08   08/07/08    LOUIS N. PICCIANO & SONS, INC.      
                                                            P-006               0                  01/28/09   04/07/09    LOUIS N. PICCIANO & SONS, INC.      
                                                            P-007           1,107                  06/11/09   08/21/09    Louis N. Picciano & Son             
                                                            P-008               0                  01/25/10   03/09/10    LOUIS N PICCIANO & SON              
                                                            P-009         -33,750                  07/28/10   09/07/10    LOUIS N PICCIANO & SON INC          
                                                            R-001           8,600                  09/04/08   10/24/08    AB CONSTRUCTION & ROOFING           
                                                            R-002           5,660                  09/04/08   10/24/08    AB CONSTRUCTION & ROOFING           
                                                            R-003             610                  11/12/09   12/08/09    AB CONSTRUCTION & ROOFING INC       
                                                            R-004             670                  11/12/09   12/08/09    AB CONSTRUCTION & ROOFING INC       
                                                            R-005          -4,460                  03/05/10   04/28/10    AB CONSTRUCTION & ROOFING INC       
                                                            SE-001          6,198                  02/22/08   03/08/08    THE JANSON INDUSTRIRES              
                                                            SE-002         11,524                  03/21/08   03/31/08    THE JANSON INDUSTRIES               
                                                            SE-003         -5,000                  03/27/09   06/25/09    THE JANSON INDUSTERIES              
 
10-1337   Reconstruction               0-001-011  07/12/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ELEV-01         8,740                  10/31/12   08/16/13    SYRACUSE LIFT & HOISE CO INC        
                                                            P-002          -2,000                  11/16/12   07/17/13    Ackerman Plumbing, Inc.             
                                                            R-001            -875                  11/26/12   03/07/13    PULVER ROOFING CO INC               
 
13-0426   Reconstruction               0-001-012  04/14/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-03           -3,679                  11/18/14   11/20/14    NELCORP Electircal Contracting Corp.
                                                            GC-01         -20,177                  08/08/14   08/28/14    Bunkoff General Contractors, Inc.   
                                                            GC-010              0                  11/18/14   11/20/14    Bunkoff General Contractors, Inc.   
                                                            GC-02               0                  08/08/14   08/28/14    Bunkoff General Contractors, Inc.   
                                                            GC-03               0                  08/21/14   09/02/14    Bunkoff General Contractors, Inc.   
                                                            GC-05               0                  09/29/14   10/08/14    Bunkoff General Contractors, Inc.   
                                                            GC-06               0                  11/18/14   11/20/14    Bunkoff General Contractors, Inc.   
                                                            GC-07               0                  11/18/14   11/20/14    Bunkoff General Contractors, Inc.   
                                                            GC-08               0                  11/18/14   11/20/14    Bunkoff General Contractors, Inc.   
                                                            GC-09               0                  11/18/14   11/20/14    Bunkoff General Contractors, Inc.   
                                                            GC-11               0                  11/18/14   11/20/14    Bunkoff General Contractors, Inc.   
                                                            GC-13          -4,652                  01/16/15   01/22/15    Bunkoff General Contractors, Inc.   
                                                            M-01           -2,870                  08/21/14   09/02/14    Avolio Brothers LLC                 
                                                            M-02           -3,365                  02/23/15   02/26/15    Avolio Brothers, LLC                
                                                            M-03              511                  02/23/15   02/26/15    Avolio Brothers, LLC                
 
12-1238   Reconstruction               0-001-013  08/30/13  NO CHANGE ORDERS ON ELECTRONIC FILE
13-1035   Reconstruction               0-001-014  10/08/13  NO CHANGE ORDERS ON ELECTRONIC FILE
14-0058   Reconstruction               0-001-015  01/07/15  NO CHANGE ORDERS ON ELECTRONIC FILE
14-1617   Reconstruction               0-001-016  06/24/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01          -2,000                  04/11/16   12/28/16    Whitton Construction Company        
 
15-0847   Reconstruction               0-001-017  06/07/16  NO CHANGE ORDERS ON ELECTRONIC FILE
16-0022   Reconstruction               0-001-018  07/25/16  NO CHANGE ORDERS ON ELECTRONIC FILE
16-0309   Reconstruction               0-001-019  04/12/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            E-01            3,000                  08/22/18   09/12/18    A. TREFFEISEN & SON LLC             
                                                            E-02            2,149                  08/22/18   09/12/18    A. TREFFEISEN & SON LLC             
                                                            GC-01         -55,000                  11/10/17   12/14/17    Upstate Companies                   
                                                            GC-02          47,000                  11/10/17   12/14/17    Upstate Companies                   
                                                            GC-03           4,476                  11/10/17   12/14/17    Upstate Companies                   
                                                            GC-04          15,790                  11/10/17   12/14/17    Upstate Companies                   
                                                            GC-05           8,403                  11/10/17   11/28/17    Upstate Companies                   
                                                            H-01           -8,000                  08/22/18   09/12/18    A. TREFFEISEN & SON LLC             
                                                            P-02           -5,000                  02/01/18   04/12/18    A. Treffeisen & Son LLC             
 
17-0429   Reconstruction               0-001-020  10/25/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-01                0                  07/11/18   07/26/18    MATCO ELECTRIC                      
                                                            E-02            1,359                  07/11/18   07/26/18    MATCO ELECTRIC                      
                                                            GC-01          -2,000                  05/02/18   08/06/18    Murnane Building Contractors, Inc.  
 
18-0012   Reconstruction               0-001-021  07/31/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-01           14,889                  12/21/18   02/12/19    A. TREFFEISEN & SON, LLC            
                                                            E-02            5,264                  02/11/19   02/27/19    A. TREFFEISEN & SON,LLC             
                                                            E-03                0                  02/15/19   03/05/19    A. TREFFEISEN & SON,LLC             
                                                            E-04            1,089                  02/27/19   03/13/19    A. TREFFEISEN & SON, LLC            
 
18-2198   Reconstruction               0-001-022  08/12/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-02             -950                  01/27/20   02/19/20    BLANDING ELECTRIC, INC.             
                                                            E-03                0                  01/27/20   02/19/20    BLANDING ELECTRIC, INC.             
                                                            EC-01          -5,300                  11/20/19   12/16/19    BLANDING ELECTRIC, INC.             
 
20-0168   Reconstruction               0-001-023  09/15/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HVAC-01        -4,000                  06/23/21   09/30/21    Piccirilli Mechanical Inc           
                                                            HVAC-02        -3,040                  07/08/21   03/16/22    Piccirilli Mechanical Inc           
 
20-1497   Reconstruction               0-001-025  06/02/21  NO CHANGE ORDERS ON ELECTRONIC FILE
21-0201   Reconstruction               0-001-026  09/29/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            WC-01          10,000                  06/13/22   03/30/23    NEP Glass CO Ltd                    
 
21-0564   Reconstruction               0-001-027  03/11/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001              0                  12/05/22   05/23/23    Schuler-Haas                        
                                                            EC-002              0                  12/05/22   05/23/23    Schuler-Haas                        
                                                            EC-003              0                  12/05/22   05/23/23    Schuler-Haas                        
                                                            EC-004              0                  12/27/22   12/14/23    Schuler-Haas                        
                                                            EC-005          4,802                  12/27/22   12/14/23    Schuler-Haas                        
                                                            EC-006         21,700                  12/27/22   12/14/23    Schuler-Haas                        
                                                            EC-007          3,617                  12/27/22   12/14/23    Schuler-Haas                        
                                                            EC-008          4,324                  06/26/23   12/29/23    SCHULER-HAAS                        
                                                            GC-001              0                  08/01/22   09/26/23    A.R Mancini                         
                                                            GC-002         -2,735                  08/01/22   09/26/23    A.R. Mancini                        
                                                            GC-003              0                  10/31/22   12/13/23    AR Mancini                          
                                                            GC-004              0                  10/31/22   12/13/23    A.R. Mancini                        
                                                            GC-005              0                  10/31/22   12/13/23    A.R Mancini                         
                                                            GC-006              0                  10/31/22   12/13/23    A.R. Mancini                        
                                                            GC-008              0                  10/31/22   12/13/23    A.R Mancini                         
                                                            GC-009              0                  12/05/22   05/23/23    AR Mancini                          
                                                            GC-010              0                  12/27/22   12/14/23    AR Mancini                          
                                                            GC-011              0                  05/01/23   12/28/23    A.R. MANCINI                        
                                                            GC-07               0                  10/31/22   12/13/23    A.R. Mancini                        
                                                            MC-001              0                  08/08/22   05/22/23    J&K Plumb                           
                                                            MC-002              0                  10/24/22   06/27/23    J&K Plumb                           
                                                            MC-003              0                  10/24/22   06/27/23    J&K Plumbing                        
                                                            MC-004         -5,831                  02/06/23   11/29/23    J&K PLUMBING                        
                                                            PC-001              0                  04/06/23     /  /      TRI-VALLEY PLUMBING AND HEATING     
                                                            PC-002         -1,213                  04/06/23   12/28/23    TRI-VALLEY PLUMBING AND HEATING     
 
21-1774   Reconstruction               0-001-028  07/25/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-1922   Reconstruction               0-001-029  05/24/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0811FP Reconstruction               0-001-FP1  06/06/03  NO CHANGE ORDERS ON ELECTRONIC FILE
03-1143SC Visual Structural Inspection 0-001-SC1  02/20/04  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Garage:
21-0565   Reconstruction               2-005-001  03/11/22  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Building:
13-0427   New Construction             2-014-001  04/14/14  NO CHANGE ORDERS ON ELECTRONIC FILE

          New Bus Garage:
10-1338   Reconstruction               5-011-002  07/12/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            P-01            3,423                  05/07/12   01/25/13    PARAGON ENVIRONMENTAL CONSTRUCTION  
                                                            P-02           -6,577                  03/30/12   08/30/12    PARAGON ENVIRONMENTAL CONSTRUCTION  
 
13-0428   Reconstruction               5-011-003  04/14/14  NO CHANGE ORDERS ON ELECTRONIC FILE
16-0310   Reconstruction               5-011-004  04/12/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-06           2,664                  11/24/17   12/15/17    Upstate Companies                   
 
16-1165   Reconstruction               5-011-005  01/23/17  NO CHANGE ORDERS ON ELECTRONIC FILE
21-0566   Reconstruction               5-011-006  03/11/22  NO CHANGE ORDERS ON ELECTRONIC FILE

          Concession Building:
13-0429   New Construction             7-013-001  04/14/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-01           -5,000                  11/18/14     /  /      NELCORP Electrical Contracting Corp.
                                                            E-02                0                  11/18/14   11/20/14    NELCORP Electrical Contracting Corp.
                                                            GC-04               0                  09/29/14   10/08/14    Bunkoff General Contractors, Inc.   
                                                            GC-12               0                  12/09/14   12/15/14    Bunkoff General Contractors, Inc.   
 

          Town Libr. Clsrm.:
21-0567   Reconstruction               8-008-002  03/11/22  NO CHANGE ORDERS ON ELECTRONIC FILE

SCHENEVUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-09-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Andrew Draper School:
01-0545   Reconstruction               0-001-006  06/18/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA2            -5,635                  02/02/04   04/07/04    Avala Contracting                   
                                                            E-6              -219                  05/17/05   07/13/05    Panko Electrical Maintenance        
                                                            GC-3             -782                  02/02/04   04/07/04    Simmons Const.                      
                                                            GC-4           17,238                  08/13/04   09/23/04    Simmons Const.                      
                                                            GC-4          -17,238                  06/22/06   07/13/06    Simmons Construction                
                                                            GC-5          -44,077                  05/18/05   07/13/05    Simmons Construction                
                                                            M-2            -3,544                  09/29/05   10/13/05    WJV Mechanical                      
                                                            P-2            13,210                  06/22/06   02/01/07    A Treffeisen and Sons               
                                                            P-3                61                  12/12/03   12/26/03    A Treffeisen & Sons                 
                                                            P2             13,210                  12/12/03   11/01/06    A Treffeisen & Sons                 
                                                            P2             13,210                  04/12/06   11/01/06    A Treffeisen and Sons               
 
00-0483   Reconstruction               0-001-007  01/24/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AE1            -3,160                  06/17/02   08/15/02    Utica Glass                         
                                                            PG1            -1,000                  11/28/01   03/27/02    RE Woodson                          
                                                            SW-1                0                  10/23/01   02/26/02    Sunrise Enterprises                 
                                                            SW2            -2,852                  11/01/02   01/08/03    Sunrise Enterprises                 
 
07-2268   Reconstruction               0-001-008  08/08/08  NO CHANGE ORDERS ON ELECTRONIC FILE
11-0485   Reconstruction               0-001-009  01/11/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            R1                  0                  05/01/12   10/05/12    JAMES A EDGAR COMPANY INC           
                                                            R2            -12,222                  07/20/12   02/19/13    JAMES A EDGAR COMPANY INC           
                                                            R3              3,257                  07/20/12   02/19/13    JAMES A EDGAR COMPANY INC           
                                                            R4            -27,765                  07/20/12   02/19/13    JAMES A EDGAR COMPANY INC           
                                                            R5              1,804                  08/09/12   12/21/12    JAMES A EDGAR COMPANY INC           
 
15-1033   Reconstruction               0-001-010  09/08/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E1                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E10                 0                  02/20/18   03/07/18    Nelcorp Electrical Contracting Corp.
                                                            E11                 0                  02/20/18   03/07/18    Nelcorp Electrical Contracting Corp.
                                                            E12                 0                  02/20/18   03/07/18    Nelcorp Electrical Contracting Corp.
                                                            E13                 0                  05/01/18   05/07/18    Nelcorp Electrical Contracting Corp.
                                                            E14                 0                  05/01/18   05/07/18    Nelcorp Electrical Contracting Corp.
                                                            E15                 0                  05/17/18   05/18/18    NELCORP ELECTRICAL CONTRACING CORP. 
                                                            E16           -12,523                  10/09/18     /  /      NELCORP ELECTRICAL CONTRACTING CORP 
                                                            E2                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E3                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E4                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E5                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E6                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E7                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E8                  0                  01/29/18   03/08/18    Nelcorp Electrical Contracting Corp.
                                                            E9                  0                  02/20/18   03/07/18    Nelcorp Electrical Contracting Corp.
                                                            GC1                 0                  05/03/17   05/12/17    Andrew R. Mancini Associates, Inc.  
                                                            GC11                0                  10/20/17   11/21/17    Andrew R. Mancini Associates, Inc.  
                                                            GC12                0                  10/20/17   11/21/17    Andrew R. Mancini Associates, Inc.  
                                                            GC13                0                  11/29/17   02/14/18    Andrew R. Mancini Associates Inc    
                                                            GC14                0                  11/29/17   02/14/18    Andrew R. Mancini Associates Inc.   
                                                            GC15                0                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC16                0                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC17                0                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC18           13,395                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC19            4,338                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC2              -274                  05/03/17   05/12/17    Andrew R. Mancini Associates, Inc.  
                                                            GC20           16,165                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC21             -966                  12/11/17   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC22           -3,668                  01/29/18   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC23             -716                  01/29/18   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC24           -2,000                  01/29/18   02/13/18    Andrew R. Mancini Associates, Inc.  
                                                            GC25           -5,000                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC26            3,944                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC27              583                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC28            1,617                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC29            2,953                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC3                 0                  06/20/17   07/14/17    Andrew R. Mancini Associates, Inc.  
                                                            GC30              478                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC31            3,709                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC32            1,332                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC33           22,077                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC34           -1,183                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC35           -4,558                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC36           -8,578                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC37            5,793                  02/20/18   02/28/18    Andrew R. Mancini Associates, Inc.  
                                                            GC38            5,723                  03/13/18   03/15/18    Andrew R. Mancini Associates, Inc.  
                                                            GC39            3,837                  03/13/18   03/15/18    Andrew R. Mancini Associates, Inc.  
                                                            GC4                 0                  07/12/17   07/14/17    Andrew R. Mancini Associates, Inc.  
                                                            GC40              360                  04/06/18   04/12/18    Andrew R. Mancini Associates        
                                                            GC41            7,572                  04/06/18   04/12/18    Andrew R. Mancini Associates, Inc.  
                                                            GC42            4,965                  04/06/18   04/12/18    Andrew R. Mancini Associates, Inc.  
                                                            GC43            2,134                  05/01/18   05/02/18    Andrew R. Mancini Associates, Inc.  
                                                            GC44           -2,500                  05/01/18   05/02/18    Andrew R. Mancini Associates, Inc.  
                                                            GC46            2,592                  05/01/18   05/02/18    Andrew R. Mancini Associates, Inc.  
                                                            GC47            1,074                  05/01/18   05/02/18    Andrew R. Mancini Associates, Inc.  
                                                            GC48           10,935                  08/30/18   09/20/18    ANDREW R. MANCINI ASSOCIATES        
                                                            GC49            7,728                  08/30/18   09/20/18    ANDREW R. MANCINI ASSOCIATES        
                                                            GC5                 0                  08/07/17   08/10/17    Andrew R. Mancini Associates, Inc.  
                                                            GC50           18,173                  08/30/18   09/20/18    ANDREW R. MANCINI ASSOCIATES        
                                                            GC51            1,781                  08/30/18   09/20/18    ANDREW R. MANCINI ASSOCIATES        
                                                            GC52          -15,000                  08/30/18   09/20/18    ANDREW R. MANCINI ASSOCIATES        
                                                            GC53            2,243                  10/16/18   11/15/18    ANDREW R MANCINI ASSOCIATES INC     
                                                            GC54            8,332                  10/16/18   11/15/18    ANDREW R. MANCINI ASSOCIATES INC    
                                                            GC6                 0                  08/07/17   09/07/17    Andrew R. Mancini Associates, Inc.  
                                                            GC7                 0                  08/07/17   08/10/17    Andrew R. Mancini Associates, Inc.  
                                                            GC8                 0                  08/21/17   09/07/17    Andrew R. Mancini Associates, Inc.  
                                                            GC9                 0                  10/13/17   10/25/17    Andrew R. Mancini Associates, Inc.  
                                                            M1                  0                  03/30/17   04/12/17    DiGesare Mechanical, Inc.           
                                                            M10                 0                  11/29/17   12/14/17    DiGesare Mechanical Inc.            
                                                            M11             6,271                  11/29/17   12/14/17    DiGesare Mechanical Inc.            
                                                            M12             4,048                  11/29/17   12/14/17    DiGesare Mechanical Inc.            
                                                            M13             2,179                  12/11/17   02/02/18    DiGesare Mechanical, Inc.           
                                                            M14               958                  12/11/17   02/02/18    DiGesare Mechanical, Inc.           
                                                            M2                  0                  03/30/17   04/12/17    DiGesare Mechanical, Inc.           
                                                            M3                  0                  05/03/17   05/10/17    DiGesare Mechanical, Inc.           
                                                            M4                  0                  05/30/17   06/26/17    DiGesare Mechanical, Inc.           
                                                            M5                  0                  06/20/17   07/14/17    DiGesare Mechanical, Inc.           
                                                            M6             -3,416                  07/12/17   07/14/17    DiGesare Mechanical, Inc.           
                                                            M8                  0                  08/07/17   09/07/17    DiGesare Mechanical, Inc.           
                                                            M9                  0                  08/07/17   09/07/17    DiGesare Mechanical, Inc.           
                                                            P1                  0                  04/19/17   04/21/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P1-revis            0                  06/19/17   07/14/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P10             1,255                  08/30/17   10/13/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P11             1,192                  09/21/17   10/12/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P12             2,631                  11/29/17   12/14/17    Tri-Valley Plumbing & Heating Inc.  
                                                            P13             2,621                  11/29/17   12/14/17    Tri-Valley Plumbing & Heating Inc.  
                                                            P14            -2,557                  03/27/18   03/28/18    Tri-Valley Plumbing & Heating, Inc. 
                                                            P2                  0                  04/19/17   04/21/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P2-revis            0                  06/19/17   07/14/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P3                  0                  06/20/17   07/14/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P4                  0                  06/20/17   07/14/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P5                  0                  06/20/17   07/14/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P6                177                  06/20/17   07/14/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P7              2,659                  08/07/17   09/07/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P8                454                  08/07/17   09/07/17    Tri-Valley Plumbing & Heating, Inc. 
                                                            P9             13,974                  08/07/17   09/07/17    Tri-Valley Plumbing & Heating, Inc. 
 
15-0817   Reconstruction               0-001-011  03/07/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA1                 0                  11/01/16     /  /      Midlanic Environmental, Inc.        
                                                            AA2           -20,387                  10/13/17   11/27/17    Midlantic Environmental, Inc.       
 
02-0200FP Reconstruction               0-001-FP1  12/19/02  NO CHANGE ORDERS ON ELECTRONIC FILE
06-0779SC Visual Structural Inspection 0-001-SC1  01/18/07  NO CHANGE ORDERS ON ELECTRONIC FILE
08-1686SC Visual Structural Inspection 0-001-SC2  06/18/09  NO CHANGE ORDERS ON ELECTRONIC FILE

          Shop Building/Bus Garage:
91-0033   Reconstruction               0-002-002  08/09/91  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0546   Reconstruction               0-002-003  06/18/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA1                 0                  04/02/03   04/21/03    Avala Contracting                   
 

          Bus Garage & Maint. Facility:
01-0547   New Construction             5-007-001  06/18/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-1                 0                  01/19/05   03/17/05    Panko Electrical Maintenance Inc    
                                                            E-2                 0                  01/19/05   03/17/05    Panko electrical Maintenance Inc    
                                                            E-3            -3,311                  01/19/05   03/17/05    Panko Electrical Maintenance Inc    
                                                            E-4                 0                  01/19/05   03/17/05    Panko Electrical Maintenance        
                                                            E-5             5,867                  05/17/05   07/14/05    Panko Electrical Maintenance        
                                                            E-8             3,441                  05/17/05   07/13/05    Panko Electrical Maintence          
                                                            E7             -1,036                  05/17/05   07/14/05    Panko electrical Maintenance        
                                                            GC-1            1,400                  01/23/04   03/08/04    Simmons Const.                      
                                                            GC-2           -5,616                  02/02/04   04/07/04    Simmons Const.                      
                                                            M1              2,273                  09/28/05   10/13/05    WJV mechanical                      
                                                            P-1            -6,300                  12/12/03   04/19/04    A Treffeisen & Sons                 
                                                            P-4           -10,760                  02/02/04   03/05/04    A Treffeisen & Sons                 
                                                            P5              2,487                  04/04/04   05/11/04    A Treffeisen & Sons                 
 
15-1034   Reconstruction               5-007-003  09/08/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC45           -3,500                  05/01/18   05/02/18    Andrew R. Mancini Associates, Inc.  
                                                            M7             -3,416                  07/12/17   07/14/17    DiGesare Mechanical, Inc.           
 

          Hogan Bus Garage Building:
02-0240   Reconstruction               5-008-L01  09/18/02  NO CHANGE ORDERS ON ELECTRONIC FILE

MILFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-11-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Milford Central School:
00-0549   Additions and Alterations    0-010-004  03/13/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1                   0                  12/20/01     /  /      Court Street Co.                    
                                                            1              54,780                  12/20/01   03/26/02    Court Street Co.                    
                                                            1              -3,485                  01/17/02   03/25/02    Bagnall Elec.                       
                                                            1              -2,500                  08/30/02   09/04/02    Auchinachie Plumbing                
                                                            1               2,800                  12/03/01   01/14/03    Auchinachie Plumbing                
                                                            2              13,300                  12/11/01   03/01/02    Auchinachie Plumbing                
                                                            2               1,975                  02/13/02   03/25/02    Auchinachie Plumbing                
                                                            2               2,225                  02/13/02   03/25/02    Bagnall Elec.                       
                                                            2              18,982                  08/07/02   08/16/02    Court Street Co.                    
                                                            3                 616                  05/09/02   06/04/02    Bagnall Elec.                       
                                                            3               6,799                  08/07/02   08/16/02    Auchinachie Plumbng                 
                                                            4               1,245                  08/07/02   08/16/02    Bagnall Elec.                       
                                                            5               1,135                  08/27/02   09/05/02    Bagnell Elec.                       
 
05-0707   Additions and Alterations    0-010-005  05/30/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            1               6,029                  01/16/07   02/12/07    Nelcorp Electrical                  
                                                            1              10,185                  01/16/07   02/21/07    W and D Smith and Sons              
                                                            1              49,407                  04/17/07   05/09/07    Puterlo Construction                
                                                            1               2,286                  11/28/07     /  /      Piccirlli slavik & vincent plumbing 
                                                            1               2,286                  11/28/07   01/28/08    Piccirilli slavik &vincent plumbing 
                                                            2              18,260                  04/17/07   05/25/07    Nelcorp Electrical                  
                                                            2               8,099                  04/17/07   05/09/07    Puterlo Construction                
                                                            2              14,213                  07/19/07   08/07/07    Henderson Johnson Co                
                                                            3               2,105                  04/17/07   05/25/07    Nelcorp electrical                  
                                                            3              14,031                  07/19/07   08/07/07    Puterlo Construction                
                                                            3               3,201                  11/28/07   12/14/07    Henderson-Johnson Company           
                                                            4               8,380                  07/19/07   10/23/07    Nelcorp Electrical                  
                                                            Roof 1         10,803                  01/16/07   02/21/07    Henderson Johnson                   
 
07-2079   Reconstruction               0-010-006  05/05/08  NO CHANGE ORDERS ON ELECTRONIC FILE
11-0405   Additions and Alterations    0-010-007  01/13/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC - 01        35,574                  10/16/12   02/11/13    Schuler - Haas Electric Corp.       
                                                            GC - 02        15,593                  10/16/12   12/04/12    Munane Building Contractors, Inc.   
                                                            GC-1            7,678                  07/19/12   02/25/13    MURNANE BUILDING CONTRACTORS INC    
                                                            GC-3           44,286                  12/04/12   03/04/13    MURNANE BUILDING CONTRACTORS INC    
                                                            GC-4           67,069                  02/06/13   07/03/13    MURNANE BUILDING CONTRACTORS INC    
                                                            HVAC-01        -3,265                  10/02/14   10/08/14    RF Gordon Mechanical LLC            
                                                            MC - 1              0                  10/16/12   02/11/13    Brosh Mechancial, Inc.              
                                                            MC-2           15,034                  12/31/12   08/12/13    Brosh Mechanical, Inc.              
 
08-1676   Reconstruction               0-010-008  09/18/09  NO CHANGE ORDERS ON ELECTRONIC FILE
10-0452   Reconstruction               0-010-009  03/15/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              13,460                  09/13/11   12/14/11    EPERGY LLC                          
 
13-0819   Reconstruction               0-010-010  04/11/13  NO CHANGE ORDERS ON ELECTRONIC FILE
18-0658   Reconstruction               0-010-011  11/30/18  NO CHANGE ORDERS ON ELECTRONIC FILE
19-0387   Reconstruction               0-010-013  01/07/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001            14,084                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            002            18,875                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            003            19,040                  02/10/21   04/08/21    TMI MECHANICAL                      
                                                            004            24,291                  02/10/21   04/08/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            005            16,422                  02/10/21   04/08/21    A. TREFFEISEN & SONS                
                                                            006             4,313                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            007             7,645                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            008             4,530                  02/10/21   05/25/21    MURNANE BUILDING CONTRATORS         
                                                            009             6,357                  02/10/21   05/25/21    MURNANE BUILDING CONTRATORS         
                                                            010             2,960                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            011             2,152                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            012             2,788                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            013             9,481                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            014             2,167                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            015             7,623                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            016             7,687                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            017               437                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            018             6,298                  02/10/21   05/25/21    MURNANE BUILDING CONTRACTORS        
                                                            019             1,806                  02/10/21   04/08/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            021            -1,750                  04/14/21     /  /      A. TREFFEISEN & SONS                
                                                            021            -1,750                  04/19/21   07/29/21    A. TREFFEISEN & SONS                
                                                            022               377                  12/23/21   12/27/22    Murnane Bldg Contr                  
 
19-0589   Reconstruction               0-010-014  12/20/19  NO CHANGE ORDERS ON ELECTRONIC FILE
20-1853   Reconstruction               0-010-015  07/26/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            GC-01         -10,699                  01/04/23   04/20/23    Murnane Bldg Contrs                 
                                                            GC-02          -4,500                  05/31/23   01/02/24    MURNANE BUILDING                    
 
21-2015   Reconstruction               0-010-016  08/03/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001          2,000                  06/27/23     /  /      NEP GLASS CO                        
 
06-0862SC Visual Structural Inspection 0-010-SC1  02/06/07  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage:
05-0708   Additions and Alterations    5-009-001  05/30/06  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0205   Reconstruction               5-009-002  01/09/07  NO CHANGE ORDERS ON ELECTRONIC FILE
16-0813   Reconstruction               5-009-003  12/03/15  NO CHANGE ORDERS ON ELECTRONIC FILE

MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-12-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Morris Central School:
92-1366   Additions and Alterations    0-001-004  07/26/93  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0163   Reconstruction               0-001-005  09/04/98  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1562   Additions and Alterations    0-001-006  11/15/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              74,519                  05/23/02   10/30/02    Marcy Excavation Company            
                                                            1              18,900                  05/23/02   07/30/02    Murnane Building Contractors        
                                                            10-1            6,112                  10/07/02   11/08/02    Facilities Equipment                
                                                            10-2           -3,400                  10/28/02   11/08/02    Facilities Equipment                
                                                            11-1          -69,302                  05/23/02   07/12/02    E&B Equipment                       
                                                            11-2            6,904                  05/23/02   07/12/02    E&B Equipment                       
                                                            11-3            2,939                  07/08/03   07/15/03    E&B Equipment                       
                                                            11-4            1,853                  09/11/02   10/30/02    E&B Equipment                       
                                                            11-5              106                  09/27/02   02/17/04    E&B Equipment                       
                                                            11-6            5,164                  12/30/02   01/08/03    E&B Equipment                       
                                                            12-1            2,272                  05/23/02   07/12/02    Buffalo Hotel Supply                
                                                            12-2            1,110                  05/23/02   07/12/02    Buffalo Hotel Supply                
                                                            12-3            1,270                  05/23/02   07/12/02    Buffalo Hotel Supply                
                                                            12-4            2,035                  05/23/02   07/12/02    Buffalo Hotel Supply                
                                                            13-1           56,700                  05/23/02   08/16/02    Henderson-Johnson                   
                                                            13-2            4,405                  05/23/02   03/28/03    Henderson-Johnson                   
                                                            13-3            7,560                  05/23/02   08/16/02    Henderson-Johnson                   
                                                            13-4            2,220                  07/31/02   08/16/02    Star Northeast                      
                                                            13-5            3,518                  07/08/03   07/15/03    Henderson-Johnson                   
                                                            13-6           12,150                  09/09/02   02/05/03    Henderson-Johnson                   
                                                            13-7             -350                  09/27/02   02/17/04    Henderson-Johnson                   
                                                            14-1           28,900                  05/23/02   07/12/02    KSP Painting                        
                                                            14-2           15,500          15,500  07/08/03   07/15/03    KSP Painting                        
                                                            14-3            8,960                  09/11/02   10/30/02    KSP Painting                        
                                                            14-4            4,060                  12/30/02   01/08/03    KSP Painting                        
                                                            14-5           -1,000                  01/31/03   02/26/03    KSP Painting                        
                                                            15-1            6,800                  07/08/03   07/15/03    Piccirilli-Slavik                   
                                                            15-2            5,314                  09/16/02   10/30/02    Piccirilli-Slavik                   
                                                            15-3             -290                  09/27/02   02/17/04    Piccirilli-Slavik                   
                                                            16-1           11,821                  05/23/02   06/13/02    M&N Plumbing                        
                                                            16-3           39,041                  09/09/02   10/30/02    M&N Plumbing                        
                                                            16-4           47,662                  10/07/02   11/08/02    M&N Plumbing                        
                                                            16-5            4,102                  01/22/03   02/06/03    M&N Plumbing                        
                                                            16-6            3,138                  01/31/03   02/11/03    M&N Plumbing                        
                                                            16-9            3,071                  02/28/03   03/11/03    M&N Plumbing                        
                                                            17-1            6,636                  05/23/02   07/10/02    Matco Elec.                         
                                                            17-2           33,229                  07/08/03   07/15/03    Matco Elec.                         
                                                            17-4           27,405                  12/30/02   01/08/03    Matco Elec.                         
                                                            18-1            1,000                  05/23/02   07/10/02    Old Castle Precast                  
                                                            19-1           -9,968                  05/23/02   08/16/02    Kelley Brothers                     
                                                            19-2            1,870                  05/23/02   10/21/02    Kelley Brothers                     
                                                            19-3              885                  07/08/03   07/15/03    Kelley Brothers                     
                                                            19-4             -876                  09/27/02   02/17/04    Kelley Brothers                     
                                                            2              33,038                  05/23/02   10/30/02    Marcy Excavation Company            
                                                            2              -3,000                  05/05/03   06/09/03    STS Steel                           
                                                            2-3            -4,177                  05/23/02   07/30/02    Murnane Bldg. Contractors           
                                                            2-5             1,661                  09/05/02   09/06/02    Murnane Bldg. Contractors           
                                                            3             118,223                  05/23/02   10/30/02    Marcy Excavation Company            
                                                            3-1             1,242                  05/23/02   07/10/02    Raulli & Sons                       
                                                            3-2             2,898                  05/23/02   07/10/02    Raulli & Sons                       
                                                            3-3             3,473                  07/08/03   07/15/03    Raulli & Sons                       
                                                            3-4               851                  07/08/03   07/15/03    Raulli & Sons                       
                                                            4              90,176                  05/23/02   02/05/03    Marcy Excavation Company            
                                                            4-1            25,330                  05/23/02   07/10/02    Hopkins and Reilly Mason            
                                                            4-2            13,337                  09/09/02   10/30/02    Hopkins and Reilly Mason            
                                                            5               1,950                  09/11/02   10/30/02    Marcy Excavation Company            
                                                            5-1          -314,537                  05/23/02   07/12/02    Murnane Bldg. Contractors           
                                                            5-2             1,839                  05/23/02   07/24/02    Murnane Bldg. Contractors           
                                                            5-3             1,787                  05/23/02   09/15/04    Murnane Bldg. Contractors           
                                                            5-4            12,128                  05/23/02   07/30/02    Murnane Bldg. Contractors           
                                                            5-5             4,336                  07/08/03   07/15/03    Murnane Bldg. Contractors           
                                                            5-6             8,886                  09/16/02   02/05/03    Murnane Bldg. Contractors           
                                                            5-7            10,952                  12/30/02   01/08/03    Murnane Bldg. Contractors           
                                                            5-8            -2,000                  01/31/03   02/26/03    Murnane Bldg. Contractors           
                                                            6              31,273                  02/28/03   03/11/03    Marcy Excavation Company            
                                                            6-1           -10,000                  05/23/02   06/13/02    Dewald Roofing                      
                                                            6-2              -330                  05/23/02   06/13/02    Dewald Roofing                      
                                                            6-3            13,337                  07/08/03   07/15/03    Dewald Roofing                      
                                                            6-4            12,420                  07/08/03   07/15/03    Dewald Roofing                      
                                                            6-5            23,380                  07/08/03   07/15/03    Dewald Roofing                      
                                                            6-6             7,700                  09/27/02   02/17/04    Dewald Roofing                      
                                                            6-7            19,200                  09/09/02   10/30/02    Dewald Roofing                      
                                                            6-8               550                  06/03/03   06/09/03    Dewald Roofing                      
                                                            7-1            -2,400                  05/23/02   07/24/02    Johnson-Howard Associates           
                                                            7-2           -14,230                  05/23/02   07/24/02    Johnson-Howard Associates           
                                                            7-3             7,500                  09/09/02   02/05/03    Johnson-Howard Associates           
                                                            7-4              -290                  09/27/02   10/30/02    Johnson-Howard Associates           
                                                            8-1            10,683                  09/27/02   02/17/04    Brownies, Inc                       
                                                            8-2              -100                  09/27/02   02/17/04    Brownies, Inc                       
                                                            9-1            -4,600                  05/23/02   06/13/02    Western NY Floor Co                 
                                                            9-2             8,878                  09/11/02   10/30/02    Western NY Floor Co.                
                                                            9-3             5,648                  10/18/02   11/08/02    Western NY Floor Co                 
 
00-1581SR Additions and Alterations    0-001-006  04/13/01  NO CHANGE ORDERS ON ELECTRONIC FILE
05-1260   Reconstruction               0-001-008  07/19/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HVAC-001       -3,200                  06/25/08   08/18/08    Louis N. Picciano & Son, Inc.       
 
12-0474   Reconstruction               0-001-010  07/25/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            EC-001         21,575                  06/09/14   07/10/14    Blanding Electric, Inc.             
                                                            EC-002         14,556                  09/29/14   10/08/14    Blanding Electric Inc.              
                                                            EC-003           -820                  11/06/14   11/24/14    Blanding Electric Inc.              
                                                            EC-004           -773                  02/25/15   03/18/15    Blanding Electric Inc.              
                                                            GC-001         60,934                  01/06/14   01/31/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-002          4,300                  01/27/14   02/21/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-003           -366                  01/27/14   02/21/14    G.M. Crissalli & Associates, Inc.   
                                                            GC-004         19,941                  02/03/14   03/21/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-005         19,884                  02/03/14   03/21/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-006         -5,180                  02/07/14   03/21/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-007          4,199                  02/07/14   03/21/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-008          5,751                  03/17/14   04/15/14    G.M. Crisalli & Assocaites, Inc.    
                                                            GC-009          5,543                  03/17/14   04/15/14    G.M. Crisalli & Assiciates, Inc.    
                                                            GC-010          2,881                  03/31/14   07/03/14    G.M. Crisalli Associates, Inc.      
                                                            GC-011         14,739                  03/31/14   07/03/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-012          6,480                  04/11/14   05/02/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-013         20,026                  04/11/14   05/02/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-014          4,140                  04/11/14   05/02/14    G.M. Crisalli & Assoiates, Inc.     
                                                            GC-015           -917                  04/11/14   05/02/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-016            -55                  06/02/14   06/27/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-017         22,295                  06/02/14   06/27/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-018           -900                  06/24/14   08/28/14    G.M. Crisalli & Associates, Inc.    
                                                            GC-019         -1,640                  01/08/15   01/29/15    GM Crisalli & Assocaites, Inc.      
                                                            HVAC-001       -4,000                  01/16/14   07/24/14    H.J. Bradeles Corp.                 
                                                            HVAC-002      -13,173                  03/31/14   07/03/14    H.J. Brandeles Corp.                
                                                            HVAC-003        1,844                  04/14/14   05/02/14    H.J. Brandeles Corp.                
                                                            HVAC-004       -1,131                  01/08/15     /  /      HJ Brandeles Corp.                  
                                                            MC-001         17,098                  01/06/14   01/31/14    Lupini Construction Inc             
                                                            MC-002         16,610                  05/01/14   05/15/14    Lupini Construction Inc             
                                                            MC-003          4,208                  06/09/14   07/10/14    Lupini Construction Inc             
                                                            MC-004         15,686                  06/09/14   07/10/14    Lupini Construction Inc             
                                                            MC-005              0                  08/25/14   10/03/14    Lupini Construction Inc             
                                                            MC-006         38,000                  09/24/14   09/26/14    Lupini Construction Inc.            
                                                            PC-001         -3,000                  12/18/14   12/30/14    H.J. Brandeles Corp.                
 
16-1912   Reconstruction               0-001-011  03/23/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            1-01           -3,938                  01/17/19   02/11/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-02           -1,025                  01/17/19   02/11/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-04              480                  04/02/19   04/05/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-05            7,267                  03/04/19   03/14/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-06             -700                  06/21/19   07/05/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-07           -1,843                  06/21/19   07/05/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-10           -3,810                  06/21/19   07/05/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-11            5,286                  07/09/19   08/12/19    NATIONAL BUILDING & RESTORATION CORP
                                                            100-04         -2,169                  09/18/18   09/27/18    NATIONAL BUILDING & RESTORATION     
                                                            100-05         -4,925                  09/18/18   09/27/18    NATIONAL BUILDING & RESTORATION     
                                                            100-07              0                  10/30/18   12/11/18    NATIONAL BUILDING & RESTORATION     
                                                            100-08              0                  11/20/18   01/24/19    NATIONAL BUILDING & RESTORATION     
                                                            100-09              0                  11/20/18   01/24/19    NATIONAL BUILDING & RESTORATION     
                                                            100-1               0                  07/25/19   08/13/19    NATIONAL BUILDING & RESTORATION     
                                                            100-2          -1,145                  09/13/18   10/01/18    NATIONAL BUILDING & RESTORATION     
                                                            100-3         -10,471                  09/13/18   10/01/18    NATIONAL BUILDING & RESTORATION     
                                                            2-02            5,665                  01/17/19   02/25/19    LOUIS N. PICCIANO & SON, INC.       
                                                            2-03              632                  03/04/19   03/07/19    LOUIS N. PICCIANO & SON, INC.       
                                                            2-06           16,243                  04/02/19   04/02/19    LOUIS N. PICCIANO & SON, INC.       
                                                            2-07            3,877                  04/02/19   04/02/19    LOUIS N. PICCIANO & SON, INC.       
                                                            200-01         -5,123                  08/10/18   08/28/18    LOUIS N PICCIANO & SON INC          
                                                            200-03         -1,367                  09/18/18   10/15/18    LOUIS N PICCIANO & SON INC          
                                                            200-04         -2,163                  09/18/18   10/15/18    LOUIS N PICCIANO & SON INC          
                                                            200-06              0                  11/20/18   01/07/19    LOUIS N. PICCIANO & SON, INC.       
                                                            4-01            7,813                  08/10/18   08/28/18    S.C SPENCER ELECTRIC INC            
                                                            4-02            6,346                  10/30/18   11/30/18    S.C SPENCER ELECTRIC INC            
                                                            4-03              361                  01/17/19   02/25/19    S.C. SPENCER ELECTRIC, INC.         
                                                            4-05            1,264                  02/11/19   02/28/19    S.C. SPENCER ELECTRIC,INC.          
                                                            4-06              -25                  02/11/19   02/28/19    S.C. SPENCER ELECTRIC,INC.          
                                                            400-03              0                  11/20/18   01/07/19    S.C. SPENCER ELECTRIC, INC.         
                                                            400-04              0                  11/20/18   01/07/19    S.C. SPENCER ELECTRIC, INC.         
                                                            400-05              0                  11/20/18   01/07/19    S.C. SPENCER ELECTRIC, INC.         
 
18-2056   Reconstruction               0-001-012  06/27/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -34,000                  11/13/19   01/17/20    MURNANE BUILDING CONTRACTORS, INC.  
                                                            1-02            3,948                  11/25/20   05/07/21    MURNANE BUILDING CONTRACTORS, INC.  
                                                            1-03          -16,755                  11/25/20   05/07/21    MURNANE BUILDING CONTRACTORS, INC.  
                                                            1-04           -1,637                  11/25/20   05/07/21    MURNANE BUILDING CONTRACTORS, INC.  
                                                            1-05           -3,435                  11/25/20   05/07/21    MURNANE BUILDING CONTRACTORS, INC.  
                                                            100-01              0                  03/27/20   07/22/20    MURNANE BUILDING CONTRACTORS, INC.  
 
21-0570   Reconstruction               0-001-013  01/24/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -2,331                  09/07/22   08/22/23    Murnane Bldg Contrs Inc             
                                                            1-02           -4,361                  09/07/22   08/22/23    Murnane Bldg Contrs Inc             
                                                            101-01              0                  09/07/22   08/22/23    Murnane Bldg Contrs Inc             
 
22-0538   Reconstruction               0-001-014  12/23/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -10,000                  04/25/23   01/08/24    MURNANE BUILDING CONTRACTORS        
                                                            1-02          -23,500                  04/25/23   01/08/24    MURNANE BUILDING CONTRACTORS        
                                                            1-03           -1,680                  04/25/23   01/08/24    MURNANE BUILDING CONTRACTORS        
                                                            101-01              0                  04/25/23   01/08/24    MURNANE BUILDING CONTRACTORS        
 

          Custodial/Mntenance(HseBoilerFor0001:
92-1367   Reconstruction               0-002-002  07/26/93  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1563   Reconstruction               0-002-003  11/15/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            16-2            3,000                  07/08/03   07/15/03    M&N Plumbing                        
                                                            16-7           27,834                  01/31/03   02/11/03    M&N Plumbing                        
                                                            16-8            6,122                  01/31/03   02/11/03    M&N Plumbing                        
                                                            17-3            1,195                  12/30/02   01/08/03    Matco Elec.                         
                                                            2-2               556                  05/23/02   06/04/02    Murnane Bldg. Contractors           
                                                            2-4               626                  05/23/02   06/04/02    Murnane Bldg. Contractors           
 
05-1261   Reconstruction               0-002-004  07/19/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001         -14,275                  06/25/08   08/26/08    Dewald Roofing                      
                                                            1-002           1,325                  06/25/08   08/26/08    Dewald Roofing                      
 
12-0475   Reconstruction               0-002-006  07/25/13  NO CHANGE ORDERS ON ELECTRONIC FILE
16-1913   Reconstruction               0-002-008  03/23/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-03              263                  01/17/19   02/11/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-08              799                  06/21/19   07/05/19    NATIONAL BUILDING & RESTORATION CORP
                                                            1-09              -54                  06/21/19   07/05/19    NATIONAL BUILDING & RESTORATION CORP
                                                            100-06         -2,199                  10/05/18   10/15/18    NATIONAL BUILDING & RESTORATION     
                                                            100-10              0                  11/20/18   01/15/19    NATIONAL BUILDING & RESTORATION     
                                                            100-11              0                  12/04/18     /  /      NATIONAL BUILDING & RESTORATION     
                                                            2-01            4,903                  01/17/19   02/25/19    LOUIS N. PICCIANO & SON, INC.       
                                                            2-04               75                  03/04/19   03/08/19    LOUIS N. PICCIANO & SON, INC.       
                                                            2-05            4,866                  04/02/19   04/02/19    LOUISE N. PICCIANO & SON,INC.       
                                                            200-02         -3,312                  08/27/18   09/12/18    LOUIS N. PICCIANO & SON INC         
                                                            4-04              456                  02/11/19     /  /      S.C. SPENCER ELECTRIC,INC.          
                                                            400-01              0                  07/25/19   07/29/19    S.C. SPENCER ELECTRIC, INC.         
                                                            400-02           -926                  09/18/18   10/15/18    S.C. SPENCER ELECTRIC INC           
                                                            E00-005Q       -5,329                  09/18/18   10/15/18    LOUIS N PICCIANO & SON INC          
 
21-0571   Reconstruction               0-002-009  01/24/22  NO CHANGE ORDERS ON ELECTRONIC FILE

          Morris Existing Bus Garage:
92-1368   Reconstruction               5-005-003  07/26/93  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1564   Additions and Alterations    5-005-004  11/15/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1               3,500                  05/23/02   06/04/02    STS Steel, Inc                      
 
13-0508   Reconstruction               5-005-007  09/26/13  NO CHANGE ORDERS ON ELECTRONIC FILE

          District-Wide:
17-1437   Reconstruction               7-999-001  05/16/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01              401                  02/04/21   03/26/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            1-02            3,917                  02/04/21   03/26/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            1-03              790                  02/04/21   03/26/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            1-04            1,320                  04/15/21   07/15/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            100-01              0                  02/04/21   03/30/21    SCHULER-HAAS ELECTRIC CORP.         
                                                            100-02              0                  02/04/21   03/30/21    SCHULER-HAAS ELECTRIC CORP.         
 

ONEONTA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-14-00-01
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Valley View Elementary:
01-0604   Reconstruction               0-004-003  07/12/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ETC-005        -7,788                  06/22/07   10/23/07    Blanding Electric                   
                                                            ETC-04          7,011                  01/08/07   01/24/07    Blanding Electric                   
 
01-0357   Reconstruction               0-004-004  01/08/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA1            -2,000                  11/21/02   11/22/02    USA Remediation                     
                                                            GC-1           -5,197                  11/21/02   11/22/02    Eastman Assoc.                      
                                                            GC-2              250                  04/21/03   05/07/03    Eastman Assoc.                      
                                                            SC-1            5,392                  11/21/02   11/22/02    Eastman Assoc.                      
 
03-0728   Reconstruction               0-004-005  04/25/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-001         5,084                  10/05/04   10/12/04    Two Brothers Contracting            
                                                            AAC-004        13,600                  09/01/05   09/09/05    Two Brother Contracting             
                                                            EC-004          1,230                  09/07/06   12/27/06    Blanding ELectric                   
                                                            GC-17           9,893                  10/13/05   11/08/05    Fahs Rolston paving Corp            
                                                            GC-30          62,945                  12/30/05   06/09/06    Fahs Rolston Paving Corp            
                                                            GC-33          -2,112                  04/13/06   06/23/06    Fahs Rolston Paving                 
                                                            HC-001         11,312                  09/10/04   09/23/04    Louis Picciano and Son              
                                                            HC-008         -3,034                  03/07/06   06/23/06    Louis Piccano and Sons              
                                                            RC-001         14,355                  09/10/04   10/22/04    DeWald Roofing                      
 
05-0922   Reconstruction               0-004-006  08/24/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC - 01R        5,069                  09/25/07   10/18/07    CHRISTA CONSTRUCTION, LLC.          
 
07-1205   Reconstruction               0-004-007  06/27/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-06          4,351                  03/17/11   05/20/11    KASCON LLC                          
                                                            AAC-12            -81                  10/17/11   12/12/11    KASCON LLC                          
                                                            CC-01          -1,150                  09/01/10   09/30/10    NORTHEAST INTERIOR SYSTEMS INC      
                                                            CC-02           2,382                  12/17/10   01/06/11    NORTHEAST INTERIOR SYSTEMS INC      
                                                            EC-01            -509                  12/09/09   01/25/10    MATCO ELECTRIC CORP                 
                                                            EC-03           9,043                  12/17/10   01/06/11    MATCO ELECTRIC CORP                 
                                                            EC-04           1,338                  02/02/11   03/10/11    MATCO ELECTRIC CORP                 
                                                            EC-07             669                  04/06/11   05/13/11    MATCO ELECTRIC CORP                 
                                                            EC-08           2,331                  04/22/11   05/13/11    MATCO ELECTRIC CORP                 
                                                            EC-13               0                  08/31/11   02/13/12    MATCO ELECTRIC CORP                 
                                                            GC-04          -3,735                  06/03/10   08/04/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-14           7,256                  09/01/10   09/30/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-15          -1,888                  09/01/10   09/30/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-16           5,079                  02/17/11   03/11/11    FE JONES CONSTRUCTION INC           
                                                            GC-17          -6,407                  02/17/11   03/14/11    FE JONES CONSTRUCTION INC           
                                                            GC-21             715                  06/24/11   08/05/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-22           3,840                  08/31/11   10/03/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-30            -182                  12/21/11   06/22/12    F.E. JONES CONSTRUCTION INC         
                                                            HVAC-03         1,094           1,094  08/31/11   Disapproved LOUIS N PICCIANO & SON INC          
                                                            HVAC-08          -616                  07/14/11   09/08/11    LOUIS N PICCIANO & SON INC          
                                                            PC-08          -3,277                  07/14/11   08/05/11    LOUIS N PICCIANO & SON INC          
                                                            SC-10          -2,278                  08/31/11   10/03/11    CLARK COMPANY                       
 
12-0608   Reconstruction               0-004-008  12/29/12  NO CHANGE ORDERS ON ELECTRONIC FILE
12-1325   Reconstruction               0-004-009  12/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-08          -9,876                  01/20/15   01/23/15    Schuler Haas Electric Corp.         
                                                            EC-20             236                  05/01/15   05/13/15    Schuler Haas Electric Corp          
                                                            GC-02          25,153                  09/29/14   10/08/14    Andrew R. Mancini Associates, Inc.  
                                                            GC-08           8,770                  02/17/15   02/18/15    Andrew R. Mancini Associates, Inc.  
                                                            GC-10            -236                  05/01/15   05/13/15    Andrew R. Mancini Associates Inc.   
                                                            GC-12               0                  05/01/15   05/13/15    Andrew R. Mancini Associates, Inc.  
                                                            HC-02           9,790                  02/17/15   02/18/15    J&K Plumbing and Heating Co., Inc.  
                                                            HC-03               0                  03/19/15   04/01/15    J&K Plumbing and Heating Co., Inc.  
 
17-0815   Reconstruction               0-004-010  05/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-2           -4,506                  09/21/18   10/22/18    BLANDING ELECTRIC                   
                                                            GC-010          3,764                  07/22/19   07/24/19    EASRMAN ASSOCIATES INC.             
                                                            GC-016          2,040                  06/12/20   08/06/20    Eastman Associates                  
                                                            GC-2           18,960                  09/21/18   10/22/18    EASTMAN ASSOCIATES                  
 
17-0804   Reconstruction               0-004-011  09/24/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1824   Reconstruction               0-004-012  11/08/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-009            756                  11/02/21   12/09/22    Blanding Electric, Inc              
                                                            GC-009          1,999                  02/18/20   06/04/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-011          6,281                  02/18/20   06/09/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-016         22,007                  03/13/20   07/14/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-038          4,116                  11/02/21   12/07/22    Andrew Mancini Associates, Inc      
                                                            GC-045            743                  12/20/21   01/24/23    Andrew Mancini Assocs Inc           
                                                            PC-011            878                  08/11/21   04/21/22    PICCIRILLI-SLAVIK-VINCENT PLUMB&HEAT
                                                            PC-07           5,277                  06/26/20   08/03/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
 
20-0272   Reconstruction               0-004-013  10/01/20  NO CHANGE ORDERS ON ELECTRONIC FILE

          Center Street Elementary:
92-1419   Reconstruction               0-006-003  07/21/93  NO CHANGE ORDERS ON ELECTRONIC FILE
96-0917   Reconstruction               0-006-004  03/28/97  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0094   Reconstruction               0-006-005  11/03/99  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0605   Reconstruction               0-006-006  07/12/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ETC-001         8,124                  01/08/07   01/24/07    Blanding Electric                   
                                                            ETC-1          11,800                  09/15/03   09/19/03    Blanding Electric                   
                                                            ETC2A          -9,350                  01/20/04   02/03/04    Blanding Electric                   
 
02-2058   Reconstruction               0-006-008  09/12/03  NO CHANGE ORDERS ON ELECTRONIC FILE
03-0729   Reconstruction               0-006-009  04/25/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-18           4,172                  10/13/05   11/08/05    fahs rolston Paving                 
                                                            GC-28           2,974                  12/23/05   06/09/06    Fahs Rolston Paving Corp            
                                                            GC-34          -2,500                  03/24/06   06/05/06    Fahs rolston Paving                 
                                                            HC-010          2,431                  09/28/06   01/09/07    Louis Picciano and sons             
                                                            PC-001          6,729                  03/24/06   06/23/06    Louis Piccano and Sons              
                                                            RC-005          1,963                  12/23/05   06/09/06    DeWald Roofing Co                   
 
05-0923   Reconstruction               0-006-010  08/24/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-005           -500                  07/02/08   10/07/08    CHRISTA CONSTRUCTION, LLC           
 
07-1206   Reconstruction               0-006-011  06/27/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-03         -9,394                  01/21/10   03/05/10    KASCON LLC                          
                                                            AAC-07            105                  03/17/11   05/20/11    KASCON LLC                          
                                                            AAC-09           -232                  10/17/11   12/28/11    KASCON LLC                          
                                                            EC-01            -426                  12/09/09   01/25/10    MATCO ELECTRIC CORP                 
                                                            EC-10               0                  08/31/11   02/13/12    MATCO ELECTRIC CORP                 
                                                            GC-04          -1,868                  06/03/10   08/04/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-07        -212,644                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-12          31,201                  11/12/09   12/23/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-27            -224                  12/21/11   06/22/12    F.E. JONES CONSTRUCTION INC         
                                                            HVAC-01         8,690                  01/21/10   03/05/10    LOUIS N. PICCIANO & SON INC         
                                                            HVAC-05        -1,694                  07/14/11   09/08/11    LOUIS N PICCIANO & SON INC          
                                                            PC-01            -623                  10/19/09   11/12/09    LOUIS N. PICCIANO & SON INC         
                                                            PC-02             703                  01/21/10   03/05/10    LOUIS N. PICCIANO & SON INC         
                                                            PC-05          -1,405                  07/14/11   08/05/11    LOUIS N PICCIANO & SON INC          
                                                            SC-07          -1,953                  08/31/11   10/03/11    CLARK COMPANIES                     
 
12-1326   Reconstruction               0-006-012  12/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-04           3,655                  12/16/14   12/30/14    Schuler Haas Electric Corp.         
                                                            EC-10             992                  01/20/15   01/23/15    Schuler Haas Electric Corp.         
 
02-0640FP Reconstruction               0-006-FP1  12/06/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Middle/High School:
94-0387   Reconstruction               0-014-005  11/23/94  NO CHANGE ORDERS ON ELECTRONIC FILE
95-0153   Additions and Alterations    0-014-006  10/16/95  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0202   Reconstruction               0-014-007  08/26/93  NO CHANGE ORDERS ON ELECTRONIC FILE
95-1027   Reconstruction               0-014-008  05/14/96  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1393   Reconstruction               0-014-009  05/06/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0942   Reconstruction               0-014-010  03/31/99  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0095   Reconstruction               0-014-011  11/03/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-0416   Reconstruction               0-014-012  01/23/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC2 rev       -4,404                  11/21/01   05/28/02    Sunstream                           
                                                            BC1            23,748                  11/16/01   05/28/02    Dant-Clayton                        
                                                            GC-1rev         7,574                  09/28/01   05/22/02    Jones-Marinich                      
                                                            GC-2rev         2,056                  09/28/01   05/22/02    Jones-Marinich                      
                                                            GC-3           -2,393                  09/01/05   09/07/05    Jones Marinich Inc                  
                                                            SC-1           19,500                  12/10/01   05/28/02    Orchard Earth & Pipe                
 
03-0595   Reconstruction               0-014-014  03/15/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001            18,000                  10/21/04   11/03/04    Clark Companies                     
                                                            EC-001          3,144                  01/21/05   02/07/05    Nelcorp Electrical Contracting      
                                                            GC-002          4,150                  12/24/04   01/03/05    Clark Companies                     
                                                            GC-003          4,378                  06/14/05   06/29/05    Clark Companies                     
                                                            GC-004         10,500                  03/17/06   07/14/06    Clark Companies                     
 
03-0730   Reconstruction               0-014-015  04/25/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0               3    /  /       /  /                                          
                                                            AAC-005        -3,600                  03/24/06   06/05/06    two brothers Contracting            
                                                            EC-001          3,945                  07/25/05   07/26/05    Blanding Electric                   
                                                            EC-002          7,953                  02/13/06   08/09/06    Blanding Electric                   
                                                            EC-005          4,778                  09/07/06   12/27/06    Blanding Electric                   
                                                            GC-12           7,683                  06/28/05   07/21/05    Fahs Rolston Paving                 
                                                            GC-14          69,057                  07/25/05   08/10/05    Fahs Rolston Paving Corp            
                                                            GC-19          49,384                  10/13/05   11/08/05    Fahs Rolston Paving Corp            
                                                            GC-21           2,148                  10/13/05   11/08/05    Fahs Rolston paving Corp            
                                                            GC-22           3,472                  10/13/05   11/08/05    Fahs Rolston Paving Corp            
                                                            GC-23           6,354                  10/13/05   11/08/05    fahs Rolston Paving Corp            
                                                            GC-24           1,355                  12/23/05   06/09/06    Fahs Rolston Paving Corp            
                                                            GC-25           1,443                  12/23/05   06/09/06    Fahs Rolston Paving                 
                                                            GC-29           2,013                  12/23/05   06/09/06    Fahs rolston Paving                 
                                                            GC-31           1,553                  02/23/06   06/05/06    Fahs Rolston Paving                 
                                                            GC-35             830                  03/24/06   06/05/06    Fahs Rolston Paving                 
                                                            GC-36           4,502                  03/24/06   06/05/06    Fahs rolston paving                 
                                                            GC-38           2,780                  03/24/06   06/05/06    Fahs RolstonPaving                  
                                                            GC-39           3,564                  04/13/06   06/23/06    Fahs Rolston Paving                 
                                                            GC-44          -2,500                  05/03/07   05/09/07    Fahs Rolston paving                 
                                                            HC-004         39,786          39,786  06/16/05   04/16/07    Louis Picciano and Son              
                                                            HC-009           -839                  04/20/06   06/30/06    Louis Picciano and Sons             
                                                            HC-011          1,847                  07/05/06   12/27/06    Louis Pifcciano and Sons            
                                                            gc-16           9,274                  07/29/05   08/03/05    Fahs-Rolston Paving Corp.           
 
05-0924   Reconstruction               0-014-016  08/24/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-01         -2,500                  12/26/07   01/07/08    REDBOLDT                            
                                                            AAC-02         -2,500                  01/18/08   01/28/08    REDBOLT DBA ACTION CLEANERS         
                                                            EC-001         11,880                  04/07/08   01/23/09    A. TREFFEISEN & SONS, LLC           
                                                            GC-002         16,532                  04/07/08   04/18/08    CHRISTA CONSTRUCTION, LLC           
                                                            GC-003           -170                  04/07/08   04/18/08    CHRISTA CONSTRUCTION, LLC           
                                                            GC-004          4,275                  04/07/08   04/18/08    CHRISTA CONSTRUCTION, LLC           
                                                            MC-001          6,515                  04/07/08   01/23/09    A. TREFFEISEN & SONS, INC.          
                                                            PC-001         -4,343                  04/07/08   01/23/09    A. TREFFEISEN & SONS, LLC           
 
07-1207   Reconstruction               0-014-017  06/27/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-01        -19,004                  06/29/09   08/03/09    KASCON LLC                          
                                                            AAC-02         92,430                  01/21/10   04/30/10    KASCON LLC                          
                                                            AAC-04         -4,515                  04/23/10   08/05/10    KASCON LLC                          
                                                            AAC-13           -241                  10/17/11   12/12/11    KASCON LLC                          
                                                            CC-03               0                  08/31/11   10/03/11    NORTHEAST INTERIOR SYSTEMS INC      
                                                            EC-01          -1,753                  12/09/09   01/25/10    MATCO ELECTRIC CORP                 
                                                            EC-02          -4,351                  12/09/09   01/21/10    MATCO ELECTRIC CORP                 
                                                            EC-06           1,208                  02/17/11   03/14/11    MATCO ELECTRIC CORP                 
                                                            EC-14               0                  08/31/11   06/19/19    MATCO ELECTRIC CORP                 
                                                            EC-15           3,744                  08/31/11   02/13/12    MATCO ELECTRIC CORP                 
                                                            GC-01         -65,680                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-02         -40,449                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-03         -42,300                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-04         -28,018                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-04          -7,471                  06/03/10   08/04/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-05          -3,552                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-06          -8,072                  06/12/09   08/04/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-08          -1,947                  10/19/09   11/12/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-09          -5,865                  10/19/09   11/12/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-10         -29,900                  10/19/09   11/12/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-11          -1,530                  10/19/09   11/12/09    F.E. JONES CONSTRUCTION INC         
                                                            GC-13           4,283                  04/23/10   08/05/10    F.E. JONES CONSTRUCTION             
                                                            GC-18            -491                  03/17/11   05/20/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-20          -5,523                  06/24/11   08/05/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-23          20,160                  08/31/11   10/03/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-24          21,000                  08/31/11   10/03/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-25           9,681                  08/31/11   01/03/12    F.E. JONES CONSTRUCTION INC         
                                                            GC-26            -578                  12/21/11   06/22/12    F.E. JONES CONSTRUCTION INC         
                                                            GC-31            -911                  12/21/11   06/25/12    F.E. JONES CONSTRUCTION INC         
                                                            HVAC-04        -3,500                  08/31/11   02/13/12    LOUIS N PICCIANO & SON INC          
                                                            HVAC-09       -11,398                  07/14/11   05/13/19    LOUIS N PICCIANO & SON INC          
                                                            PC-03          -2,362                  02/03/11   03/10/11    LOUIS N PICCIANO & SON INC          
                                                            PC-09          -1,682                  07/14/11   09/08/11    LOUIS N PICCIANO & SON INC          
                                                            PC-11             -31                  10/17/11   08/23/12    LOUIS N PICCIANO & SON INC          
                                                            SC-03        -251,270                  06/29/09   08/03/09    CLARK COMPANIES                     
                                                            SC-04          89,000                  06/29/09   08/03/09    CLARK COMPANIES                     
                                                            SC-05          -8,000                  07/08/10   08/23/10    CLARK COMPANIES                     
                                                            SC-06          17,738                  06/24/11   08/05/11    CLARK COMPANIES                     
                                                            SC-11         -26,040                  08/31/11   10/03/11    CLARK COMPANIES                     
                                                            SC-12R        290,200                  08/31/11   01/03/12    CLARK COMPANY                       
 
07-1858   Reconstruction               0-014-020  05/28/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HVAC-001       -1,667                  03/25/09   01/30/12    A. TREFFEISEN & SONS, LLC           
 
12-1327   Reconstruction               0-014-021  12/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01           8,293                  09/29/14     /  /      Schuler Haas Electric Corp.         
                                                            EC-03          30,328                  12/16/14   12/30/14    Schuler Haas Electric Corp.         
                                                            EC-09           4,692                  01/20/15   01/23/15    Schuler Haas Electric Corp.         
                                                            GC-01          23,824                  09/29/14   10/08/14    Andrew R. Mancini Associates, Inc.  
                                                            GC-04           4,745                  01/20/15   01/23/15    Andrew R. Mancini Associates, Inc.  
                                                            GC-06          13,667                  01/30/15   02/02/15    Andrew R. Mancini Associates, Inc.  
                                                            GC-14            -166                  05/01/15   05/13/15    Andrew R. Mancini Associates, Inc.  
                                                            HC-01             132                  12/16/14   12/30/14    J&K Plumbing and Heating Co., Inc.  
 
14-0347   Reconstruction               0-014-022  05/11/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01          -6,981                  05/26/17   06/26/17    Nelcorp Electrical Contracting Corp.
                                                            HVAC-01         1,717                  05/26/17   06/26/17    Evans Mechanical, Inc.              
                                                            PC-01              -9                  05/26/17   06/26/17    Evans Mechanical, Inc.              
 
17-0817   Reconstruction               0-014-023  05/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-3          -10,108                  09/21/18   10/22/18    BLANDING ELECTRIC                   
                                                            GC-011            728                  11/22/19   12/27/19    EASTMAN ASSOCIATES, INC.            
                                                            GC-011            728                  06/12/20   07/20/20    Eastman Associates                  
                                                            GC-014         -4,025                  06/24/20   07/24/20    EASTMAN ASSOCIATES, INC.            
                                                            GC-1           -4,386                  09/21/18   10/22/18    EASTMAN ASSOCIATES                  
                                                            GC-3             -900                  09/21/18   10/22/18    EASTMAN ASSOCIATES INC.             
                                                            GC-6            3,483                  09/21/18   10/22/18    EASTMAN ASSOCIATES                  
                                                            GC-7            4,830                  09/21/18   10/22/18    EASTMAN ASSOCIATES                  
 
17-0805   Reconstruction               0-014-024  09/24/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1825   Reconstruction               0-014-025  11/08/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001          4,607                  03/13/20   06/30/20    BLANDING ELECTRIC, INC.             
                                                            EC-002         11,255                  09/23/20   11/06/20    BLANDING ELECTRIC, INC.             
                                                            EC-003          2,102                  03/05/21   04/29/21    BLANDING ELECTRIC, INC.             
                                                            EC-004          7,031                  03/05/21   04/29/21    BLANDING ELECTRIC, INC.             
                                                            EC-005          2,854                  03/05/21   04/29/21    BLANDING ELECTRIC, INC.             
                                                            EC-006          1,523                  03/05/21   04/29/21    BLANDING ELECTRIC, INC.             
                                                            EC-007         10,171                  03/31/21   05/12/21    BLANDING ELECTRIC, INC.             
                                                            EC-008         26,254                  11/02/21   12/09/22    Blanding Electric, Inc              
                                                            GC-001         27,561                  07/22/19   07/24/19    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-002          2,394                  07/22/19   07/24/19    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-003          2,705                  08/05/19   08/06/19    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-004         15,361                  08/05/19   08/06/19    ANDREW R, MANCINI ASSOCIATES, INC.  
                                                            GC-005         32,666                  08/05/19   08/06/19    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-005         32,266                  10/28/19   11/05/19    ANDREW R. MANCICI ASSOCIATES, INC.  
                                                            GC-006         29,503                  01/17/20   03/05/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-007         23,533                  01/17/20   06/02/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-008          3,345                  01/17/20   06/02/20    ANDREW R. MANCINI ASSOCIATES,INC.   
                                                            GC-010         17,176                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-011          6,281                  07/21/20   10/28/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-012         22,586                  06/12/20   07/14/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-012         22,586                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-013         13,800                  06/12/20   07/14/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-013         13,800                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-014          5,741                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-015          8,065                  03/13/20   07/14/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-015          8,065                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-017         16,935                  03/13/20   07/14/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-017         16,935                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-018         19,405                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-019         14,081                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-020         30,101                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-021         15,336                  07/21/20   10/28/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-023         30,571                  06/22/20   07/24/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-024         26,584                  08/10/20   09/17/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-025         32,110                  09/01/20   11/09/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-026         26,264                  09/01/20   11/20/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-027         13,596                  09/01/20   11/20/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-028         17,050                  09/01/20   11/20/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-029         30,301                  12/22/20   02/26/21    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-030          3,585                  12/22/20   04/08/21    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-032         29,739                  12/22/20   02/26/21    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-033          7,985                  12/22/20   02/26/21    SNDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-034         10,069                  12/22/20   02/26/21    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-035         -1,031                  11/02/21   11/17/22    Andrew Mancini Associates, Inc      
                                                            GC-036          2,278                  11/02/21   12/07/22    Andrew Mancini Associates, Inc      
                                                            GC-042          4,144                  11/02/21   12/07/22    Andrew mancini Associates, Inc      
                                                            GC-043          4,536                  12/20/21   01/24/23    Andrew Mancini Assocs Inc           
                                                            GC-044          5,550                  12/20/21   01/24/23    Andrew Mancini Assocs Inc           
                                                            GC-10          17,176                  06/12/20   07/14/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-14           5,741                  06/12/20   07/14/20    ANDREW R. MANCINI ASSOCIATES,INC.   
                                                            MC-001         14,699                  06/12/20   07/20/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            MC-002         11,530                  06/12/20   07/20/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-001          3,880                  03/13/20   06/30/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-002          5,525                  03/13/20   06/30/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-003         25,263                  06/12/20   07/20/20    PICCIRILLI-SLAVIK & VENCENT PLUMBING
                                                            PC-004         24,851                  06/25/20   07/24/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-06          14,375                  07/21/20   09/11/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-08           4,022                  06/25/20   07/24/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-10           4,987                  04/16/21   07/27/21    PICCIRILLI-SLAVIK & VINCENT PLUMBING
 
18-2210   Reconstruction               0-014-026  11/04/18  NO CHANGE ORDERS ON ELECTRONIC FILE
18-2211   Reconstruction               0-014-027  11/04/18  NO CHANGE ORDERS ON ELECTRONIC FILE
22-0520   Reconstruction               0-014-028  09/23/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HVAC-01        -7,600                  03/16/23   12/19/23    A.TREFFEISEN & SON, LLC             
 
02-0643FP Reconstruction               0-014-FP1  12/06/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Great Plains Elementary:
92-0159   Reconstruction               0-017-003  08/25/92  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0229   Reconstruction               0-017-004  10/27/93  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0096   Reconstruction               0-017-005  11/03/99  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0606   Reconstruction               0-017-006  07/12/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ETC-002         6,210                  01/08/07   01/24/07    Blanding Electric                   
 
02-2059   Reconstruction               0-017-007  09/12/03  NO CHANGE ORDERS ON ELECTRONIC FILE
03-0731   Reconstruction               0-017-008  04/25/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-003        38,965                  03/29/05   05/02/05    Two Brothers Contracting            
                                                            GC-002          8,935                  12/24/04   01/03/05    Fahs Rolston Paving                 
                                                            GC-007         -6,905                  03/29/05   05/02/05    Fahs Rolston Paving Corp            
                                                            GC-009         25,234                  03/10/05   04/15/05    Fahs Rolston Paving Corp            
                                                            GC-010         30,535                  06/16/05   06/30/05    Fahs Rolston Paving Corp            
                                                            GC-11          33,822                  06/02/05   06/30/05    Fahs Rolston Paving Corp            
                                                            GC-13           6,870                  07/25/05   07/26/05    Fahs Rolston Paving Corp            
                                                            GC-20          14,588                  10/13/05   11/08/05    Fahs Riolston Paving Corp           
                                                            GC-26           1,227                  12/23/05   06/09/06    Fahs Rolston paving Corp            
                                                            GC-27           2,697                  12/23/05   06/09/06    Fahs Rolston Paving Corp            
                                                            GC-32           5,911                  02/23/06   07/14/06    fahs Rolston Paving                 
                                                            GC-37           7,784                  03/24/06   06/05/06    Fahs RolstonPaving                  
                                                            HC-003          3,591                  12/02/04   12/08/04    Louis Picciano & Son                
                                                            HC-005          8,034                  12/23/05   12/29/05    Louis Picciano                      
                                                            HC-006         11,874                  12/23/05   12/29/05    Louis Picciano                      
                                                            HC-007         17,472                  02/01/06   06/30/06    louis Picciano and sons             
                                                            RC-003          5,200                  12/09/04   06/23/05    DeWald Roofing Co                   
 
05-0925   Reconstruction               0-017-009  08/24/06  NO CHANGE ORDERS ON ELECTRONIC FILE
07-1208   Reconstruction               0-017-010  06/27/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-08         -1,145                  03/17/11   05/20/11    KASCON LLC                          
                                                            AAC-10            -29                  10/17/11   12/28/11    KASCON LLC                          
                                                            EC-01            -549                  12/09/09   01/25/10    MATCO ELECTRIC CORP                 
                                                            EC-05             672                  02/02/11   03/10/11    MATCO ELECTRIC CORP                 
                                                            EC-09             627                  07/14/11   08/12/11    MATCO ELECTRIC CORP                 
                                                            EC-11               0                  08/31/11   02/13/12    MATCO ELECTRIC CORP                 
                                                            GC-04          -7,471                  06/03/10   08/04/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-28             -42                  12/21/11   06/25/12    F.E. JONES CONSTRUCTION INC         
                                                            HVAC-06          -770                  07/14/11   08/12/11    LOUIS N PICCIANO & SON INC          
                                                            PC-06            -189                  07/14/11   08/05/11    LOUIS N PICCIANO & SON INC          
                                                            SC-01         -22,000                  06/29/09   08/03/09    CLARK COMPANIES                     
                                                            SC-08          -1,953                  08/31/11   10/03/11    CLARK COMPANIES                     
 
07-1162   Reconstruction               0-017-011  03/18/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001            207                  03/11/09   06/08/09    A. Treffeisen & Sons                
                                                            PC-001          8,063                  03/11/09   06/08/09    A. Treffeisen & Sons                
                                                            RC-001        -18,125                  11/16/09   02/09/10    DEWALD ROOFING CO INC               
                                                            RC-002         -5,680                  05/11/09   07/29/09    DEWALD ROOFING CO., INC.            
 
12-1328   Reconstruction               0-017-012  12/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            EC-06           6,424                  12/16/14   12/30/14    Schuler Haas Electric Corp.         
                                                            EC-18             896                  05/01/15   05/13/15    Schuler Haas Electric Corp          
                                                            EC-19             787                  05/01/15   05/13/15    Schuler Haas Electric Corp          
                                                            GC-03           1,877                  12/16/14   12/30/14    Andrew R. Mancini Associates, Inc.  
                                                            GC-05           2,675                  01/30/15   01/02/15    Andrew R. Mancini Associates, Inc.  
                                                            GC-09             199                  05/01/15   05/13/15    Andrew R. Mancini Associates Inc.   
                                                            GC-11               0                  05/01/15   05/13/15    Andrew R. Mancini Associates Inc.   
                                                            HC-04               0                  03/19/15   04/01/15    J&K Plumbing and Heating., Inc.     
                                                            PC-01         -10,000                  10/31/14   11/12/14    Louis N. Picciano & Son, Inc.       
                                                            PC-02R1        13,807                  03/09/15   03/30/15    Louis N. Picciano & Son, Inc.       
 
17-0818   Reconstruction               0-017-013  05/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-5            2,042                  09/21/18   10/22/18    BLANDING ELECTRIC                   
                                                            EC-6            9,239                  09/25/18   10/22/18    BLANDING ELECTRIC                   
                                                            GC-012          8,394                  01/22/20   02/19/20    EASTMAN ASSOCIATES, INC.            
                                                            GC-012          8,394                  06/12/20   08/06/20    Eastman Associates                  
                                                            GC-012          8,394                  06/12/20     /  /      Eastman Associates                  
                                                            GC-015          1,040                  06/12/20   08/06/20    Eastman Associates                  
                                                            GC-4           13,200                  09/21/18   10/22/18    EASTMAN ASSOCIATES                  
                                                            GC-5            7,892                  09/21/18   10/22/18    EASTMAN ASSOCIATES                  
                                                            GC-8           -4,450                  04/17/19   04/29/19    EASTMAN ASSOCIATES INC.             
 
17-0806   Reconstruction               0-017-014  09/24/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1826   Reconstruction               0-017-015  11/08/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-023          1,497                  07/21/20   10/28/20    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-031          1,788                  02/05/21   03/30/21    ANDREW R. MANCINI ASSOCIATES, INC.  
                                                            GC-040          5,315                  11/02/21   12/07/22    Andrew Mancini Associates, Inc      
                                                            GC-041          2,909                  11/02/21   12/07/22    Andrew mancini Associates, Inc      
 
20-0273   Reconstruction               0-017-016  10/01/20  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0641FP Reconstruction               0-017-FP1  12/06/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Riverside Elementary:
92-0160   Reconstruction               0-018-002  08/25/92  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0230   Reconstruction               0-018-003  10/27/93  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0097   Reconstruction               0-018-005  11/03/99  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0607   Reconstruction               0-018-006  07/12/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ETC-003         8,923                  01/08/07   01/24/07    Blanding Electric                   
 
02-2060   Reconstruction               0-018-007  09/12/03  NO CHANGE ORDERS ON ELECTRONIC FILE
03-0732   Reconstruction               0-018-008  04/25/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-02         32,400                  03/29/05   05/02/05    Two Brothers Contracting            
                                                            GC-001         11,659                  10/21/04   11/15/04    Fahs Rolston Paving                 
                                                            GC-003         26,096                  12/24/04   01/03/05    Fahs Rolston Paving                 
                                                            GC-004         17,423                  12/27/04   01/03/05    Fahs Rolston Paving                 
                                                            GC-005          9,625                  01/21/05   06/29/05    Fahs Rolston Paving Corp            
                                                            GC-006         15,268                  03/10/05   04/15/05    Fahs Rolston Paving Corp            
                                                            GC-008         21,873                  03/10/05   05/02/05    Fahs Rolston Paving                 
                                                            GC-009            350                  03/10/05   04/15/05    Fahs Rolston Paving Corp            
                                                            GC-15           3,563                  07/25/05   07/26/05    Fahs Rolston Paving Corp            
                                                            HC-002          9,562                  10/21/04   06/21/05    Louis Picciano & Sons               
                                                            HC-003          3,078                  12/02/04   12/08/04    Louis Picciano & Son                
                                                            RC-002          3,900                  09/10/04   09/24/04    DeWald Roofing                      
 
05-0926   Reconstruction               0-018-009  08/24/06  NO CHANGE ORDERS ON ELECTRONIC FILE
07-1209   Reconstruction               0-018-010  06/27/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-11            -91                  10/17/11   12/12/11    KASCON LLC                          
                                                            EC-01            -549                  12/09/09   01/25/10    MATCO ELECTRIC CORP                 
                                                            EC-12               0                  08/31/11   02/13/12    MATCO ELECTRIC CORP                 
                                                            GC-04          -7,471                  06/03/10   08/04/10    F.E. JONES CONSTRUCTION INC         
                                                            GC-19             449                  08/31/11   10/03/11    F.E. JONES CONSTRUCTION INC         
                                                            GC-29             -42                  12/21/11     /  /      F.E. JONES CONSTRUCTION INC         
                                                            HVAC-07          -924          -1,196  07/14/11   09/08/11    LOUIS N PICCIANO & SON INC          
                                                            PC-07            -196                  07/14/11   08/05/11    LOUIS N PICCIANO & SON INC          
                                                            SC-02         -17,500                  06/29/09   08/03/09    CLARK COMPANIES                     
                                                            SC-09            -325                  08/31/11     /  /      CLARK COMPANIES                     
 
07-1163   Reconstruction               0-018-011  03/18/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            HVAC-001       -2,875                  03/11/09   06/08/09    A. Treffeisen & Sons LLC            
                                                            RC-001         -9,918                  05/11/09     /  /      DEWALD ROOFING CO., INC.            
                                                            RC-0012A       -3,218                  06/24/11   07/01/11    DEWALD ROOFING CO INC               
                                                            RC-0012B       -6,700                  06/24/11   07/01/11    DEWALD ROOFING CO INC               
                                                            RC001ARS        8,207                  11/16/09   02/04/10    DEWALD ROOFING CO INC               
 
12-1329   Reconstruction               0-018-012  12/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-05           4,452                  12/16/14   12/30/14    Schuler Haas Electric Corp.         
                                                            GC-07           2,765                  01/30/15   02/02/15    Andrew R. Mancini Assocaites, Inc.  
                                                            GC-13               0                  05/01/15   05/13/15    Andrew R. Mancini Associates, Inc.  
 
17-0819   Reconstruction               0-018-013  05/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-4            2,042                  09/21/18   10/22/18    BLANDING ELECTRIC                   
                                                            EC-7           31,133                  09/21/18   10/22/18    BLANDING ELECTRIC                   
                                                            GC-013          1,438                  01/17/20   03/05/20    EASTMAN ASSOCIATES, INC.            
                                                            GC-013          1,438                  06/12/20   08/06/20    Eastman Associates                  
                                                            GC-9          -13,348                  04/17/19   04/29/19    EASTMAN ASSOCIATES INC.             
 
17-0807   Reconstruction               0-018-014  09/24/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1827   Reconstruction               0-018-015  11/08/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-037          9,872                  11/02/21   12/07/22    Andrew Mancini Associates, Inc      
                                                            GC-039            247                  11/02/21   12/07/22    Andrew Mancini Associates, Inc      
                                                            PC-005          2,230                  07/21/20   09/11/20    PICCIRILLI-SLAVIK & VINCENT PLUMBING
                                                            PC-012            846                  08/11/21   04/21/22    PICCIRILLI-SLAVIK-VINCENT PLUMB&HEAT
                                                            PC-09           1,067                  04/16/21   07/27/21    PICCIRILLI-SLAVIK & VINCENT         
 
20-0274   Reconstruction               0-018-016  10/01/20  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0642FP Reconstruction               0-018-FP1  12/06/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Building:
22-1570   New Construction             2-028-001  05/30/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXMaintenace Storage Bldg-Demo:
22-1571   Reconstruction               3-023-003  05/30/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage Reconstruction:
01-0578   Reconstruction               5-001-L01  01/30/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          New Bus Garage:
00-0126   New Construction             5-019-001  10/26/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            2,979                  02/12/02   05/13/02    A. Treffeisen & Sons                
                                                            GC-5          -14,095                  02/12/02   05/13/02    Eastman Assoc.                      
                                                            MC1            -1,087                  07/22/02   08/28/02    B&H Air Conditioning                
                                                            PC-1           -2,000                  02/12/02   05/13/02    Auchinachie Plumbing                
 
07-1210   Reconstruction               5-019-002  06/27/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PC-10            -531                  07/14/11   08/12/11    LOUIS N PICCIANO & SON INC          
 
20-0275   Reconstruction               5-019-003  10/01/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC-01          44,394                  08/23/21   04/26/22    SMITH SITE DEVELOPMENT LLC          
 

          District-Wide:
12-1330   Reconstruction               7-999-001  12/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-02          80,992                  11/12/14   11/14/14    Schuler Haas Electric Corp.         
                                                            EC-07           6,794                  12/16/14   12/30/14    Schuler Haas Electric Corp.         
                                                            EC-11          25,806                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
                                                            EC-12          28,719                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
                                                            EC-13          23,400                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
                                                            EC-14               0                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
                                                            EC-15               0                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
                                                            EC-16              -5                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
                                                            EC-17           3,066                  02/17/15   02/18/15    Schuler Haas Electric Corp.         
 
17-0777   Reconstruction               7-999-002  05/11/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1845   Reconstruction               7-999-003  01/02/17  NO CHANGE ORDERS ON ELECTRONIC FILE

UNATEGO (OTEGO-UNADILLA) CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-16-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          XXOtego ES (sold 2/20/2020):
96-0844   Additions and Alterations    0-001-003  04/02/97  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0531   Additions and Alterations    0-001-004  06/11/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00002          39,556                  11/29/02   12/06/02    Leitz Ent.                          
                                                            00003             264                  11/29/02   12/06/02    Leitz Ent.                          
                                                            00007          -3,238                  11/29/02   12/06/02    Leitz Ent.                          
                                                            02-00008       -3,160                  11/29/02   12/06/02    Leitz Ent.                          
                                                            02-00012          391                  11/29/02   12/06/02    Leitz Ent.                          
                                                            02-00014           61                  03/06/03   03/11/03    Leitz Ent.                          
                                                            EC-11             688                  03/11/04   04/12/04    Nelcorp Elec.                       
                                                            EC-15           1,743                  05/19/04   06/04/04    Nelcorp Elec.                       
                                                            EC-22             699                  08/19/04   09/27/04    Nelcorp Elec.                       
                                                            EC-26           5,212                  11/04/04   11/29/04    Nelcorp Elec.                       
                                                            EC-30           1,067                  02/26/05   06/15/05    Nelcorp Electrical Contracting      
                                                            EC-32             383                  12/08/04   01/03/05    Nelcorp Elec.                       
                                                            EC-35          54,985                  01/26/05   10/03/05    Nelcorp Electrical Contracting      
                                                            EC-41             245                  04/28/05   06/21/05    Nelcorp Electrical Contracting      
                                                            EC-43          -5,025                  06/08/05   06/29/05    Nelcorp Electrical Contracting      
                                                            EC-5            2,671                  12/16/03   01/08/04    Nelcorp Elec.                       
                                                            GC-12          14,490                  03/11/04   03/15/04    Murnane Bldg Contractors            
                                                            GC-27           3,130                  07/07/04   07/13/04    Muranne Bldg Contractors            
                                                            GC-30          39,779                  07/22/04   07/27/04    Murnane Bldg Contractors            
                                                            GC-42          15,241                  11/10/04   11/19/04    Murnane Bldg Contractors            
                                                            GC-44           1,610                  01/05/04   01/25/05    Murnane Bldg Contractors            
                                                            GC-7              917                  12/16/03   12/30/03    Murnane Bldg Contractors            
                                                            HC-1            7,553                  11/14/03   01/14/04    Kimble Inc                          
                                                            HC-16           1,824                  03/11/04   04/12/04    Kimble Inc                          
                                                            HC-20           4,123                  03/11/04   04/12/04    KImble Inc                          
                                                            HC-22             530                  04/20/04   04/23/04    Kimble Inc                          
                                                            HC-25           1,236                  06/17/04   06/25/04    Kimble Inc                          
                                                            HC-29           7,231                  07/22/04   09/27/04    Kimble Inc                          
                                                            HC-37           7,321                  12/20/04   01/03/05    Kimble Inc                          
                                                            HC-39          10,445                  12/20/04   01/03/05    Kimble Inc                          
                                                            HC-41           7,307                  12/20/04   01/03/05    Kimble Inc                          
                                                            HC-49           2,361                  05/12/05   06/07/05    Kimble Inc                          
                                                            HC-53             839                  04/28/05   06/21/05    Kimble Inc                          
                                                            HC-9              412                  12/02/03   12/09/03    Kimble Inc                          
                                                            PC-7              929                  11/17/04   11/29/04    Evans Mech.                         
                                                            SC-17          -5,225                  08/14/03   08/27/03    Leitz Ent.                          
                                                            SC-21          -2,671                  12/05/03   12/09/03    Leitz Ent.                          
 
08-0520   Reconstruction               0-001-007  03/31/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-3            2,576                  10/13/10   10/29/10    ADVANCED POWER & LIGHT INC          
 
08-1213   Reconstruction               0-001-008  04/29/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           -1,316                  04/29/10   07/19/10    MATCO ELECTRIC CORP                 
                                                            EC-3           10,666                  09/15/10   02/09/11    MATCO ELECTRIC CORP                 
                                                            EC-4           60,663                  01/10/11   02/17/11    MATCO ELECTRIC CORP                 
                                                            EC-6            3,113                  07/01/11   01/11/12    MATCO ELECTRIC CORP                 
                                                            EC-9            1,988                  07/13/11   08/17/11    MATCO ELECTRIC CORP                 
                                                            GC-12          -4,718                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-16         105,253                  09/23/10   12/15/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-17         120,137                  09/23/10   12/15/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-18          19,251                  01/24/11   02/23/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-21           4,139                  01/24/11   02/23/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-27          23,028                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-28          18,077                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-29           3,275                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-30          -2,898                  09/01/11   10/22/12    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-4              685                  03/08/10   09/23/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-7            6,641                  05/17/10   08/27/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            MC-2            4,266                  07/01/11   08/17/11    LOUIS N PICCIANO AND SON INC        
                                                            PC-1           31,651                  12/17/10   02/09/11    LOUIS N PICCIANO AND SON INC        
 
13-0113   Reconstruction               0-001-009  11/20/13  NO CHANGE ORDERS ON ELECTRONIC FILE

          Unadilla Elementary School:
92-0078   Reconstruction               0-009-004  07/29/92  NO CHANGE ORDERS ON ELECTRONIC FILE
96-0843   Additions and Alterations    0-009-005  04/02/97  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0532   Additions and Alterations    0-009-006  06/11/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00001          29,931                  11/29/02   12/06/02    Leitz Ent.                          
                                                            00004             475                  11/29/02   12/06/02    Leitz Ent.                          
                                                            00006          -4,326                  11/29/02   12/06/02    Leitz Ent.                          
                                                            02-00010       20,682                  02/12/03   02/19/03    Leitz Ent.                          
                                                            02-00011          892                  11/29/02   12/06/02    Leitz Ent.                          
                                                            02-00013          391                  12/11/02   12/13/02    Leitz Ent.                          
                                                            02-0009        -3,745                  11/29/02   12/06/02    Leitz Ent.                          
                                                            AAC-4           4,761                  09/24/03   10/02/03    S&S Environ.                        
                                                            EC-12             127                  03/11/04   04/12/04    Nelcorp Elec.                       
                                                            EC-13           2,421                  03/03/04   10/07/08    NELCORP ELECTRICAL CONTRACTING CORP.
                                                            EC-20             459                  07/13/04   07/13/04    Nelcorp Elec.                       
                                                            EC-23           4,989                  12/08/04   01/03/05    Nelcorp Elec.                       
                                                            EC-3            2,357                  12/16/03   01/08/04    Nelcorp Elec.                       
                                                            EC-39             491                  08/22/08   07/09/09    NELCORP ELECTRICAL CONTRACTING CORP.
                                                            EC-40           4,516                  08/22/08   07/09/09    NELCORP ELECTRICAL CONTRACTING CORP.
                                                            GC-11          32,682                  03/11/04   03/15/04    Murnane Bldg Contractors            
                                                            GC-16           4,078                  04/09/04   04/20/04    Murnane Bldg Contractors            
                                                            GC-21          13,024                  06/17/04   06/25/04    Murnane Bldg Contractors            
                                                            GC-22           1,495                  05/25/04   06/10/04    Murnane Bldg Contractors            
                                                            GC-26           2,129                  07/07/04   07/13/04    Murnane Bldg Contractors            
                                                            GC-3           31,890                  03/25/04   04/06/04    Murnane Bldg Contractors            
                                                            GC-34          26,988                  05/05/05   06/21/05    Murnane Building Contractors        
                                                            GC-35          20,160                  09/30/04   11/15/04    Murnane Bldg Contractors            
                                                            GC-4           58,555                  02/09/04   02/20/04    Murnane Bldg Contractors            
                                                            GC-41             286                  11/04/04   11/19/04    Murnane Bldg Contractors            
                                                            GC-8           16,613                  03/11/04   03/15/04    Murnane Bldg Contractors            
                                                            GC-9            4,813                  12/18/03   12/30/03    Murnane Bldg Contractors            
                                                            HC-10           3,679                  12/16/03   04/08/04    Kimble Inc                          
                                                            HC-15           3,833                  03/11/04   04/12/04    Kimble Inc                          
                                                            HC-17          10,188                  03/17/04     /  /      Kimble Inc                          
                                                            HC-18           3,170                  03/11/04     /  /      Kimble Inc                          
                                                            HC-2           11,458                  11/14/03   01/08/04    Kimble Inc                          
                                                            HC-21           1,161                  04/20/04   04/23/04    Kimble Inc                          
                                                            HC-27           4,031                  07/15/04   07/21/04    Kimble Inc                          
                                                            HC-3              716                  11/24/03   01/08/04    Kimble Inc                          
                                                            HC-31           3,087                  07/15/04   07/21/04    Kimble Inc                          
                                                            HC-32          10,040                  09/02/04   09/23/04    Kimble Inc                          
                                                            HC-40           9,400                  12/20/04   01/03/05    Kimble Inc                          
                                                            HC-45           4,334                  08/22/08   07/09/09    KIMBLE, INC.                        
                                                            HC-48           3,768                  05/12/05   06/07/05    Kimble Inc                          
                                                            HC-51           9,284                  05/12/05   06/07/05    Kimble Inc                          
                                                            HC-52           3,504                  04/28/05   06/21/05    Kimble Inc                          
                                                            HC-55             858                  04/28/05   06/21/05    Kimble Inc                          
                                                            HC-6            2,130                  11/18/03   01/08/04    Kimble Inc                          
                                                            SC-16          -5,330                  08/14/03   08/27/03    Leitz Ent.                          
 
08-0521   Reconstruction               0-009-008  03/31/09  NO CHANGE ORDERS ON ELECTRONIC FILE
08-1214   Additions and Alterations    0-009-009  04/29/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-2           14,429                  09/15/10   02/09/11    MATCO ELECTRIC CORP                 
                                                            EC-5            2,011                  01/18/11   02/17/11    MATCO ELECTRIC CORP                 
                                                            EC-7            6,676                  07/01/11   12/29/11    MATCO ELECTRIC CORP                 
                                                            EC-8            1,988                  07/13/11   08/17/11    MATCO ELECTRIC CORP                 
                                                            GC-1           16,477                  11/02/09   12/30/09    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-10          16,532                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-11          -4,718                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-13           1,802                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-15           5,721                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-19          10,433                  01/24/11   02/23/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-20          20,548                  01/24/11   02/23/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-22         178,782                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-23          18,051                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-24          18,695                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-25          13,358                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-26          11,767                  06/15/11   09/09/11    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-3           11,601                  03/08/10   05/11/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-6           10,500                  05/17/10   08/27/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-8            9,189                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-9           12,477                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            MC-1            7,306                  10/13/10   11/12/10    LOUIS N PICCIANO AND SON INC        
                                                            MC-3          -34,327                  09/30/11   12/22/11    LOUIS N PICCIANO AND SON INC        
                                                            MC-4           10,120                  02/17/12   07/20/12    LOUIS N PICCIANO AND SON INC        
                                                            MC-5            2,358                  05/29/12   12/11/12    LOUIS N PICCIANO AND SON INC        
                                                            PC-2            6,312                  03/28/11   04/22/11    LOUIS N PICCIANO AND SON INC        
                                                            PC-3            7,922                  07/01/11   08/17/11    LOUIS N PICCIANO AND SON INC        
                                                            PC-4            6,214                  07/01/11   08/17/11    LOUIS N PICCIANO AND SON INC        
 
10-1118   Reconstruction               0-009-010  05/31/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-1           -8,545                  12/19/11   06/25/12    ANDREW R MANCINI ASSOCIATES INC     
 
13-0114   Reconstruction               0-009-011  11/20/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-1            8,426                  01/09/15   01/20/15    Forno Enterprises Inc.              
 
16-1799   Reconstruction               0-009-012  06/29/17  NO CHANGE ORDERS ON ELECTRONIC FILE
21-1491   Reconstruction               0-009-013  01/12/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Unatego Jr/Sr High:
91-0285   Reconstruction               0-015-004  10/08/91  NO CHANGE ORDERS ON ELECTRONIC FILE
96-0845   Alterations                  0-015-005  04/02/97  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0533   Additions and Alterations    0-015-006  06/11/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00005           2,464                  11/29/02   12/06/02    Leitz Ent.                          
                                                            AAC-1           1,455                  08/14/03   08/28/03    S&S Environ.                        
                                                            AAC-2           5,232                  08/14/03   08/28/03    S&S Environ.                        
                                                            AAC-3           1,369                  09/24/03   10/02/03    S&S Environ.                        
                                                            EC-1           -8,734                  11/18/03   01/08/04    Nelcorp Elec.                       
                                                            EC-10           1,605                  03/11/04     /  /      Nelcorp Elec.                       
                                                            EC-14             936                  03/03/04   04/12/04    Nelcorp Elec.                       
                                                            EC-16            -243                  06/17/04   06/25/04    Nelcorp Elec.                       
                                                            EC-17           4,630                  07/07/04   07/13/04    Nelcorp Elec.                       
                                                            EC-18           2,740           2,740  07/07/04     /  /      Nelcorp Elec.                       
                                                            EC-19           3,646                  07/07/04   07/13/04    Nelcorp Elec.                       
                                                            EC-21           2,551                  08/19/04   09/27/04    Nelcorp Elec.                       
                                                            EC-24           1,064                  08/19/04   09/27/04    Nelcorp Elec.                       
                                                            EC-27           6,088                  11/04/04   01/03/05    Nelcorp Elec.                       
                                                            EC-28           5,556                  11/04/04   11/29/04    Nelcorp Elec.                       
                                                            EC-29          10,154                  11/04/04   01/03/05    Nelcorp Elec.                       
                                                            EC-31           3,134                  11/10/04   11/29/04    Nelcorp Elec.                       
                                                            EC-33           2,228                  12/20/04   01/03/05    Nelcorp Elec.                       
                                                            EC-34           4,625                  12/20/04   01/03/05    Nelcorp Elec.                       
                                                            EC-37           1,166                  02/26/05   06/15/05    Nelcorp Electrical Contracting      
                                                            EC-4            1,076                  12/16/03   01/08/04    Nelcorp Elec.                       
                                                            EC-42             444                  04/28/05   06/21/05    Nelcorp Electrical Contracting      
                                                            EC-6            4,443                  12/16/03   01/08/04    Nelcorp Elec.                       
                                                            EC-7            9,105                  12/30/03     /  /      Nelcorp Elec.                       
                                                            EC-8            2,145                  12/18/03   12/29/03    Nelcorp Elec.                       
                                                            EC-9            3,836                  12/18/03   12/29/03    Nelcorp Elec.                       
                                                            GC-1            3,291                  08/14/03   08/28/03    Murnane Bldg Contractors            
                                                            GC-10           7,683                  03/11/04   03/15/04    Murnane Bldg Contractors            
                                                            GC-13           4,057                  03/11/04   03/15/04    Murnane Bldg Contractors            
                                                            GC-14          13,716                  03/11/04   06/10/04    Murnane Bldg Contractors            
                                                            GC-15           3,065                  03/11/04     /  /      Murnane Bldg Contractors            
                                                            GC-17           3,703                  04/09/04   04/13/04    Murnane Bldg Contractors            
                                                            GC-18           4,725                  02/18/04   02/23/04    Murnane Bldg Contractors            
                                                            GC-19           4,570                  03/25/04   04/06/04    Murnane Bldg Contractors            
                                                            GC-2            5,071                  11/24/03   12/04/03    Murnane Bldg Contractors            
                                                            GC-20           3,065                  06/07/04   06/10/04    Murnane Bldg Contractors            
                                                            GC-23          14,902                  06/17/04   06/25/04    Murnane Bldg Contractors            
                                                            GC-24           1,431                  05/25/04   06/10/04    Murnane Bldg Contractors            
                                                            GC-25           1,022                  06/17/04   06/25/04    Murnane Bldg Contractors            
                                                            GC-28           6,069                  07/22/04   09/28/04    Murnane Bldg Contractors            
                                                            GC-29           2,558                  07/07/04     /  /      Murnane Bldg Contractors            
                                                            GC-31          16,748                  09/30/04   10/04/04    Murnane Bldg Contractors            
                                                            GC-32           3,516                  07/15/04   07/21/04    Murnane Bldg Contractors            
                                                            GC-33           8,057                  09/02/04   09/24/04    Murnane Bldg Contractors            
                                                            GC-36          23,468                  09/30/04   10/04/04    Murnane Bldg Contractors            
                                                            GC-38           5,379                  11/04/04   11/19/04    Murnane Bldg Contractors            
                                                            GC-39          -8,093                  11/15/04   11/19/04    Murnane Bldg Contractors            
                                                            GC-40           5,113                  11/04/04   11/19/04    Murnane Bldg Contractors            
                                                            GC-43           9,286                  12/20/04   01/20/05    Murnane Bldg Contractors            
                                                            GC-45           2,573                  01/26/05   02/08/05    Murnane Building Contractors        
                                                            GC-46           1,247                  04/28/05   06/21/05    Murnane Building Contractors        
                                                            GC-5            3,237                  12/05/03   12/09/03    Murnane Bldg Contractors            
                                                            GC-6           10,314                  12/05/03   12/09/03    Murnane Bldg Contractors            
                                                            HC-11           5,508                  12/30/03   01/14/04    Kimble Inc                          
                                                            HC-12             772                  03/11/04   04/12/04    Kimble Inc                          
                                                            HC-13          13,943                  03/17/04   04/06/04    Kimble Inc                          
                                                            HC-14           4,807                  03/11/04   04/12/04    Kimble Inc                          
                                                            HC-19           2,201                  03/03/04   03/05/04    Kimble Inc                          
                                                            HC-23             588                  04/20/04   04/23/04    Kimble Inc                          
                                                            HC-24           2,231                  05/19/04   06/04/04    Kimble Inc                          
                                                            HC-26           1,981                  07/07/04   07/13/04    Kimble Inc                          
                                                            HC-28           3,214                  07/15/04   07/21/04    Kimble Inc                          
                                                            HC-30             440                  07/15/04   07/21/04    Kimble Inc                          
                                                            HC-33          11,139                  09/02/04   09/24/04    Kimble Inc                          
                                                            HC-34          12,470                  11/04/04   06/21/05    Kimble Inc                          
                                                            HC-35           5,556                  11/04/04   11/29/04    Kimble Inc                          
                                                            HC-36           1,370                  11/04/04   11/29/04    Kimble Inc                          
                                                            HC-38           6,345                  12/08/04   01/03/05    Kimble inc                          
                                                            HC-4            4,862                  11/24/03   01/08/04    Kimble Inc                          
                                                            HC-43           2,370                  12/20/04   01/03/05    Kimble Inc                          
                                                            HC-44           3,204                  01/05/05   06/30/05    Kimble Inc                          
                                                            HC-54          10,266                  05/05/05   06/21/05    Kimble Inc                          
                                                            HC-57           7,258                  05/05/05   06/21/05    Kimble Inc                          
                                                            HC-58          13,950                  05/05/05   06/21/05    Kimble Inc                          
                                                            HC-60           9,236                  06/08/05   06/29/05    Kimble Inc                          
                                                            HC-7            4,629                  11/18/03   01/08/04    Kimble Inc                          
                                                            HC-8            5,429                  12/05/03   12/09/03    Kimble Inc                          
                                                            PC-1            2,920                  08/14/03   08/28/03    Evans Mech.                         
                                                            PC-10           6,459                  01/05/05   06/30/05    Evans Mechanical Inc                
                                                            PC-2           10,227                  11/24/03   01/08/04    Evans Mech.                         
                                                            PC-3            2,916                  03/25/04   04/13/04    Evans Mech.                         
                                                            PC-4            4,485                  03/25/04   04/13/04    Evans Mech.                         
                                                            PC-5            3,073                  08/19/04   09/27/04    Evans Mech.                         
                                                            PC-6              496                  11/17/04   11/29/04    Evans Mech.                         
                                                            PC-8            1,321                  11/15/04   11/29/04    Evans Mech.                         
                                                            SC-15          17,893                  08/14/03   08/28/03    Leitz Ent.                          
                                                            SC-18           5,718                  08/14/03   08/28/03    Leitz Ent.                          
                                                            SC-19           1,354                  11/24/03   12/02/03    Leitz Ent.                          
                                                            SC-20           9,122                  11/24/03   12/04/03    Leitz Ent.                          
                                                            SC-22               0                  03/17/04   04/06/04    Leitz Ent.                          
                                                            SC-23           9,163                  07/22/04   07/27/04    Leitz Ent.                          
                                                            SC-24           2,500                  07/15/04   07/21/04    Leitz Ent.                          
                                                            SC-25             884                  08/19/04   09/27/04    Leitz Ent.                          
                                                            SC-26           1,909                  11/04/04   11/19/04    Leitz Ent.                          
                                                            SC-27          50,513                  11/04/04   10/03/05    Leitz Ent.                          
 
08-0522   Reconstruction               0-015-010  03/31/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           16,704                  06/23/10   08/05/10    ADVANCED POWER & LIGHT INC          
                                                            EC-2            9,565                  10/13/10   11/16/10    ADVANCED POWER & LIGHT INC          
                                                            EC-4           -7,647                  01/18/11   02/11/11    ADVANCED POWER & LIGHT INC          
                                                            EC-5             -500                  07/21/11   08/09/11    Advanced Power & Light              
                                                            GC-1           -5,145                  02/23/11   03/18/11    ANDREW R MANCINI ASSOCIATES INC     
                                                            MC-1          -18,381                  02/01/10   03/22/10    J&K PLUMBING & HEATING CO INC       
                                                            PC-1            3,456                  05/21/10   08/04/10    ORCHARD EARTH AND PIPE CORP         
                                                            PC-2           10,796                  05/21/10   08/04/10    ORCHARD EARTH AND PIPE CORP         
                                                            PC-3           16,825                  08/23/10   09/10/10    ORCHARD EARTH AND PIPE CORP         
                                                            PC-4           12,730                  08/23/10   09/10/10    ORCHARD EARTH AND PIPE CORP         
                                                            PC-5           14,142                  08/23/10   09/10/10    ORCHARD EARTH AND PIPE CORP         
                                                            PC-6              -23                  11/24/10   12/16/10    ORCHARD EARTH AND PIPE CORP         
 
07-0525   Reconstruction               0-015-012  10/11/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           12,585                  05/26/10   07/20/10    BLANDING ELECTRIC                   
                                                            EC-2            2,765                  04/20/09   09/23/09    BLANDING ELECTRIC INC               
                                                            SC-1           16,842                  10/30/08   03/06/09    W & D SMITH & SONS CONSTRUCTION, INC
                                                            SC-2            9,336                  05/26/10   07/20/10    W&D SMITH & SONS CONSTRUCTION INC   
 
07-1464   Reconstruction               0-015-013  02/28/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            RC-1          -41,250                  04/26/10   08/23/10    DELUXE ROOFING & SHEET METAL CORP   
 
13-0115   Reconstruction               0-015-014  11/20/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-2           -3,209                  01/09/15   01/20/15    Forno Enterprises, Inc.             
 
12-0864   Reconstruction               0-015-015  04/22/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-03           7,093                  06/06/14   07/03/14    Matco Electric Corp.                
                                                            EC-1            5,155                  02/06/14   03/05/14    Matco Electric Corp.                
                                                            EC-2             -571                  02/06/14   03/05/14    Matco Electric Corp.                
                                                            GC-1             -832                  08/19/13   09/20/13    F.E. Johnes Construction, Inc.      
                                                            GC-2            2,652                  10/24/13   11/18/13    F.E. JONES CONSTRUCTION INC         
                                                            GC-3           12,370                  02/06/14   03/05/14    F. E. Jones Construction, Inc.      
                                                            GC-4            4,804                  02/06/14   03/05/14    F.E. Jones Construction, Inc.       
                                                            GC-5           -1,036                  02/06/14   03/05/14    F.E. Jones Construction, Inc.       
                                                            MC-1              620                  11/25/13   01/27/14    A.TREFFEISEN & SON,LLC              
                                                            MC-2               64                  01/17/14   02/24/14    A. Treffeisen & Son, LLC            
                                                            PC-1              -93                  12/26/13   02/04/14    United Plumbing & Heating, Inc.     
 
15-2002   Reconstruction               0-015-017  08/04/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            GC-1           -9,700                  12/16/16   12/22/16    David E. Stanton                    
 
18-0170   Reconstruction               0-015-018  09/04/18  NO CHANGE ORDERS ON ELECTRONIC FILE
21-1492   Reconstruction               0-015-020  01/12/23  NO CHANGE ORDERS ON ELECTRONIC FILE
23-0106   Reconstruction               0-015-021  01/02/24  NO CHANGE ORDERS ON ELECTRONIC FILE
02-2109FP Reconstruction               0-015-FP1  06/18/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Old Kindgtn House:
96-0431   Reconstruction               2-002-001  11/08/96  NO CHANGE ORDERS ON ELECTRONIC FILE

          Agriculture Bldg:
99-0104   Reconstruction               2-005-001  08/31/00  NO CHANGE ORDERS ON ELECTRONIC FILE

          NEW STORAGE #1:
01-0534   New Construction             2-016-001  06/11/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          NEW STORAGE #2:
01-0535   New Construction             2-017-001  06/11/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Bldg @ Unadilla Elementary:
08-0117   New Construction             2-019-001  12/10/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-2           -5,630                  05/26/09   08/13/09    FINGERLAKES CONSTRUCTION CO INC     
 

          XXStorage Bldg Otego ES (sold xxxx):
08-0118   Alterations                  2-020-001  12/10/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           -2,500                  05/21/09   08/19/09    ADVANCED POWER & LIGHT INC          
                                                            GC-1           -5,630                  05/26/09   08/13/09    FINGERLAKES CONSTRUCTION CO INC     
                                                            GC-3           -5,000                  05/26/09   08/13/09    FINGERLAKES CONSTRUCTION CO INC     
 

          Bus Garage:
01-0537   Reconstruction               5-006-003  06/11/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-2            8,165                  11/24/03     /  /      Nelcorp Elec.                       
                                                            EC-36             822                  01/26/05   06/29/05    Nelcorp electrical Contracting      
                                                            HC-42           3,038                  12/20/04   01/03/05    Kimble Inc                          
                                                            HC-5           50,692                  12/05/03   12/09/03    Kimble Inc                          
                                                            HC-50           4,641                  05/12/05   06/07/05    Kimble Inc                          
                                                            HC-56          -2,140                  04/28/05   06/21/05    Kimble Inc                          
                                                            HC-59           1,267                  05/24/06   01/30/07    Kimble Inc                          
                                                            PC-11          13,885                  12/08/04   01/03/05    Evans Mech.                         
                                                            PC-9           42,964                  11/10/04   10/03/05    Evans Mech.                         
 
05-1299   Reconstruction               5-006-004  07/11/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1                0                  12/12/06   01/09/07    Matco Electric                      
                                                            GC-1           10,103                  05/01/07   08/07/07    Orchard Earth and Pipe              
                                                            GC-10           5,520                  08/17/09   01/08/10    ORCHARD EARTH & PIPE CORP           
                                                            GC-2           40,772                  05/14/07   08/07/07    Orchard Earth and Pipe              
                                                            GC-3           20,125                  05/14/08   09/29/08    ORCHARD EARTH & PIPE CORP.          
                                                            GC-4           29,849                  10/08/08   01/26/09    ORCHARD EARTH & PIPE CORP.          
                                                            GC-5           20,427                  10/08/08   01/26/09    ORCHARD EARTH & PIPE CORP.          
                                                            GC-6           18,457                  11/19/08   07/08/09    ORCHARD EARTH & PIPE CORP.          
                                                            GC-7           18,457                  08/17/09   01/08/10    ORCHARD EARTH & PIPE CORP           
                                                            GC-8           18,457                  08/17/09   01/08/10    ORCHARD EARTH & PIPE CORP           
                                                            GC-9           12,259                  08/17/09   01/08/10    ORCHARD EARTH & PIPE CORP           
 
08-1215   Reconstruction               5-006-005  04/29/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-14             516                  08/23/10   11/26/10    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-2           18,747                  11/02/09   12/30/09    LECHASE CONSTRUCTION SERVICES LLC   
                                                            GC-5            1,104                  03/08/10   06/01/10    LECHASE CONSTRUCTION SERVICES LLC   
 
21-1493   Reconstruction               5-006-006  01/12/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Concession Stand:
01-0536   New Construction             7-018-001  06/11/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-25             285                  11/01/04   11/29/04    Nelcorp Elec.                       
 

          Districtwide:
11-1069   Reconstruction               7-999-001  06/08/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            7,650                  02/06/14   03/04/14    Matco Electric Corp.                
                                                            EC-2            8,441                  02/06/14   03/04/14    Matco Electric Corp.                
                                                            EC-3           -2,674                  03/02/15   03/26/15    Matco Electric Corp.                
 
20-0630   Reconstruction               7-999-002  01/06/21  NO CHANGE ORDERS ON ELECTRONIC FILE

COOPERSTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-17-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Elementary School:
94-0331   Additions and Alterations    0-002-005  11/29/94  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1429   Reconstruction               0-002-006  06/26/98  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1113   Reconstruction               0-002-007  07/19/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-2          -18,450                  09/14/01   01/08/02    Panko Elec.                         
                                                            EC-3           -4,784                  04/30/02   05/24/02    Panko Elec.                         
                                                            GC-3          -13,700                  09/14/01   01/08/02    Mancini Assoc.                      
                                                            GC-8           12,963                  03/25/02   05/23/02    Mancini Assoc.                      
                                                            GC-9             -444                  05/17/02   05/24/02    Mancini Assoc.                      
                                                            MC-1           -2,733                  02/12/02   04/05/02    B&H Air Conditioning Co             
                                                            PC-1            5,990                  09/14/01   01/08/02    Auchinachie Plumbing                
 
05-0478   Reconstruction               0-002-008  04/03/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-2            7,050                  01/02/07   01/19/07    M Gleason Plumbing                  
                                                            RC-2           34,876                  10/20/06   11/03/06    Murnane Building                    
                                                            RC-3           14,467                  10/20/06   11/03/06    Murnane Building                    
                                                            RC-5           16,800                  10/20/06   11/03/06    Murnane Building                    
                                                            RC-7            2,501                  04/21/08   08/06/08    MURNANE BUILDING CONT., INC.        
 
07-1077   Reconstruction               0-002-010  05/28/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA-1           16,000                  10/30/09   12/22/09    MIDLANTIC ENVIRONMENTAL INC         
                                                            AA-3           15,400                  05/26/10   07/20/10    MIDLANTIC ENVIRONMENTAL INC         
                                                            AA-4           16,133                  11/15/10   11/22/10    MIDLANTIC ENVIRONMENTAL INC         
                                                            AA-5            5,040                  11/15/10   11/22/10    MIDLANTIC ENVIRONMENTAL INC         
                                                            GC-10          -6,000                  11/25/09   01/12/10    CONMAS, INC.                        
                                                            GC-6           -4,000                  10/15/09   11/13/09    CONMAS INC                          
                                                            PC-1           -2,677                  03/23/09   06/17/09    H.J. BRANDELES CORP.                
                                                            PC-2           -2,183                  10/15/09   11/13/09    H.J. BRANDELES CORP                 
                                                            SC-1            7,280                  11/12/08   12/09/08    TITAN DEVELOPMENT, INC.             
                                                            SC-2           -3,270                  04/10/09   07/22/09    TITAN DEVELOPMENT, INC.             
 
08-0459   Reconstruction               0-002-011  04/10/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA-2           -5,557                  09/22/11   11/04/11    EXCEL INSULATION CO INC             
                                                            EC-2            4,648                  12/15/10   02/07/11    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            EC-4            6,373                  03/14/11   05/13/11    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            GC-10           6,285                  01/31/12   05/17/12    GEORGE A NOLE & SON INC             
                                                            GC-17           3,218                  02/17/12   06/22/12    GEORGE A NOLE & SON INC             
                                                            GC-3           14,292                  12/15/10   01/06/11    GEORGE A NOLE & SON INC             
                                                            GC-6            4,336                  01/21/11   02/28/11    GEORGE A NOLE & SON INC             
                                                            GC-8            6,517                  06/03/11   06/17/11    GEORGE A NOLE & SON INC             
                                                            MC-10           4,083                  02/17/12   08/09/13    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-2            6,074                  10/25/10   11/16/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-5            4,110                  12/15/10   02/07/11    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-6           20,484                  01/31/12   05/11/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-7            8,201                  01/31/12   05/11/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
 
14-0309   Reconstruction               0-002-012  11/18/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA-1          -15,000                  06/08/17   06/14/17    Midlantic Environmental, Inc.       
                                                            GC-1           34,997                  06/13/16   07/08/16    NATIONAL BUILDING & RESTORATION     
                                                            GC-3            6,086                  12/27/16   01/13/17    National Building & Restoration Corp
                                                            GC-4            6,985                  04/03/17   06/19/17    National Building & Restoration Corp
                                                            SC-1           20,153                  11/18/15   01/05/16    Boland's Excavating & Topsoil, Inc. 
                                                            SC-4           89,320                  12/11/15   12/28/15    Boland's Ecxavating & Topsoil, Inc. 
 
14-1627   Reconstruction               0-002-013  04/06/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-3            1,490                  11/17/17   12/01/17    Matco Electric Corp.                
                                                            GC-3            1,627                  12/06/17   12/26/17    Andrew R. Mancini Associates, Inc.  
 
17-0096   Reconstruction               0-002-014  10/12/17  NO CHANGE ORDERS ON ELECTRONIC FILE
19-0165   Reconstruction               0-002-015  02/05/20  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0675   Reconstruction               0-002-016  02/04/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC-3            1,645                  08/29/22   08/22/23    Burrells Excavting Inc              
 
22-0103   Reconstruction               0-002-017  10/17/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-2367   Reconstruction               0-002-018  11/06/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0691FP Reconstruction               0-002-FP1  01/22/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Junior/High School(was MS/HS):
94-0333   Additions and Alterations    0-006-003  11/29/94  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1427   Reconstruction               0-006-004  06/26/98  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1114   Reconstruction               0-006-005  07/19/00  NO CHANGE ORDERS ON ELECTRONIC FILE
05-0479   Reconstruction               0-006-006  04/03/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           18,000                  10/27/06   01/09/07    M Gleason and Sons                  
                                                            EC-3           -2,986                  02/22/07   03/08/07    M Gleason and Sons                  
                                                            RC-1           16,485                  10/20/06   11/03/06    Murnane Building                    
                                                            RC-4           17,772                  10/20/06   11/03/06    Murnane Building                    
                                                            RC-6          -17,355                  01/24/07   03/14/07    Murnane Building                    
 
07-1078   Reconstruction               0-006-008  05/28/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA-2            2,400                  10/30/09   12/22/09    MIDLANTIC ENVIRONMENTAL INC         
                                                            EC-1           10,761                  01/20/09   05/05/09    BAGNALL ELECTRIC, INC.              
                                                            EC-2            8,005                  11/05/09   01/19/10    BAGNALL ELECTRIC INC                
                                                            GC-1            4,411                  05/26/09   08/13/09    CONMAS INC                          
                                                            GC-11           2,949                  05/13/10   10/04/10    CONMAS INC                          
                                                            GC-12          -1,940                  10/25/10   11/16/10    ConMas Inc                          
                                                            GC-2          -30,690                  08/27/09   09/16/09    CONMAS INC                          
                                                            GC-3            3,421                  10/15/09   11/13/09    CONMAS INC                          
                                                            GC-4            5,864                  10/30/09   12/22/09    CONMAS INC                          
                                                            GC-5           -4,700                  10/15/09   11/13/09    CONMAS INC                          
                                                            GC-7           14,963                  11/25/09   01/12/10    CONMAS, INC.                        
                                                            GC-8           -1,000                  11/25/09   01/12/10    CONMAS,INC.                         
                                                            MC-1           -1,247                  10/30/09   12/22/09    H.J. BRANDELES CORP                 
 
08-0460   Reconstruction               0-006-009  04/10/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA-1           -2,010                  05/13/10   07/20/10    EXCEL INSULATION CO INC             
                                                            EC-1            6,410                  12/15/10   02/07/11    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            EC-5           -2,800                  09/22/11   11/08/11    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            EC-6           13,874                  01/31/12   05/11/12    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            EC-7              844                  02/17/12   09/12/12    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            GC-1           18,060                  12/15/10   02/07/11    GEORGE A NOLE & SON INC             
                                                            GC-11           6,709                  01/31/12   05/17/12    GEORGE A NOLE & SON INC             
                                                            GC-12          20,043                  01/31/12   05/17/12    GEORGE A NOLE & SON INC             
                                                            GC-13          22,685                  01/31/12   05/17/12    GEORGE A NOLE & SON INC             
                                                            GC-14          19,851                  01/31/12   05/17/12    GEORGE A NOLE & SON INC             
                                                            GC-15          14,902                  02/17/12   06/22/12    GEORGE A NOLE & SON INC             
                                                            GC-16          14,235                  02/17/12   06/22/12    GEORGE A NOLE & SON INC             
                                                            GC-18             448                  02/17/12   06/22/12    GEORGE A NOLE & SON INC             
                                                            GC-2            5,416                  12/15/10   01/06/11    GEORGE A NOLE & SON INC             
                                                            GC-5           18,191                  01/21/11   02/28/11    GEORGE A NOLE & SON INC             
                                                            GC-7            1,585                  01/21/11   02/28/11    GEORGE A NOLE & SON INC             
                                                            GC-9            8,004                  01/31/12   05/17/12    GEORGE A NOLE & SON INC             
                                                            MC - 12        20,243                  11/13/12   01/31/14    Piccirilli - Slavik & Vincent Plumbi
                                                            MC-1            4,895                  10/25/10   11/16/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-11           7,009                  02/17/12   09/12/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-12          20,243                  02/17/12   06/28/13    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-13          17,262                  06/14/12   01/24/13    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-4            1,186                  12/15/10   02/07/11    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-8           16,143                  01/31/12   05/11/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            MC-9            8,626                  02/17/12   09/12/12    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            PC-1           10,679                  01/31/12   05/11/12    SCHARF PLUMBING & HEATING INC       
                                                            PC-2            3,061                  07/09/12   07/29/13    SCHARF PLUMBING & HEATING INC       
 
14-0310   Reconstruction               0-006-010  11/18/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1           31,855                  09/11/15   10/28/15    Nelcorp Electrical Contracting Corp.
                                                            EC-2           -5,000                  11/25/15   12/28/15    Nelcorp Electrical Contracting Corp.
                                                            EC-3           28,664                  08/22/16   09/30/16    Nelcorp Electrical Contracting Corp 
                                                            EC-4            9,362                  10/17/16   11/01/16    Nelcorp Electrical Contracting Corp.
                                                            GC-5             -795                  06/08/17   06/14/17    National Building & Restoration Corp
                                                            SC-2            9,698                  11/18/15   01/05/16    Boland's Excavating & Topsoil, Inc. 
                                                            SC-3           20,030                  12/07/15   01/05/16    BOLAND'S EXCAVATING & TOPSOIL,INC.  
                                                            SC-5           18,805                  05/16/16   05/19/16    BOLAND'S EXCAVATING & TOPSOIL       
 
14-1626   Reconstruction               0-006-011  04/06/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1          -18,844                  10/12/17   11/10/17    Matco Electric Corp.                
                                                            EC-2            7,331                  11/17/17   12/01/17    Matco Electric Corp.                
                                                            EC-4            2,632                  11/17/17   12/01/17    Matco Electric Corp.                
                                                            GC-1           -2,400                  07/19/17   08/15/17    Andrew R. Mancini Associates, Inc.  
                                                            GC-2            4,464                  11/08/17   11/24/17    Andrew R. Mancini Associates, Inc.  
                                                            MC-1              877                  11/08/17   12/01/17    Piccirilli-Slavik & Vincent Plumbing
                                                            PC-1              735                  11/17/17   12/01/17    Piccirilli-Slavik & Vincent Plumbing
 
17-0097   Reconstruction               0-006-012  10/12/17  NO CHANGE ORDERS ON ELECTRONIC FILE
17-2077   Reconstruction               0-006-013  07/13/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SW-1           -3,000                  10/09/18   01/25/19    BOLANDS EXCAVATING & TOPSOIL INC    
 
19-0153   Reconstruction               0-006-014  09/17/19  NO CHANGE ORDERS ON ELECTRONIC FILE
19-0166   Reconstruction               0-006-015  10/16/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC-1           25,300                  08/09/21   04/21/22    CENTRAL PAVING, INC                 
                                                            SC-2            3,606                  08/09/21   04/21/22    CENTRAL PAVING, INC                 
 
20-0676   Reconstruction               0-006-016  02/04/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-1            8,799                  10/11/22   07/11/23    Schuler-Haas Elec Corp              
                                                            EC-2            4,951                  10/11/22   07/11/23    Schuler-Haas Elec Corp              
                                                            EC-3           12,976                  09/22/23     /  /      SCHULER-HAAS ELECTRIC CORP          
                                                            GC-1          -16,326                  07/25/22     /  /      Murnane Bldg Contrs Inc             
                                                            PC-1           -5,000                  10/11/22   07/11/23    Treffeisen&Son LLC                  
                                                            PC-2           -5,000                  10/11/22   07/11/23    Treffeisen&Son LLC                  
                                                            SC-1           -1,489                  08/29/22   08/22/23    Burrells Excavating Inc             
                                                            SC-2            2,420                  08/29/22   08/22/23    Burrells Excavating Inc             
 
21-0069   Reconstruction               0-006-017  08/11/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-1            4,505                  10/11/22   12/06/23    Andrew Mancini Assocs Inc           
                                                            GC-2            4,075                  10/11/22   12/06/23    Andrew Mancini Assocs Inc           
                                                            GC-3             -449                  03/16/23   12/19/23    ANDREW R. MANCINI                   
 
22-2368   Reconstruction               0-006-018  11/06/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0677FP Reconstruction               0-006-FP1  01/22/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage:
93-0096   Reconstruction               5-003-004  09/16/93  NO CHANGE ORDERS ON ELECTRONIC FILE
94-0332   Reconstruction               5-003-005  11/29/94  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1428   Reconstruction               5-003-006  06/26/98  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1112   Reconstruction               5-003-007  07/19/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-5            9,533                  10/09/01   05/23/02    Mancini Assoc.                      
                                                            GC-6            8,610                  10/09/01   05/23/02    Mancini Assoc.                      
 
07-1079   Reconstruction               5-003-009  05/28/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-9           -3,000                  11/25/09   01/12/10    CONMAS, INC.                        
                                                            RC-1             -525                  02/09/09   03/04/09    APPLE ROOFING CORP.                 
 
08-0461   Reconstruction               5-003-010  04/10/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            BL-1             -754                  04/05/10   06/14/10    FILTREC CORPORATION                 
                                                            BL-2           18,287                  06/17/10   08/05/10    FILTREC CORPORATION                 
                                                            BL-3           -5,000                  07/16/10   09/13/10    FILTREC CORPORATION                 
                                                            EC-3            3,498                  03/14/11   05/13/11    PANKO ELECTRICAL & MAINTENANCE INC  
                                                            GC-4           10,284                  01/21/11   07/29/11    GEORGE A NOLE & SON INC             
                                                            MC-3            8,934                  10/25/10   11/16/10    PICCIRILLI-SLAVIK & VINCENT P/H INC 
                                                            PT-1            7,268                  04/20/11   05/17/11    ORCHARD EARTH & PIPE CORP           
 
14-0311   Reconstruction               5-003-011  11/18/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            SC-6           10,940                  12/27/16   01/13/17    Boland's Excavating & Topsoil, Inc. 
                                                            SC-7           11,588                  01/11/17   01/13/17    Boland's Excavatimg & Topsoil, Inc. 
 
14-1628   Reconstruction               5-003-012  04/06/16  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0677   Reconstruction               5-003-013  02/04/21  NO CHANGE ORDERS ON ELECTRONIC FILE
21-2009   Reconstruction               5-003-014  08/03/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-1           -3,000                  08/25/23     /  /      MURNANE BUILDING CONTRACTORS        
 

          Press Box:
00-0009   New Construction             7-008-001  07/18/00  NO CHANGE ORDERS ON ELECTRONIC FILE

          Districtwide:
21-1234FA Reconstruction               7-999-002  02/17/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            MC-1           -2,790                  10/07/22   07/11/23    Family Danz Mech LLC                
                                                            MC-2            2,581                  12/16/22   11/27/23    Family Danz Mech LLC                
                                                            MC-3              437                  02/08/23   11/29/23    FAMILY DANZ MECH LLC                
 

RICHFIELD SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-20-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Building:
91-1507   Reconstruction               0-001-007  07/07/92  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0606   Reconstruction               0-001-008  03/07/94  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0737   Reconstruction               0-001-009  03/23/94  NO CHANGE ORDERS ON ELECTRONIC FILE
95-0002   Reconstruction               0-001-010  07/21/95  NO CHANGE ORDERS ON ELECTRONIC FILE
95-1264   Reconstruction               0-001-011  05/17/96  NO CHANGE ORDERS ON ELECTRONIC FILE
96-1124   Reconstruction               0-001-012  05/14/97  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1686   Reconstruction               0-001-013  07/13/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0633   Reconstruction               0-001-014  05/18/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-0877   Additions and Alterations    0-001-015  07/27/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AA-5           11,215                  05/26/04   07/21/04    Avala Contracting                   
                                                            AA-6           11,456                  05/26/04   07/21/04    Avala Contracting                   
                                                            AA-7              323                  05/26/04   07/21/04    Avala Contracting                   
                                                            AA1             8,950                  11/21/02   01/02/03    Avala Contracting                   
                                                            AA2            14,664                  11/21/02   01/02/03    Avala Contracting                   
                                                            AA3               687                  05/16/03   05/27/03    Avala Contracting                   
                                                            AA4             2,200                  05/16/03   05/27/03    Avala Contracting                   
                                                            E-3             2,504                  06/13/03   07/01/03    DC Elec.                            
                                                            E-4             2,964                  06/13/03   07/01/03    DC Elec.                            
                                                            E1             53,174                  01/06/03   01/10/03    DC Elec.                            
                                                            E2             -2,073                  06/13/03   07/01/03    DC Elec.                            
                                                            E5              4,111                  08/28/03   11/06/03    DC Elec.                            
                                                            GC-10           4,578                  01/22/04   01/02/08    Bette & Cring                       
                                                            GC-11           5,210                  01/22/04   02/18/04    Bette & Cring                       
                                                            GC-12          14,556                  05/26/04   01/02/08    Bette & Cring                       
                                                            GC-13           7,829                  05/26/04   01/02/08    Bette & Cring                       
                                                            GC-14           3,233                  05/26/04   01/02/08    Bette & Cring                       
                                                            GC-3           22,894                  01/13/03   02/06/03    Bette & Cring                       
                                                            GC-4            2,525                  01/06/03   01/10/03    Bette & Cring                       
                                                            GC-5           47,971                  01/13/03   02/06/03    Bette & Cring                       
                                                            GC-6            3,579                  05/16/03   05/27/03    Bette & Cring                       
                                                            GC-7           18,152                  06/02/03   06/09/03    Bette & Cring                       
                                                            GC-8          -26,914                  06/02/03   06/09/03    Bette & Cring                       
                                                            GC-9            1,166                  06/02/03   06/09/03    Bette & Cring                       
                                                            GC1                 0                  07/23/02   08/28/02    Bette & Cring                       
                                                            GC2           -59,838                  01/06/03   01/10/03    Bette & Cring                       
                                                            M-11            4,690                  04/13/05   01/02/08    Schamlz Mechanical Contractors      
                                                            M-12            1,437                  04/13/05   04/26/05    Schamlz mechanical Contractors      
                                                            M-6            -1,152                  05/26/04   01/02/08    Schmalz Mech. Contractors           
                                                            M-7            -4,574                  05/26/04   01/02/08    Schmalz Mech. Contractors           
                                                            M-8              -111                  05/26/04   07/21/04    Schmalz Mech. Contractors           
                                                            M1                232                  05/16/03   05/27/03    Schmalz Mech. Contractors           
                                                            M10                 0                  04/13/05   01/02/08    Schmalz Mechanical Contractors      
                                                            M2              4,098                  05/16/03   06/03/03    Schmalz Mech. Contractors           
                                                            M3                346                  05/16/03   06/02/03    Schmalz Mech. Contractors           
                                                            M4                  0                  05/16/03   06/03/03    Schmalz Mech. Contractors           
                                                            M5             -6,342                  01/23/04   01/30/04    Schmalz Mech. Contractors           
                                                            M9                  0                  04/20/05   04/26/05    Schmalz Mechanical Contractors      
                                                            P-2            13,910                  04/11/03   04/17/03    Superior Plumbing                   
                                                            P-3            20,144                  04/11/03   04/17/03    Superior Plumbing                   
                                                            P-4             8,998                  04/11/03   04/17/03    Superior Plumbing                   
                                                            P-5            10,141                  04/11/03   04/17/03    Superior Plumbing                   
                                                            P-6             1,488                  04/14/04   04/28/04    Superior Plumbing                   
                                                            P-7             6,861                  04/14/04   04/28/04    Superior Plumbing                   
                                                            P-8             6,282                  04/14/04   04/28/04    Superior Plumbing                   
                                                            P1                -44                  06/17/02   07/10/02    Superior Plumbing                   
 
99-1088   Reconstruction               0-001-016  05/01/00  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0746   Reconstruction               0-001-017  02/14/08  NO CHANGE ORDERS ON ELECTRONIC FILE
07-1374   Reconstruction               0-001-018  10/06/08  NO CHANGE ORDERS ON ELECTRONIC FILE
12-0940   Reconstruction               0-001-020  04/18/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            GC-001         31,037                  07/23/14   08/15/14    PCC Contracting, Inc.               
                                                            GC-002         25,800                  07/23/14   08/15/14    PCC Contracting, Inc.               
                                                            GC-003         -2,144                  07/23/14   11/05/14    PCC Contracting, Inc.               
                                                            GC-004          7,420                  07/23/14   08/15/14    PCC Contracting, Inc.               
                                                            GC-005         12,862                  07/23/14     /  /      PCC Contracting, Inc.               
                                                            GC-006          7,199                  07/23/14   08/15/14    PCC Contracting, Inc.               
                                                            GC-007         62,408                  07/23/14   08/15/14    PCC Contracting, Inc.               
                                                            RC-001          4,621                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-002          9,785                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-003         19,550                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-004         -1,830                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-005            328                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-006          2,124                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-007          1,823                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-008          4,269                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-009          7,876                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-010         51,460                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-011         14,895                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-012          1,389                  07/23/14   08/15/14    Titan Roofing, Inc.                 
                                                            RC-13           6,041                  07/23/14   08/15/14    Titan Roofing, Inc.                 
 
14-0164   Reconstruction               0-001-021  04/01/15  NO CHANGE ORDERS ON ELECTRONIC FILE
15-0267   Reconstruction               0-001-024  08/21/15  NO CHANGE ORDERS ON ELECTRONIC FILE
16-1366   Reconstruction               0-001-025  04/10/17  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0674   Reconstruction               0-001-026  01/31/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            OEC-001        15,312                  02/08/19   02/27/19    ONEIDA ELECTRICAL INC               
 
18-0581   Reconstruction               0-001-027  12/19/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC01-001            0                  08/20/19   08/21/19    ONEIDA ELECTRICAL CONTRACTORS,INC.  
                                                            EC01-002            0                  08/20/19   08/21/19    ONEIDA ELECTRICAL CONTRACTORS,INC.  
                                                            EC01-003            0                  10/03/19   10/17/19    ONEIDA ELECTRICAL CONTRACTORS, INC. 
                                                            EC01-004            0                  07/29/20   10/27/20    ONEIDA ELECTRICAL CONTRACTORS, INC. 
                                                            EC01-005            0                  11/13/20   02/16/21    ONEIDA ELECTRICAL CONTRACTORS, INC. 
                                                            EC01-006       -9,040                  11/27/20   02/01/21    ONEIDA ELECTRICAL CONTRACTORS, INC. 
                                                            GC01-004            0                  08/15/19   08/19/19    TRIVEDI CONSTRUCTION CORP.          
                                                            GC01-005            0                  08/15/19   08/19/19    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-001             0                  07/22/19   07/24/19    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-002        -5,167                  07/22/19   07/24/19    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-006             0                  12/20/19   01/28/20    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-007             0                  01/02/20   01/22/20    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-008             0                  08/12/20   09/29/20    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-009       -16,968                  09/10/20   11/25/20    TRIVEDI CONSTRUCTION CORP.          
                                                            GC1-010          -801                  09/30/20   12/02/20    TRIVEDI CONSTRUCTION CORP.          
                                                            HC01-001            0                  06/07/19   06/10/19    SCHMALZ MECHANICAL CONTRACTORS, INC.
                                                            HC01-002            0                  09/27/19   10/07/19    SCHMALZ MECHANICAL CONTRACTORS, INC 
                                                            HC01-004            0                  12/18/19   12/31/19    SCHAMLZ MECHANICAL CONTRACTORS,INC. 
                                                            HC01-005            0                  01/17/20   02/10/20    SCHMATS MECHANICAL CONTRACTORS      
                                                            HC01-006       -1,875                  09/10/20   11/05/20    SCHMALZ MECHANICAL CONTRACTORS      
                                                            HC01-007       -4,280                  10/14/20   12/18/20    SCHMALZ MECHANICAL CONTRACTORS      
                                                            HC01-008       -7,344                  10/14/20   12/18/20    SCHMALZ MECHANICAL CONTRACTORS      
                                                            MC01-001      106,445                  08/15/19   08/19/19    LUPINI CONSTRUCTION, INC.           
                                                            MC01-002            0                  10/03/19   10/10/19    LUPINI CONSTRUCTION, INC.           
                                                            MC01-003       -3,500                  12/18/19   01/02/20    LUPINI CONSTRUCTION, INC.           
                                                            MC01-004      -21,870                  10/26/20   12/31/20    LUPINI CONSTRUCTION, INC.           
                                                            RC01-001       -6,000                  12/21/20   04/02/21    PULVER ROOFING CO.,INC.             
                                                            RC01-002      -60,000                  12/21/20   04/02/21    PULVER ROOFING CO.,INC.             
 
18-0746   Reconstruction               0-001-028  12/19/18  NO CHANGE ORDERS ON ELECTRONIC FILE

CHERRY VALLEY-SPRINGFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-22-02-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Build. del./FSU/Sold:
04-1188   Reconstruction               0-001-004  07/11/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01           1,500                  10/27/06   12/19/06    Billbern Construction               
                                                            PC-01           4,622                  03/10/06   06/23/06    Orchard Earth pipe                  
                                                            PC-02          17,290                  08/14/06     /  /      Orchard Earth and Pipe              
 
02-1341   Reconstruction               0-001-FP1  03/18/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Main Building:
93-0433   Additions and Alterations    0-004-001  01/14/94  NO CHANGE ORDERS ON ELECTRONIC FILE
98-1631   Reconstruction               0-004-002  07/26/99  NO CHANGE ORDERS ON ELECTRONIC FILE
08-1341   Reconstruction               0-004-003  10/07/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ELEC-001        8,050                  10/08/10   10/29/10    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-002       10,229                  10/08/10   10/29/10    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-003       -2,630                  10/08/10   11/18/10    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-004          161                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-005        6,922                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-006        3,312                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-007        8,405                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-008        8,613                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-009        5,300                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-010       10,192                  03/03/11   04/12/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-011        2,854                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-012        7,149                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-013       -1,341                  03/03/11   03/23/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-014       19,659                  04/20/11   05/13/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-015        7,085                  04/20/11   05/13/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            ELEC-016        2,203                  07/06/12   12/13/12    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            GC-001              0                  10/08/10   10/29/10    GEORGE A NOLE & SON INC             
                                                            GC-002         31,865                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-003       -115,355                  03/03/11   04/12/11    GEORGE A NOLE & SON INC             
                                                            GC-004         45,118                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-005          8,009                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-006         -5,859                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-007         11,224                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-008          4,657                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-009          8,095                  03/03/11   03/23/11    GEORGE A NOLE & SON INC             
                                                            GC-010        -42,500                  07/18/12   01/24/13    GEORGE A NOLE & SON INC             
                                                            GC-011          6,983                  07/18/12   01/24/13    GEORGE A NOLE & SON INC             
                                                            GC-012         14,089                  07/18/12   01/24/13    GEORGE A NOLE & SON INC             
                                                            MECH-001        1,314                  10/08/10   10/29/10    H.J. BRANDELES CORP                 
                                                            MECH-002        2,802                  10/08/10   10/29/10    H.J. BRANDELES CORP                 
                                                            MECH-003          896                  04/20/11   05/13/11    H.J. BRANDELES CORP                 
                                                            MECH-004          621                  04/20/11   05/13/11    H.J. BRANDELES CORP                 
                                                            MECH-005        4,406                  04/20/11   05/13/11    H.J. BRANDELES CORP                 
                                                            MECH-006        3,604                  04/20/11   05/13/11    H.J. BRANDELES CORP                 
                                                            MECH-007       -9,125                  04/20/11   05/13/11    H.J. BRANDELES CORP                 
                                                            MECH-008        5,510                  04/20/11   05/13/11    H.J. BRANDELES CORP                 
                                                            PLUMB001       -3,994                  10/08/10   10/29/10    H.J. BRANDELES CORP                 
                                                            PLUMB002       -8,912                  03/03/11   03/23/11    H.J. BRANDELES CORP                 
                                                            PLUMB003            0                  03/03/11   03/23/11    H.J. BRANDELES CORP                 
                                                            PLUMB004       -3,339                  10/12/11   12/22/11    H.J. BRANDELES CORP                 
                                                            ROOF-001          282                  04/20/11   05/13/11    WEATHER GUARD ROOFING CO LLC        
                                                            ROOF-002        9,109                  04/20/11   05/13/11    WEATHER GUARD ROOFING CO LLC        
                                                            ROOF-003        1,793                  04/20/11   05/13/11    WEATHER GUARD ROOFING CO LLC        
                                                            ROOF-004       -1,566                  07/27/11   09/02/11    WEATHER GUARD ROOFING CO LLC        
                                                            SITE-001       90,825                  10/08/10   10/29/10    BOLAND'S EXCAVATING AND TOPSOIL INC 
                                                            SITE-002        1,991                  10/08/10   10/29/10    BOLAND'S EXCAVATING AND TOPSOIL INC 
                                                            SITE-003       12,657                  10/08/10   10/29/10    BOLAND'S EXCAVATING AND TOPSOIL INC 
                                                            SITE-004       -1,406                  03/03/11   03/23/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-005       10,647                  03/03/11   03/23/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-006       26,679                  03/03/11   04/12/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-007        6,918                  03/03/11   03/23/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-008       71,455                  03/03/11   03/23/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-009       48,038                  04/20/11   05/13/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-010        4,641                  04/20/11   05/13/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-011        2,789                  04/20/11   05/13/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-012       21,340                  04/20/11   05/13/11    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-013       89,200                  06/23/11   09/28/11    BOLAND'S EXCAVATION & TOPSOIL INC   
                                                            SITE-014      127,540                  07/16/12   11/28/12    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-015       29,180                  07/18/12   01/24/13    BOLAND'S EXCAVATING & TOPSOIL INC   
                                                            SITE-016       22,477                  08/27/12   12/14/12    BOLAND'S EXCAVATING AND TOPSOIL INC 
                                                            SITE-017        4,793                  09/20/12   01/24/13    BOLAND'S EXCAVATING AND TOPSOIL INC 
 
13-0369   Reconstruction               0-004-004  03/21/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001         21,367                  10/07/14     /  /      Mid State Industries, Ltd.          
                                                            GC-002         -5,000                  12/18/14   12/30/14    Mid State Industries, Ltd.          
                                                            MC-001              0                  08/07/14   09/04/14    A. Treffeisen & Sons, LLC.          
                                                            MC-002              0                  09/23/14   10/03/14    A. Treffeisen & Sons, LLC.          
                                                            MC-003            855                  11/04/14   11/14/14    A. Treffeisen & Sons, LLC.          
                                                            RC-001         12,000                  11/03/14   11/10/14    Mid State Industries Ltd.           
                                                            SC-001              0                  09/18/14   10/16/14    Colony Construction & Daughter, LLC 
                                                            SC-002          2,047                  11/12/14   11/21/14    Colony Construction & Daughter, LLC 
 
12-0132   Reconstruction               0-004-005  01/15/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001         -4,000                  07/05/13   07/24/13    View Tech Inc.                      
 
13-0986   Reconstruction               0-004-006  04/24/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001           -513                  06/03/15   06/17/15    Murnane Building Contractors, Inc.  
 
14-0445   Reconstruction               0-004-007  08/01/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            CC-003            740                  10/09/15   11/04/15    Colony Construction & Daughter, LLC.
 
16-0339   Reconstruction               0-004-008  09/15/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001         -4,000                  05/24/17   06/01/17    NEP Glass Co. Ltd.                  
                                                            PC2-6`03        2,930                  03/19/20     /  /      D.V. BROWN & ASSOCIATES             
 
17-0856   Reconstruction               0-004-009  10/03/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001          9,733                  12/12/19   01/09/20    MURNANE BUILDING CONTRACTORS, INC.  
                                                            HVAC-001       29,977                  06/17/20   07/15/20    CRISAFULLI BROS. PLUMBING & HEATING 
                                                            HVAC-002       15,840                  08/10/20   09/17/20    CRISAFULLI BROS. PLUMBING & HEATING 
                                                            HVAC-003       19,164                  02/16/21   04/09/21    CRISAFULLI BROS. PLUMBING & HEATING 
                                                            PL-002              0                  01/27/21   03/24/21    CRISAFULLI BROS. PLUMBING & HEATING 
                                                            SC-001         -3,540                  10/25/19   12/11/19    CNY EXCAVATING & CONCRETE,LLC       
 
16-1990   Reconstruction               0-004-010  06/30/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            CO-1           -1,833                  01/29/18   02/02/18    Hoosick Valley Contractors, Inc.    
 
18-1646   Reconstruction               0-004-011  05/13/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            CC-001          1,439                  12/23/19   01/07/20    GARNET TECHNOLOGY SOLUTIONS, INC.   
 
17-1589   Reconstruction               0-004-012  05/22/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001         -3,000                  01/09/19   02/06/19    NEP GLASS CO. LTD.                  
 
22-0720   Reconstruction               0-004-013  11/29/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2-01            7,155                  06/14/23   12/28/23    A.TREFFEISEN & SONS                 
 

          New Transportation Bldg.:
93-0472   New Construction             5-012-001  02/16/94  NO CHANGE ORDERS ON ELECTRONIC FILE
04-1189   Reconstruction               5-012-002  07/11/05  NO CHANGE ORDERS ON ELECTRONIC FILE
13-0370   Reconstruction               5-012-004  03/21/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            GC-001         21,367                  10/07/14   10/08/14    Mid State Industries, Ltd.          
                                                            SC-001              0                  09/18/14   10/16/14    Colony Construction & Daughter, LLC 
                                                            SC-002          2,047                  11/12/14   11/21/14    Colony Construction & Daughter, LLC 
 
17-0857   Reconstruction               5-012-005  10/03/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EL-001          2,493                  11/13/19   11/21/19    HAROLD R. CLUNE, INC.               
                                                            EL-002         11,156                  01/14/20   01/27/20    HAROLD R. CLUNE, INC.               
                                                            GC-002          1,664                  01/17/20   06/30/20    MURNANE BUILDING CONTRACTORS, INC.  
                                                            GC-003          6,284                  12/28/20   04/02/21    MURNANE BUILDING CONTRACTORS, INC.  
                                                            PL-001         10,151                  01/21/20   02/06/20    CRISAFULLI BROS. PLUMBING & HEATING 
 
17-0149   Reconstruction               5-012-006  09/29/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC-001            -50                  07/03/18   07/24/18    LAVALLEY BROS CONSTRUCTION INC      
 
22-1757   Reconstruction               5-012-007  05/01/23  NO CHANGE ORDERS ON ELECTRONIC FILE

WORCESTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-25-06-04
last updated on 01/10/24
REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Building:
96-1081   Reconstruction               0-001-004  04/11/97  NO CHANGE ORDERS ON ELECTRONIC FILE
09-0204   Additions and Alterations    0-001-005  12/18/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-001        13,827                  11/08/10   11/12/10    KASCON LLC                          
                                                            AAC-002        15,328                  04/03/12   10/22/12    KASCON LLC                          
                                                            AAC-003        17,617                  04/03/12   10/22/12    KASCON LLC                          
                                                            AAC-004        13,208                  04/03/12   04/22/14    KASCON LLC                          
                                                            AAC-005           -52                  04/03/12   10/22/12    KASCON LLC                          
                                                            EC-001         15,594                  02/22/11   03/18/11    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            EC-002R1       -2,606                  09/07/12   07/29/13    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            EC-003R1      -13,186                  08/15/12   07/29/13    FLEX ELECTRICAL CONSTRUCTORS INC    
                                                            GC-001         55,645                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-002         -3,117                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-003         -1,189                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-004         26,005                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-005         17,079                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-006         22,409                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-007         -3,018                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-008         27,475                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-009         -5,232                  09/10/10   09/28/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-010         19,607                  11/08/10   11/12/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-011         17,549                  11/08/10   11/12/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-012         44,318                  11/08/10   11/12/10    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-013        117,419                  12/23/10   02/09/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-014         -4,198                  02/22/11   03/18/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-015         34,403                  02/22/11   03/22/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-016          6,745                  02/22/11   03/18/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-017         13,431                  02/22/11   03/18/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-018         19,354                  02/22/11   03/18/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-019          4,064                  03/28/11   04/22/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-020         17,508                  04/08/11   05/05/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-021         22,498                  04/08/11   05/05/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-022         17,304                  06/06/11   07/15/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-023          3,110                  06/06/11   07/15/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-024         29,457                  08/04/11   09/02/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-025         13,130                  08/04/11   09/02/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-026          2,437                  08/04/11   09/02/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-027          2,690                  09/22/11   11/01/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-028          4,062                  09/22/11   11/01/11    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-029         10,534                  10/06/11   01/19/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-030         17,468                  10/06/11   01/19/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-031          9,456                  10/06/11   01/19/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-032            -14                  02/03/12   05/03/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-033            318                  02/15/12   06/12/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-035          1,368                  04/30/12   10/23/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-036           -951                  05/29/12   10/23/12    BUNKOFF GENERAL CONTRACTORS INC     
                                                            GC-037         45,497          45,497  11/02/12   03/11/13    BUNKOFF GENERAL CONTRACTORS INC     
                                                            HVAC-001       14,068                  02/22/11   01/31/14    GENERAL MECHANICAL SYSTEMS INC      
                                                            HVAC-002        6,577                  02/22/11   03/18/11    GENERAL MECHANICAL SYSTEMS INC      
                                                            HVAC-003       -2,488                  02/12/13   07/16/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            HVAC-004      -25,501                  02/12/13   09/19/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            PC-001          8,029                  03/28/11   04/22/11    GENERAL MECHANICAL SYSTEMS INC      
                                                            PC-002          5,186                  04/30/12   07/03/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            PC-003         13,129                  09/07/12   07/29/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            PC-004         -3,412                  02/12/13   09/19/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            RC-001          2,274                  03/07/12   04/22/14    MID-STATE INDUSTRIES LTD            
                                                            RC-002           -166                  04/03/12   10/22/12    MID-STATE INDUSTRIES LTD            
 
05-0197   Reconstruction               0-001-006  10/26/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-1            -2,370                  05/04/05   07/21/06    Hopkins Reilly mason Contrators     
 
09-0883   Reconstruction               0-001-007  06/23/10  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            CC-02          27,815                  02/03/12   05/03/12    NORTHEAST INTERIOR SYSTEMS INC      
                                                            CC-03           5,754                  04/30/12   10/23/12    NORTHEAST INTERIOR SYSTEMS INC      
                                                            CC-04           1,221                  09/07/12   12/19/12    NORTHEAST INTERIOR SYSTEMS INC      
                                                            EC-01          14,020                  09/22/11   11/09/11    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-02          18,690                  10/06/11   05/15/12    NELCORP ELECTRICAL CONSTRUCTION CORP
                                                            EC-03         117,285                  02/03/12   03/28/17    NELCORP ELECTRICAL CONTRACTIGN CORP 
                                                            EC-04          13,465                  02/03/12   05/15/12    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-05          17,845                  02/03/12   05/15/12    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-06          10,310                  02/15/12   09/18/12    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-07            -252                  04/03/12   01/10/13    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-08          14,939                  04/30/12   10/23/12    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-09           7,718                  04/30/12   07/03/13    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-10          11,209                  10/01/12   08/12/13    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-11           2,265                  04/01/13   07/16/13    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-12          16,595                  09/19/13   02/05/14    Nelcorp Electrical Contracting Corp.
                                                            EC-13           2,000                  10/28/13   12/04/13    Nelcorp Electrical Contracting Corp.
                                                            EC-15          19,840                  11/29/13   02/04/14    NELCORP ELECTRICAL CONTRACTING CORP.
                                                            EC-16          16,652                  11/29/13   02/04/14    NELCORP ELECTRICAL CONTRACTING CORP 
                                                            EC-17           2,863                  01/10/14   02/06/14    Nelcorp Electrical Contracting Corp.
                                                            FSC-01           -910                  07/28/11   09/02/11    JOSEPH FILHAN CO                    
                                                            FSC-02        -19,490                  11/26/12   03/11/13    JOSEPH FILHAN CO                    
                                                            FSC-03          2,772                  07/19/12   07/10/13    JOSEPH FILHAN CO                    
                                                            GC-01          -8,760                  12/17/10   01/06/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-02          11,752                  03/28/11   04/22/14    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-03          28,928                  04/08/11   05/05/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-04          20,197                  04/08/11   05/05/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-05          -2,327                  07/28/11   09/02/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-06          13,964                  09/22/11   11/01/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-07          11,944                  09/22/11   04/22/14    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-08           8,162                  09/22/11   11/01/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-09          23,268                  09/22/11   11/01/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-10          13,695                  09/22/11   11/01/11    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-11           1,364                  12/13/12   03/14/13    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-12          10,254                  12/19/11   06/12/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-13          24,642                  12/19/11   06/04/18    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-14          24,051                  12/13/12   03/14/13    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-15           2,985                  12/13/12   03/14/13    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-16           5,068                  02/03/12   05/03/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-17          15,927                  02/03/12   05/03/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-18          14,816                  02/15/12   06/12/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-19          14,223                  02/15/12   06/12/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-20           6,587                  02/15/12   06/12/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-21          14,717                  02/15/12   06/12/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-22R         11,205                  03/07/12   10/22/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-23           6,679                  03/07/12   10/22/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-24             -77                  03/07/12   04/29/14    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-25           3,522                  04/05/12   10/22/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-26           2,038                  04/30/12   10/23/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-27R2        -6,550                  07/06/12   11/28/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-28          10,389                  07/06/12   11/28/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-29           9,064                  07/06/12   11/28/12    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-30           5,357                  07/19/12   01/25/13    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-31             805                  10/04/12   02/22/13    HOOSICK VALLEY CONTRACTORS INC      
                                                            GC-32          10,564                  10/04/12   02/22/13    HOOSICK VALLEY CONTRACTORS INC      
                                                            HVAC-01        17,354                  10/06/11   05/15/12    GENERAL MECHANICAL SYSTEMS INC      
                                                            HVAC-02       -13,899                  02/12/13   09/19/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            HVAC-03        -9,216                  05/01/13   02/11/14    GENERAL MECHANICAL SYSTEMS, INC.    
                                                            PC-01          -2,912                  02/12/13   09/19/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            PC-02          -2,889                  02/12/13   09/19/13    GENERAL MECHANICAL SYSTEMS INC      
                                                            TEC-01         -9,490                  02/15/12   06/12/12    SYRACUSE SCENERY & STAGE LIGHTING CO
 
11-1305   Reconstruction               0-001-008  06/08/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            RC-001        -14,750                  08/08/13   11/25/13    Mid-State Industries, Ltd.          
 
12-0729   Reconstruction               0-001-009  02/13/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            ERC-01         -2,005                  01/10/14   02/07/14    Sullivan Contracting, Inc.          
                                                            FC-01            -718                  01/10/14   02/07/14    The Western New York Floor Co., Inc.
 
17-2062   Reconstruction               0-001-010  08/28/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -2,421                  10/08/20   02/04/21    UPSTATE COMPANIES I, LLC            
                                                            1-02          -71,927                  10/08/20   02/04/21    UPSTATE COMPANIES I, LLC            
                                                            100-01              0                  10/28/20   02/08/21    UPSTATE COMPANIES I, LLC            
                                                            100-02              0                  10/28/20   02/09/21    UPSTATE COMPANIES I, LLC            
                                                            2-01           -4,893                  10/08/20   02/04/21    THOMPSON BROTHERS, INC.             
                                                            2-02            3,068                  10/08/20   02/04/21    THOMPSON BROTHERS, INC.             
                                                            2-03           -2,146                  10/08/20   02/04/21    THOMPSON BROTHERS, INC.             
                                                            2-04             -107                  10/08/20   02/04/21    THOMPSON BROTHERS, INC.             
                                                            2-05           21,233                  10/08/20   02/04/21    THOMPSON BROTHERS, INC.             
                                                            2-06             -448                  10/08/20   02/04/21    THOMPSON BROTHERS, INC.             
                                                            2-07            4,800                  10/28/20   02/08/21    THOMPSON BROTHERS, INC.             
                                                            200-01              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-02              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-03              0                  02/10/21   04/14/21    THOMPSON BROTHERS, INC.             
                                                            200-04              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-05              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-06              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-07              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-08              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-09              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-10              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            200-11              0                  10/28/20   02/09/21    THOMPSON BROTHERS, INC.             
                                                            300-01              0                  07/18/19   07/22/19    HAROLD R. CLUNE, INC.               
 
22-0739FA Reconstruction               0-001-013  12/14/22  NO CHANGE ORDERS ON ELECTRONIC FILE
22-1186FA Reconstruction               0-001-014  02/13/23  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2-01          -88,691                  09/21/23   12/18/23    T. MCELLIGOTT INC                   
 
03-0119FP Reconstruction               0-001-FP1  10/14/03  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1840SC Visual Structural Inspection 0-001-SC1  04/07/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXAnnex/Bus Garage:
91-0066   Reconstruction               0-002-002  09/05/91  NO CHANGE ORDERS ON ELECTRONIC FILE
08-0176   Reconstruction               0-002-003  02/05/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAC-01            833                  08/26/10   09/13/10    KASCON LLC                          
                                                            EC-01          -1,680                  08/26/10   09/13/10    A. TREFFEISEN & SONS LLC            
                                                            PC-01               0                  08/26/10   09/13/10    A. TREFFEISEN & SONS LLC            
                                                            SC-02          12,244                  08/26/10   09/13/10    EDWARD V NADEAU & SONS INC          
                                                            SC-04            -599                  08/26/10   09/13/10    EDWARD V NADEAU & SONS INC          
 

          Storage Building:
10-0602   New Construction             2-004-001  05/19/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01          10,196                  06/29/12   01/10/13    Nelcorp Electrical Contracting Corp.
                                                            EC-02           6,337                  12/17/12   08/12/13    Nelcorp Electrical Contracting Corp.
                                                            GC-01            -941                  02/03/12   05/23/12    EASTERN BUILDING & RESTORATION INC  
                                                            GC-02          -9,195                  04/30/12   10/05/12    EASTERN BUILDING & RESTORATION INC  
                                                            HVAC-01       -10,000                  11/02/12   07/16/13    HT LYONS                            
                                                            PC-01             371                  03/07/12   09/18/12    HT LYONS                            
 

          Pole Barn:
17-2063   New Construction             2-005-001  08/28/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            3-02            2,166                  10/28/20   01/11/21    HAROLD R. CLUNE, INC.               
 

          New Bus Garage:
08-0175   New Construction             5-003-001  02/05/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01         -11,195                  08/26/10   09/13/10    BEEBE CONSTRUCTION SERVICES         
                                                            HVAC-01        -7,213                  08/26/10   09/13/10    GENERAL MECHANICAL SYSTEMS INC      
                                                            PC-02          -2,593                  08/26/10   09/13/10    A. TREFFEISEN & SONS LLC            
                                                            SC-01            -915                  08/26/10   09/13/10    EDWARD V NADEAU & SONS INC          
                                                            SC-03               0                  08/26/10   09/13/10    EDWARD V NADEAU & SONS INC          
 
17-2064   Reconstruction               5-003-002  08/28/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            3-01            8,081                  10/28/20   01/11/21    HAROLD R. CLUNE, INC.               
 

          Pavilion:
22-1230FA New Construction             7-007-001  12/14/22  NO CHANGE ORDERS ON ELECTRONIC FILE