Change Order Status - Jefferson


SOUTH JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-01-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Wilson Elementary:
00-0885   Reconstruction               0-001-006  06/20/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1.02            5,257                  06/17/02   08/15/02    Purcell Const.                      
 
01-0672   Additions and Alterations    0-001-007  04/26/02  NO CHANGE ORDERS ON ELECTRONIC FILE
08-0507   Reconstruction               0-001-008  03/25/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-003              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-010              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-013              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-017         -1,552                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            GC-005              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-006              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-009              0                  05/27/11   07/19/11    BETTE & CRING LLC                   
                                                            GC-017              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            GC-019              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            GC-020        -31,076                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            MC-011        -11,720                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-002              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            SC-001         57,969                  05/07/10   08/05/10    LANDMARK ENTERPRISES                
                                                            SC-006         12,753                  05/27/11   07/15/11    LANDMARK ENTERPRISES                
                                                            SC-007         17,992                  05/27/11   07/15/11    LANDMARK ENTERPRISES                
 
17-1181   Reconstruction               0-001-009  12/14/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01           8,064                  12/09/19   12/19/19    DOW ELECTRIC                        
                                                            GC-03          -9,260                  12/09/19   12/20/19    CON TECH BUILDING SYSTEMS           
                                                            GC-05           2,171                  12/09/19   12/20/19    CON TECH BUILDING SYSTEMS           
                                                            SC-01          31,429                  12/09/19   12/20/19    CUNNINGHAM EXCAVATING               
                                                            SC-03          23,596                  12/09/19   12/20/19    CUNNINGHAM EXCAVATING               
                                                            SC-06           6,823                  12/09/19   12/20/19    CUNNINGHAM EXCAVATION               
                                                            SC-10           2,828                  02/24/20   06/12/20    CUNNINGHAM EXCAVATION               
 
20-0353   Reconstruction               0-001-010  11/17/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01          12,854                  04/27/21   08/03/21    WATSON ELECTRIC, INC.               
                                                            EC-02          15,223                  04/27/21   08/03/21    WATSON ELECTRIC, INC.               
                                                            EC-03           2,416                  04/27/21   08/03/21    WATSON ELECTRIC, INC.               
 
21-0316   Reconstruction               0-001-011  12/21/21  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1364FP Reconstruction               0-001-FP1  02/13/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXAdams ES (Scholtz Bldg) Sold 2005:
93-1565   Reconstruction               0-004-003  07/25/94  NO CHANGE ORDERS ON ELECTRONIC FILE
00-0886   Reconstruction               0-004-004  06/20/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1.02              439                  05/06/03   05/07/03    Blackstone Elec.                    
 

          Clarke Jr/Sr High School:
00-0887   Reconstruction               0-005-003  06/20/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1.01          -35,049                  12/07/01   04/05/02    Purcell Const.                      
                                                            1.01          -47,607                  12/07/01   04/05/02    Blackstone Elec.                    
 
01-0673   Additions and Alterations    0-005-004  04/26/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            E-4            15,883                  01/27/04   10/22/04    Watson Elec.                        
                                                            E-5             1,059                  03/15/04   04/23/04    Watson Elec.                        
                                                            E-8            16,277                  09/27/04   10/22/04    Watson Elec.                        
                                                            E10            10,589                  04/21/05   06/07/05    Watson Electric                     
                                                            E12            13,350                  08/24/05   09/01/05    watson Electric                     
                                                            E2                  0                  08/26/03   09/09/03    Watson Elec.                        
                                                            GC-1             -220                  03/17/03   03/19/03    Bette & Cring                       
                                                            GC-11          30,995                  01/26/04   01/29/04    Bette & Cring                       
                                                            GC-13          32,756                  03/15/04   04/06/04    Bette & Cring                       
                                                            GC-15           7,024                  05/24/04   06/10/04    Bette & Cring                       
                                                            GC-17           8,296                  08/24/04   09/24/04    Bette & Cring                       
                                                            GC-2         -234,970                  06/02/03   06/04/03    Bette & Cring                       
                                                            GC-20          30,653                  09/27/04   10/13/06    Bette & Cring                       
                                                            GC-22         -10,123                  09/27/04   10/04/04    Bette & Cring                       
                                                            GC-23           3,490                  04/05/05   06/21/05    Bette Cring                         
                                                            GC-4          -28,477                  08/26/03   09/09/03    Bette & Cring                       
                                                            GC-6          -66,260                  08/26/03   09/09/03    Bette & Cring                       
                                                            GC-8          -33,439                  11/03/03   12/02/03    Bette & Cring                       
                                                            H-10            1,786                  11/23/05   10/13/06    Northern mechanicals                
                                                            H-2                 0                  08/26/03   09/09/03    Northern Mech.                      
                                                            H-3                 0                  01/26/04   02/02/04    Northern Mech.                      
                                                            H-4                 0                  03/15/04   04/23/04    Northern Mech.                      
                                                            H-6             9,464                  02/26/05   07/26/05    Northern Mechanical                 
                                                            P-12           15,903                  09/24/04   10/12/04    Brosh Mech.                         
                                                            P-15            1,833                  04/21/05   06/07/05    Brosh Mechanical                    
                                                            P-5             9,995                  01/26/04   11/29/04    Brosh Mech.                         
                                                            P-8             2,696                  03/15/04   04/23/04    Brosh Mech.                         
                                                            P2                  0                  08/26/03   09/09/03    Brosh Mech.                         
                                                            P3             15,152                  08/25/03   09/09/03    Brosh Mech.                         
                                                            S-2            25,841                  09/04/03   09/16/03    Acts II Const.                      
                                                            S-4             6,778                  05/24/04   06/10/04    Acts II Const.                      
                                                            S-6             8,692                  07/26/04   09/09/04    Acts II Const.                      
                                                            S8             34,664                  08/24/04   10/01/04    Acts II Const.                      
 
08-0508   Reconstruction               0-005-005  03/25/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-005              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-006              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-009              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-011              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-012              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-014              0                  12/05/12     /  /      WATSON ELECTRIC INC                 
                                                            EC-015              0                  12/05/12     /  /      WATSON ELECTRIC INC                 
                                                            EC-016         -1,552                  12/05/12   02/27/13    WATSON ELECTRIC                     
                                                            EC-019         -1,261                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            GC-003              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-004              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-011              0                  05/27/11   07/15/11    BETTE & CRING LLC                   
                                                            GC-012              0                  05/27/11   07/15/11    BETTE & CRING LLC                   
                                                            GC-015              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            GC-016              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            GC-018              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            MC-001         16,658                  12/13/12   12/30/13    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-005            606                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-006          5,257                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-009              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-010              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-001              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-009          2,107                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-010            812                  12/13/12   03/14/13    J&A MECHANICAL CONTRACTORS INC      
                                                            SC-002         12,638                  05/07/10   08/05/10    LANDMARK ENTERPRISES                
                                                            SC-003          4,750                  05/07/10   08/05/10    LANDMARK ENTERPRISES                
                                                            SC-004         17,155                  05/07/10   08/05/10    LANDMARK ENTERPRISES                
                                                            SC-005          3,000                  05/07/10   08/05/10    LANDMARK ENTERPRISES                
                                                            SC-008         19,101           1,950  05/27/11   07/15/11    LANDMARK ENTERPRISES                
                                                            SC-009         17,834                  05/27/11   07/15/11    LANDMARK ENTERPRISES                
                                                            SC-011          5,997                  04/29/13   07/12/13    LANDMARK ENTERPRISES                
 
14-0215   Reconstruction               0-005-006  04/23/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001             5,950                  08/12/16   09/30/16    Hyde-Stone Mechanical Contractors   
                                                            EC-001         32,006                  09/02/15   10/26/15    Watson Electric Inc.                
                                                            EC-002           -132                  12/02/16   01/06/17    Watson Electric, Inc.               
                                                            GC-002         16,951                  09/02/15   10/28/15    Con Tech Building Systems Inc.      
                                                            GC-004            851                  09/02/15   10/28/15    Con Tech Building Systems Inc.      
 
16-0660   Reconstruction               0-005-007  11/07/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            eC-001         12,000                  06/12/17   06/21/19    Dow Electric, Inc.                  
 
16-0934   Reconstruction               0-005-008  01/12/17  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1182   Reconstruction               0-005-009  12/14/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-03           7,520                  01/13/20   02/03/20    DOW ELECTRIC                        
                                                            EC-06           1,150                  01/13/20   02/03/20    DOW ELECTRIC                        
                                                            EC-07            -201                  01/22/20   02/19/20    DOW ELECTRIC                        
                                                            GC-02          27,600                  12/09/19   12/20/19    CON TECH BUILDING SYSTEMS           
                                                            GC-04           2,054                  01/22/20   03/10/20    CON TECH BUILDING SYSTEMS           
                                                            GC-06          13,225                  12/09/19   12/20/19    CON TECH BUILDING SYSTEMS           
                                                            GC-07          -1,009                  12/09/19   12/20/19    CON TECH BUILDING SYSTEMS           
                                                            GC-08           4,868                  07/24/20   09/22/20    CON TECH BUILDING SYSTEMS           
                                                            GC-09            -230                  07/24/20   09/22/20    CON TECH BUILDING SYSTEMS           
                                                            MC-01          -5,501                  12/09/19   12/19/19    ENI MECHANICAL, INC.                
                                                            PC-01            -370                  02/24/20   07/02/20    HYDE-STONE MECHANICAL               
                                                            SC-02          24,864                  12/09/19   01/22/20    CUNNINGHAM EXCAVATING               
                                                            SC-04          21,449                  12/09/19   12/20/19    CUNNINGHAM EXCAVATING               
                                                            SC-08          11,070                  02/24/20   06/12/20    CUNNINGHAM EXCAVATION               
                                                            SC-09          18,190                  02/24/20   06/12/20    CUNNINGHAM EXCAVATION               
                                                            SC-11          10,660                  02/24/20   06/12/20    CUNNINGHAM EXCAVATION               
                                                            SC-12            -197                  07/24/20   09/22/20    CUNNINGHAM EXCAVATION               
                                                            SC-13          -8,590                  12/15/20   04/06/21    CUNNINGHAM EXCAVATING               
 
17-0764   Reconstruction               0-005-010  02/16/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01          15,687                  06/20/18   07/24/18    S.C.SPENCER ELECTRIC                
 
18-0533   Reconstruction               0-005-011  12/13/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001         29,300                  05/06/19   05/07/19    ROMBOUGH ELECTRIC INC.              
                                                            EC-002          4,576                  06/20/19   06/24/19    ROMBOUGH ELECTRIC, INC.             
 
19-0971   Reconstruction               0-005-013  04/10/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01           3,587                  12/15/20   03/09/21    S&L ELECTRIC, INC.                  
                                                            EC-02           2,200                  04/27/21   07/15/21    S&L ELECTRIC, INC.                  
                                                            EC-03            -530                  04/27/21   08/03/21    S&L ELECTRIC, INC.                  
                                                            GC-02             561                  12/15/20   04/06/21    BLACK HORSE GROUP, LLC              
                                                            GC-03           6,919                  12/15/20   04/06/21    BLACK HORSE GROUP, LLC              
                                                            GC-04           2,304                  12/15/20   04/06/21    BLACK HORSE GROUP, LLC              
                                                            GC-05            -223                  04/27/21   08/12/21    BLACK HORSE GROUP, LLC              
                                                            GC-06          29,295                  09/01/21   05/11/22    BLACK HORSE GROUP, LLC              
                                                            GC-07          20,876                  09/01/21   05/11/22    BLACK HORSE GROUP, LLC              
                                                            GC-08          16,255                  09/01/21   05/11/22    BLACK HORSE GROUP, LLC              
                                                            GC-1            2,029                  10/07/20   02/09/21    BLACK HORSE GROUP, LLC              
                                                            MC-01           6,064                  02/11/21   04/08/21    HYDE-STONE MECHANICAL               
                                                            MC-02          -2,000                  04/27/21   08/03/21    HYDE-STONE MECHANICAL               
 
20-1023   Reconstruction               0-005-014  01/08/21  NO CHANGE ORDERS ON ELECTRONIC FILE
21-1971   Reconstruction               0-005-015  08/02/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001              0                  05/01/23   12/27/23    S&L ELECTRIC                        
                                                            EC-002              0                  05/01/23   12/27/23    S&L ELECTRIC                        
                                                            EC-003            -70                  06/26/23     /  /      S&L ELECTRIC                        
 
23-0224   Reconstruction               0-005-017  09/20/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1329FP Reconstruction               0-005-FP1  02/13/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Mannsville Elementary:
00-0888   Reconstruction               0-006-003  06/20/01  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0674   Additions and Alterations    0-006-004  04/26/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            E-3             5,335                  01/26/04   02/02/04    Watson Elec.                        
                                                            E-6               732                  03/15/04   04/23/04    Watson Elec.                        
                                                            E-7             3,440                  09/24/04   10/14/04    Watson Elec.                        
                                                            E1                  0                  08/26/03   10/13/06    Watson Elec.                        
                                                            E13             6,261                  08/24/05   09/01/05    Watson Electric                     
                                                            E9              7,275                  04/21/05   06/07/05    Watson Electric                     
                                                            GC-10           2,628                  01/26/04   01/29/04    Bette & Cring                       
                                                            GC-12          29,095                  03/15/04   04/07/04    Bette & Cring                       
                                                            GC-14          20,208                  05/24/04   06/30/04    Bette & Cring                       
                                                            GC-16          20,770                  08/24/04   10/01/04    Bette & Cring                       
                                                            GC-19             869                  09/24/04   10/04/04    Bette & Cring                       
                                                            GC-21          -5,000                  09/27/04   10/04/04    Bette & Cring                       
                                                            GC-3          -39,309                  08/26/03   09/09/03    Bette & Cring                       
                                                            GC-5                0                  08/26/03   09/09/03    Bette & Cring                       
                                                            GC-7                0                  08/26/03   09/09/03    Bette & Cring                       
                                                            GC-9                0                  11/03/03   11/21/03    Bette & Cring                       
                                                            H-1                 0                  08/26/03   09/09/03    Northern Mech.                      
                                                            H-11            1,786                  11/23/05   10/13/06    Northern mechanical                 
                                                            H-5             4,623                  03/15/04   04/23/04    Northern Mech.                      
                                                            H-7             1,083                  02/26/05   07/26/05    Northern Mechanical                 
                                                            H-8           -10,000                  02/26/05   07/26/05    Northern Mechanicals Inc            
                                                            H-9           -10,000                  02/26/05   07/26/05    Northern Mechanical Inc             
                                                            P-1                 0                  03/17/03   03/19/03    Brosh Mech.                         
                                                            P-11            1,823                  05/24/04   06/10/04    Brosh Mech.                         
                                                            P-13          -20,000                  09/24/04   10/12/04    Brosh Mech.                         
                                                            P-7            11,448                  04/15/04   04/23/04    Brosh Mech.                         
                                                            P4             22,500                  08/26/03   09/16/03    Brosh Mech.                         
                                                            S-3               613                  09/15/03   09/19/03    Acts II Const.                      
                                                            S-5             7,298                  07/26/04   09/09/04    Acts II Const.                      
                                                            S-7             3,491                  08/24/04   10/01/04    Acts II                             
                                                            S1                  0                  08/26/03   09/09/03    Acts II Const.                      
                                                            p-6               288                  01/26/04   10/18/04    Brosh mechanical                    
 
08-0509   Reconstruction               0-006-005  03/25/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-008              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-018         -1,552                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            GC-007              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-010              0                  05/27/11     /  /      BETTE & CRING LLC                   
                                                            GC-013              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            MC-002         20,557                  04/29/13   07/12/13    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-004          1,649                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-008              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-005              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-008              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            SC-010          2,901                  05/27/11   07/15/11    LANDMARK ENTERPRISES                
 
14-0216   Reconstruction               0-006-006  04/23/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            002             1,600                  08/12/16   09/30/16    Hyde-Stone Mechanical Contractors   
                                                            005              -766                  07/01/16   08/01/16    Con Tech Building Systems, Inc.     
                                                            GC-001         19,203                  09/02/15   10/26/15    Con Tech Building Systems Inc.      
                                                            GC-003         -7,627                  09/02/15   10/28/15    Con Tech Building Systems Inc.      
 
17-1183   Reconstruction               0-006-007  12/14/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-04           6,554                  01/13/20   02/03/20    DOW ELECTRIC                        
                                                            GC-01          33,007                  12/09/19   12/24/19    CON TECH BUILDING SYSTEMS           
 
19-0440   Reconstruction               0-006-008  10/18/19  NO CHANGE ORDERS ON ELECTRONIC FILE

          Adams Bus Garage@WilsonES:
92-1369   Reconstruction               5-002-002  07/06/93  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1131   Reconstruction               5-002-003  03/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
01-0676   Reconstruction               5-002-004  04/26/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E11               508                  04/21/05   06/07/05    Watson electric Inc                 
                                                            GC-18          27,282                  08/24/04   10/01/04    Bette Cring                         
                                                            GC-24           3,109                  04/05/05   04/26/05    Bette Cring                         
                                                            P-14          -14,267                  04/21/05   09/09/05    Brosh mechanical                    
                                                            P-9             1,996                  03/15/04   04/23/04    Brosh Mech.                         
 
08-0510   Additions and Alterations    5-002-005  03/25/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-002              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            EC-007              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            GC-001              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-002              0                  10/08/10   10/29/10    BETTE & CRING LLC                   
                                                            GC-014              0                  05/30/12   10/23/12    BETTE & CRING LLC                   
                                                            MC-003         14,335                  04/06/11   05/05/11    J&A MECHANICAL CONTRACTORS INC      
                                                            MC-007              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-003              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
                                                            PC-007              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
 
14-0217   Reconstruction               5-002-006  04/23/15  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1185   Reconstruction               5-002-007  12/14/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC-005         13,630                  12/09/19   12/20/19    CUNNINGHAM EXCAVATION               
                                                            SC-07             321                  02/24/20   06/12/20    CUNNINGHAM EXCAVATION               
 
19-0041   Reconstruction               5-002-008  07/19/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC2-01         -3,000                  01/22/20   02/21/20    HILL HIGH EXCAVATION, LLC           
 

          Press Box / Concession Building:
08-0511   Reconstruction               7-009-002  03/25/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-004              0                  12/05/12   02/27/13    WATSON ELECTRIC INC                 
                                                            GC-008              0                  10/08/10   11/09/10    BETTE & CRING LLC                   
 

          Clarke Storage and Concession Stand:
08-0512   New Construction             7-010-001  03/25/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PC-006              0                  12/05/12   02/27/13    J&A MECHANICAL CONTRACTORS INC      
 

          Press Box @ Jr/Sr High School:
17-1186   New Construction             7-017-001  12/14/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-02           2,073                  12/09/19   12/19/19    DOW ELECTRIC                        
                                                            EC-05          -7,000                  01/13/20   02/03/20    DOW ELECTRIC                        
 

          District-Wide:
21-0263   Reconstruction               7-999-002  01/13/22  NO CHANGE ORDERS ON ELECTRONIC FILE

ALEXANDRIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-02-02-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Alexandria Central:
94-0787   Additions and Alterations    0-001-003  03/02/95  NO CHANGE ORDERS ON ELECTRONIC FILE
94-0378   Reconstruction               0-001-004  11/22/94  NO CHANGE ORDERS ON ELECTRONIC FILE
96-1755   Reconstruction               0-001-005  07/30/97  NO CHANGE ORDERS ON ELECTRONIC FILE
00-0068   Additions and Alterations    0-001-006  02/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1               3,987           3,987  08/18/03   09/09/03    Northern Mech.                      
                                                            1              15,405                  05/08/06   05/22/06    Phase 4 Builders, Inc.              
                                                            1              -3,150                  05/08/06   05/22/06    Bette & Cring                       
                                                            10             39,680                  06/10/03   06/13/03    Phase 4 Builders                    
                                                            10            -53,566                  09/26/03   10/03/03    Bette & Cring                       
                                                            10             39,680                  01/13/04   02/18/04    Phase 4 Builders                    
                                                            11              3,480                  07/14/03   07/23/03    Phase 4 Builders                    
                                                            11            -21,912                  05/28/04   07/14/04    Bette & Cring                       
                                                            12              4,730                  06/10/03   05/22/06    Phase 4 Builders                    
                                                            13                880                  07/14/03   07/23/03    Phase 4 Builders                    
                                                            14              8,335                  10/22/03   11/06/03    Phase 4 Builders                    
                                                            2             187,646                  09/25/02   10/30/02    AJ Montclair                        
                                                            2               4,730                  01/30/03   02/11/03    Phase 4 Builders                    
                                                            2               9,185           9,185  08/18/03   09/09/03    Northern Mech.                      
                                                            2               6,562                  06/29/04   07/14/04    Empire Northeast                    
                                                            2              17,753                  05/08/06   05/22/06    Bette & Cring                       
                                                            3               6,760                  09/25/02   10/30/02    AJ Montclair                        
                                                            3               1,578                  08/18/03   09/09/03    Northern Mech.                      
                                                            3               9,658                  09/04/03   09/16/03    Phase 4 Builders                    
                                                            3              23,292          23,292  06/29/04   07/14/04    Empire Northeast                    
                                                            3              16,654                  05/08/06   05/22/06    Bette & Cring                       
                                                            4               4,098                  10/23/02   12/02/02    Bette & Cring                       
                                                            4              28,000                  06/09/03   06/10/03    AJ Montclair                        
                                                            4               8,799           8,799  08/18/03   09/09/03    Northern Mech.                      
                                                            4               2,454           1,370  09/04/03   09/16/03    Phase 4 Builders                    
                                                            4               8,440                  06/29/04   07/14/04    Empire Northeast                    
                                                            5               2,200                  10/29/02   12/02/02    Bette & Cring                       
                                                            5               6,850                  06/09/03   06/10/03    AJ Montclair                        
                                                            5               3,033                  09/04/03   09/16/03    Phase 4 Builders                    
                                                            5              -6,784          -1,126  01/13/04   02/03/04    Northern Mech.                      
                                                            5               5,163                  06/29/04   07/14/04    Empire Northeast                    
                                                            6                 772                  10/29/02   12/02/02    Bette & Cring                       
                                                            6              10,234                  06/09/03   06/10/03    AJ Montclair                        
                                                            6               3,665                  09/04/03   09/16/03    Phase 4 Builders                    
                                                            7              22,147                  05/02/03   05/21/03    Bette & Cring                       
                                                            7               8,757                  09/04/03   09/16/03    Phase 4 Builders                    
                                                            7              -3,628                  09/08/03   11/17/03    AJ Montclair                        
                                                            8             -20,000                  05/02/03   05/21/03    Bette & Cring                       
                                                            8               1,398                  09/04/03   09/16/03    Phase 4 Builders                    
                                                            9               2,402                  09/04/03   09/16/03    Phase 4 Builders                    
                                                            9              -6,369                  09/04/03   09/16/03    Bette & Cring                       
                                                            9               2,402                  01/13/04   02/18/04    Phase 4 Builders                    
 
99-1573   Reconstruction               0-001-007  06/08/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              -4,669                  06/27/02   10/21/02    Hyde Stone Mech.                    
                                                            1              -2,475                  09/09/02   10/21/02    Reindeer Environ.                   
                                                            1              15,500                  07/05/06   08/11/06    Reindeer Environmental              
                                                            1              -5,230                  07/05/06   08/11/06    Sand Brothers Roofing               
                                                            2              16,568                  07/05/06   08/11/06    Reindeer Environmental              
 
05-0341   Reconstruction               0-001-010  06/16/06  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0973   Reconstruction               0-001-011  06/26/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-03            4,516                  04/19/10   07/23/10    WATSON ELECTRIC INC                 
                                                            E-04            2,253                  04/19/10   07/23/10    WATSON ELECTRIC INC                 
                                                            E-05              865                  07/01/10   09/29/10    WATSON ELECTRIC INC                 
                                                            E-CCD002        3,958                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-CCD003        6,124                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-CCD008        3,397                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-CCD009        1,131                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-CCD012        1,219                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-CCD015        1,399                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            G-003          20,387                  01/06/10   04/02/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-001              0                  05/20/09   06/17/09    Con Tech Building Systems, Inc      
                                                            GC-001          3,399                  10/29/09   12/24/09    CON TECH BUILDING SYSTEMS INC       
                                                            GC-002         20,387                  02/05/10   04/21/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-04           4,880                  03/22/10   06/14/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-05           4,650                  03/22/10   06/14/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-06           2,200                  03/22/10   06/14/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-07           9,576                  04/08/10   06/16/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-08           2,295                  04/08/10   06/16/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-09          -2,019                  06/28/10   11/18/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-10          -4,114                  10/18/10   11/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD01          543                  05/18/10   07/28/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD08        6,629                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD11        5,530                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD14        2,902                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD16        3,788                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD17        7,531                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD32        4,399                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GCCCD07R        2,411                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            H-001          14,026                  12/07/09   01/22/10    NORTHERN MECHANICALS INC            
                                                            H-002          16,494                  12/28/09   02/09/10    NORTHERN MECHANICALS INC            
                                                            H-003          18,975                  12/28/09   02/09/10    NORTHERN MECHANICALS INC            
                                                            H-04            1,790                  04/19/10   07/23/10    NORTHERN MECHANICALS INC            
                                                            H-05           10,698                  04/19/10   07/23/10    NORTHERN MECHANICALS INC            
                                                            H-06           44,444                  04/19/10   07/23/10    NORTHERN MECHANICALS INC            
                                                            H-07           -8,193                  09/20/10     /  /      NORTHERN MECHANICALS                
                                                            H-CCD001        3,493                  07/23/10   08/23/10    NORTHERN MECHANICALS INC            
                                                            H-CCD005        2,591                  07/23/10   08/23/10    NORTHERN MECHANICALS INC            
                                                            H-CCD007        4,500                  09/20/10   11/19/10    NORTHERN MECHANICALS INC            
                                                            P-005             575                  05/18/10   07/27/10    NORWOOD PLUMBING INC                
                                                            P-06             -652                  06/14/10   11/18/10    NORWOOD PLUMBING INC                
                                                            P-CCD001          901                  02/16/10   07/29/10    NORWOOD PLUMBING INC                
                                                            P-CCD001        8,220                  04/28/10   07/21/10    NORWOOD PLUMBING INC                
                                                            P-CCD002        2,270                  02/16/10   04/15/10    NORWOOD PLUMBING INC                
                                                            P-CCD009        1,579                  07/01/10   09/29/10    NORWOOD PLUMBING INC                
 
13-0106   Reconstruction               0-001-012  08/21/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            P-01           -6,075                  02/18/14   03/04/14    Burns Brothers Contracting          
                                                            P-02           -1,912                  03/06/14   04/10/14    Burns Brothers Contracting          
                                                            P-03              624                  03/12/14   04/10/14    Burns Brothers Associates           
 
13-1621   Reconstruction               0-001-013  06/27/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            P-01                0                  03/16/15   03/25/15    Burns Brothers Contracting          
                                                            P-02                0                  03/16/15   03/26/15    Burns Brothers Contracting          
                                                            P-03           -2,118                  03/16/15   03/26/15    Burns Brothers Contracting          
                                                            P-04           -1,110                  12/26/14   01/13/15    Burns Brothers Contracting          
 
15-0006   Reconstruction               0-001-014  05/10/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01               0                  07/20/17   11/27/17    Watson Electric, Inc.               
                                                            EC-02          -2,584                  07/20/17   11/27/17    Watson Electric, Inc.               
                                                            EC-03               0                  07/20/17   11/27/17    Watson Electric, Inc.               
                                                            EC-05          -1,292                  02/20/18   04/18/18    Watson Electric, Inc.               
                                                            EC-06               0                  02/20/18   04/18/18    Watson Electric, Inc.               
                                                            EC-07               0                  02/20/18   04/18/18    Watson Electric, Inc.               
                                                            EC-09               0                  02/20/18   04/25/18    Watson Electric, Inc.               
                                                            EC-10               0                  02/20/18   04/25/18    Watson Electric, Inc.               
                                                            EC-11          23,421                  02/20/18   06/03/19    Watson Electric, Inc.               
                                                            EC-12             681                  02/20/18   04/25/18    Watson Electric, Inc.               
                                                            EC-13           2,268                  02/20/18   04/25/18    Watson Electric, Inc.               
                                                            EC-15           3,006                  05/10/18   06/04/18    Watson Electric, Inc.               
                                                            EC-17           1,946                  05/10/18   06/04/18    Watson Electric, Inc.               
                                                            EC-18          14,655                  05/10/18   06/04/18    Watson Electric, Inc.               
                                                            GC-01           1,927                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-02             734                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-03           6,607                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-04           6,607                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-05           6,607                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-06           1,600                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-07           7,136                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-08           2,398                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-09          -3,000                  02/20/18     /  /      Northern Tier Contracting, Inc.     
                                                            GC-10           3,186                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-12            -404                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-13           4,564                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-14           2,256                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-15           6,351                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-16             349                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-17           2,903                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-18             616                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-19          19,981                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-20           3,516                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-22          11,300                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-23           4,391                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-24           6,352                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            GC-25           1,453                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            HC-01               0                  06/20/17   10/30/17    Lawman Heating & Cooling, Inc.      
                                                            HC-02          -1,050                  06/20/17   10/30/17    Lawman Heating & Cooling, Inc.      
                                                            HC-03               0                  06/20/17   10/30/17    Lawman Heating & Cooling, Inc.      
                                                            HC-04               0                  04/16/18   06/01/18    Lawman Heating & Cooling, Inc.      
                                                            HC-05               0                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-06               0                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-07               0                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-08               0                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-09               0                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-10               0                  04/16/18   05/31/18    Lawman Heating & Coolong, Inc.      
                                                            HC-11          18,216                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-12          11,561                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-13          23,202                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-14           8,355                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-15          13,676                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-16           5,402                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            HC-18           1,840                  04/16/18   05/31/18    Lawman Heating & Cooling, Inc.      
                                                            P-02                0                  11/14/16   11/17/16    Bellucci Enterprises, Inc.          
                                                            P-03                0                  11/14/16   11/18/16    Bellucci Enterprises, Inc.          
                                                            P-07                0                  02/20/18   04/18/18    Bellucci Enterprises, Inc.          
                                                            P-08                0                  02/20/18   04/18/18    Bellucci Enterprises, Inc.          
                                                            PC-04               0                  06/20/17   10/30/17    Bellucci Enterprises, Inc.          
                                                            PC-05               0                  06/20/17   10/30/17    Bellucci Enterprises, Inc.          
                                                            PC-06               0                  06/20/17   10/30/17    Bellucci Enterprises, Inc.          
                                                            PC-09               0                  02/20/18   04/18/18    Bellucci Enterprises, Inc.          
                                                            PC-10          -2,360                  02/20/18   04/18/18    Bellucci Enterprises, Inc.          
                                                            PC-11          -1,845                  02/20/18   04/18/18    Bellucci Enterprises, Inc.          
                                                            SW-01           9,023                  05/21/18   06/01/18    ACTS II Construction                
                                                            SW-02               0                  06/20/17   07/05/17    ACTS II Construction                
                                                            SW-03           1,370                  05/21/18   06/01/18     CTS II Construction                
 
15-1361   Reconstruction               0-001-015  02/02/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01               0                  07/29/16   09/30/16    Northern Tier Contracting, Inc.     
                                                            EC-01               0                  03/21/18   03/27/18    Watson Electric, Inc.               
                                                            EC-02             789                  01/29/18   02/05/18    Watson Electric, Inc.               
                                                            EC-03          -4,739                  01/29/18   02/05/18    Watson Electric, Inc.               
                                                            GC-01           8,020                  07/29/16   09/30/16    Northern Tier Contracting, Inc.     
                                                            GC-02           4,050                  01/29/18   02/05/18    Northern Tier Contracting, Inc.     
                                                            GC-03            -930                  01/29/18   02/05/18    Northern Tier Contracting, Inc.     
                                                            P-01            1,062                  01/29/18   02/05/18    Burns Bros. Contractors, Inc.       
 
17-1094   Reconstruction               0-001-016  02/27/18  NO CHANGE ORDERS ON ELECTRONIC FILE
18-0860   Reconstruction               0-001-017  01/31/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  07/05/19   07/15/19    CONTINENTAL CONSTRUCTION, LLC       
                                                            GC-02               0                  07/05/19   07/15/19    CONTINENTAL CONSTRUCTION,LLC        
 
19-0268   Reconstruction               0-001-019  12/05/19  NO CHANGE ORDERS ON ELECTRONIC FILE
21-0904   Additions and Alterations    0-001-020  03/04/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -41,167                  08/25/22   09/07/23    Bette Cring LLC                     
                                                            1-02          -99,958                  08/25/22   09/07/23    Bette Cring LLC                     
                                                            1-03         -187,110                  09/16/22   11/13/23    Bette & Cring LLC                   
                                                            1-04          -32,889                  10/07/22   12/14/23    Bette&Cring LLC                     
                                                            1-05           -5,956                  10/07/22   12/14/23    Bette&Cring LLC                     
                                                            1-06          -29,139                  06/20/23   12/26/23    BETTE & CRING                       
                                                            1-07          -23,900                  10/20/22   12/19/23    Bette&Cring LLC                     
                                                            1-08           -3,469                  06/20/23   12/26/23    BETTE & CRING                       
                                                            1-09           33,150                  12/22/22   12/11/23    Bette&Cring LLC                     
                                                            1-10           38,325                  03/02/23   12/15/23    BETTE & CRING LLC                   
                                                            1-11           34,565                  06/20/23   12/22/23    BETTE & CRING                       
                                                            1-12           -2,065                  06/30/23     /  /      BETTE & CRING                       
                                                            1-13            5,250                  06/30/23     /  /      BETTE & CRING                       
                                                            2-01          -15,173                  10/07/22   07/13/23    Ontario HVAC Solutions Inc          
                                                            2-02           23,000                  11/10/22   07/27/23    ONTARIO HVA SOLUTIONS, INC.         
                                                            3-01           -5,672                  10/28/22   11/15/23    Ontario HVAC Solutions Inc          
                                                            4-01          -20,825                  08/15/22   03/23/23    watson Elec                         
                                                            4-02          -10,306                  11/02/22   11/16/23    Watson Elec                         
                                                            4-03             -926                  03/02/23   12/05/23    WATSON ELECTRIC                     
                                                            4-05            4,624                  06/20/23   12/27/23    WATSON ELECTRIC                     
                                                            5-01          -15,455                  09/27/22   12/11/23    PTL Contr Corp                      
                                                            5-02           10,900                  10/07/22   12/14/23    PTL Contr Corp                      
                                                            6-01           -4,000                  08/17/22   04/18/23    Assoc Fire Protect Corp             
 
21-0539   Reconstruction               0-001-021  01/10/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            4-04            5,744                  06/21/23   12/27/23    WATSON ELECTRIC                     
 
22-1049   Reconstruction               0-001-022  01/11/23  NO CHANGE ORDERS ON ELECTRONIC FILE
22-2208   Reconstruction               0-001-023  07/21/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage/Agriculture Clrm:
96-1756   Reconstruction               0-004-001  07/30/97  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            1              -7,190                  02/03/06   05/25/06    Diamond Roofing                     
                                                            1                 177                  02/10/06   05/25/06    DeClerck Flooring                   
                                                            1              15,034                  03/02/06   07/21/06    DeClark Flooring                    
 
05-0342   Reconstruction               0-004-002  06/16/06  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0974   Additions and Alterations    0-004-003  06/26/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-CCD001        2,137                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            GC-03          11,537                  10/29/09   12/24/09    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD04       13,009                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
 
15-0005   Reconstruction               0-004-004  05/10/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-08               0                  02/20/18   04/18/18    Watson Electric, Inc.               
                                                            EC-14           1,292                  02/20/18   04/25/18    Watson Electric, Inc.               
                                                            EC-16             313                  05/10/18   06/04/18    Watson Electric, Inc.               
                                                            GC-11           3,184                  02/20/18   02/28/18    Northern Tier Contracting, Inc.     
                                                            GC-21             835                  05/10/18   05/14/18    Northern Tier Contracting, Inc.     
                                                            HC-17           4,001                  04/16/18   06/01/18    Lawman Heating & Cooling, Inc.      
                                                            P-01                0                  11/14/16   11/17/16    Bellucci Enterprises, Inc.          
 
20-1133   Reconstruction               0-004-005  02/17/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -1,786                  10/19/21   12/06/22    Docteur Environmental, LLC          
                                                            1-02              810                  10/19/21   12/06/22    Docteur Environmental, LLC          
 

          Greenhouse:
07-0975   New Construction             0-005-001  06/26/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-01           13,200                  12/28/09   02/09/10    WATSON ELECTRIC INC                 
                                                            E-02           -3,213                  12/28/09   02/09/10    WATSON ELECTRIC INC                 
                                                            E-06            1,419                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-07            3,878                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            E-CCD010        5,635                  07/08/10   08/23/10    WATSON ELECTRIC INC                 
                                                            GC-CCD03       12,237                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            GC-CCD19        7,707                  07/23/10   08/23/10    CON TECH BUILDING SYSTEMS INC       
                                                            H-CCD004        4,088                  07/23/10   08/23/10    NORTHERN MECHANICALS INC            
                                                            P-04            2,068                  02/26/10   03/16/10    NORWOOD PLUMBING INC                
 
16-0312   Reconstruction               0-005-002  09/12/16  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage #2:
20-0134   New Construction             2-007-001  11/10/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  06/29/21   04/04/22    Northern Tier Contracting           
                                                            GC-02          -1,423                  06/29/21   04/04/22    Northern Tier Contracting           
 

INDIAN RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-03-01-06
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Antwerp Primary School:
92-0302   Reconstruction               0-001-005  10/20/92  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0225   Reconstruction               0-001-006  10/25/93  NO CHANGE ORDERS ON ELECTRONIC FILE
97-0939   Reconstruction               0-001-007  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0379   Reconstruction               0-001-008  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1194   Additions and Alterations    0-001-009  10/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001-BC21       38,000                  05/22/02   06/04/02    Purcell Const.                      
                                                            003-P21         5,187                  11/22/02   01/02/03    Brosh Mech.                         
                                                            003BC-21       39,700                  11/28/03   12/05/03    Purcell Const.                      
                                                            005-E21        10,052                  11/29/02   01/03/03    Ridley Elec.                        
                                                            F-4            -7,097                  02/27/03   07/01/03    Robert Office Interiors             
 
04-0804   Reconstruction               0-001-010  03/08/05  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2047   Reconstruction               0-001-011  11/13/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            02 006         -6,384                  09/03/09   10/13/09    M&N PLUMBING AND HEATING INC        
                                                            1              -1,000                  09/19/11   12/20/11    NEW YORK STATE FENCE INC            
 
13-1579   Reconstruction               0-001-012  03/25/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PH1-PC-1      -19,491                  10/24/16   11/02/16    DW & Crew Mechanical                
 
19-1324   Reconstruction               0-001-013  04/29/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E1 EC-04         -260                  05/18/22   04/04/23    Collins-Hammond Elec Contrs         
                                                            EC-10         -40,507                  12/16/22   12/18/23    Collins-Hammond Electrical Contracto
                                                            G1               -260                  05/18/22     /  /      Black Horse Const Group             
                                                            GC-09            -260                  05/18/22   05/15/23    Black Horse Const Group             
                                                            GC-11         -53,183                  12/16/22   12/06/23    Black Horse Const Group             
                                                            M1 MC-03       -1,835                  05/18/22   04/04/23    Lawman Heat&Cool Inc                
                                                            M2 MC-04         -260                  05/18/22   04/04/23    Lawman Heat&Cool Inc                
                                                            M3 MC-05      -98,092                  05/18/22   04/04/23    Lawman Heat&Cool Inc                
                                                            PC-03          -2,528                  12/16/22   11/27/23    JE Sheehan Contrg Corp              
 

          Evans Mills Primary School:
90-1715   Reconstruction               0-004-006  07/12/91  NO CHANGE ORDERS ON ELECTRONIC FILE
94-1136   Reconstruction               0-004-008  03/13/95  NO CHANGE ORDERS ON ELECTRONIC FILE
97-0943   Additions and Alterations    0-004-010  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0380   Reconstruction               0-004-011  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1196   Additions and Alterations    0-004-012  10/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            002-P21        23,960                  11/22/02   01/02/03    Brosh Mech.                         
                                                            003-E21        15,513                  11/29/02   01/03/03    Ridley Elec.                        
                                                            F-5             1,631                  02/27/03   07/01/03    Robert Office Interiors             
 
04-0805   Reconstruction               0-004-013  03/08/05  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2048   Reconstruction               0-004-014  11/13/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00 002         30,527                  02/05/10   03/19/10    BETTE & CRING LLC                   
                                                            01 001        -11,350                  02/05/10   03/18/10    PTL CONTRACTING CORPORATION         
                                                            01 006         30,189                  03/01/10   04/30/10    PTL CONTRACTING CORPORATION         
                                                            02 002         -5,130                  09/03/09   10/13/09    M&N PLUMBING AND HEATING INC        
                                                            02 007         24,413                  04/23/10   07/23/10    M&N PLUMBING AND HEATING INC        
                                                            1              -1,000                  10/11/11   12/20/11    AMERICAN ASPHALT                    
                                                            2              -1,000                  10/24/11   12/20/11    AMERICAN ASPHALT                    
 
14-0299   Additions and Alterations    0-004-015  06/29/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            PH2-1          19,000                  02/19/16   02/29/16    Barber Corporation                  
                                                            PH2-2          12,564                  02/19/16   02/29/16    Barber Corporation                  
                                                            PH2-EC-1      -27,814                  02/17/17   09/14/17    Collins-Hammond Electrical Contracto
                                                            PH2-PC-1      -20,845                  02/17/17   09/14/17    Hyde-Stone Mechanical Contractors   
                                                            PH2SITE5        9,989                  10/24/16   11/02/16    Barber Corporation                  
                                                            PH2SITE6        8,449                  12/07/16   12/09/16    Barber Corporation                  
                                                            PH2SITE7        3,223                  12/07/16   12/09/16    Barber Corporation                  
 
20-0812   Reconstruction               0-004-016  04/06/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E1            -20,401                  12/22/22   12/11/23    S&L Elec Inc                        
 

          Philadelphia Primary School:
97-0940   Additions and Alterations    0-005-006  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0381   Reconstruction               0-005-007  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1197   Additions and Alterations    0-005-008  10/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001-ACM2       13,840                  08/01/02   08/16/02    Balsam Lane Contractors             
                                                            001-E21        10,472                  02/19/03   02/20/03    Ridley Elec.                        
                                                            001-H21       -91,230                  12/23/02   01/08/03    Lawman Heating                      
                                                            001-P21        24,444                  08/01/02   08/16/02    Brosh Mech.                         
                                                            002-H21       -34,175                  04/01/03   04/03/03    Lawman Heating                      
                                                            003-H21         3,636                  06/03/03   06/09/03    Lawman Heating                      
                                                            005-P21        38,783                  12/23/02   01/08/03    Brosh Mech.                         
                                                            006-E21       -60,722                  04/01/03   04/03/03    Ridley Elec.                        
                                                            006-P21        -8,000                  03/03/03   03/11/03    Brosh Mech.                         
                                                            F-8            -2,454                  02/27/03   07/01/03    Robert Office Interiors             
 
00-0260   Reconstruction               0-005-009  11/13/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              -2,140                  01/07/02   02/14/02    Edward F. Galvin                    
 
04-0806   Reconstruction               0-005-010  03/08/05  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2049   Reconstruction               0-005-011  11/13/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00 001         26,245                  11/23/09   12/17/09    BETTE & CRING LLC                   
 
11-1374   Reconstruction               0-005-012  07/13/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            M1              2,300                  04/08/13   07/08/13    EMPIRE NORTHEAST INC                
 
13-1580   Reconstruction               0-005-013  03/25/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PH1-EC-1       -6,740                  10/24/16   11/02/16    S&L Electric                        
                                                            PH1-GC-3        5,842                  10/24/16   11/02/16    Bette & Cring                       
                                                            PH1-GC-4       -5,165                  02/03/17   03/02/17    Bette & Cring                       
                                                            PH1MC-1        -9,494                  10/24/16   11/02/16    Lawman Heating & Cooling            
 
19-1325   Reconstruction               0-005-014  04/29/20  NO CHANGE ORDERS ON ELECTRONIC FILE

          Indian River High School:
90-1716   Reconstruction               0-007-006  07/15/91  NO CHANGE ORDERS ON ELECTRONIC FILE
92-0303   Additions and Alterations    0-007-008  11/16/92  NO CHANGE ORDERS ON ELECTRONIC FILE
93-0053   Reconstruction               0-007-009  10/04/93  NO CHANGE ORDERS ON ELECTRONIC FILE
94-0847   Additions and Alterations    0-007-010  03/02/95  NO CHANGE ORDERS ON ELECTRONIC FILE
97-0945   Additions and Alterations    0-007-011  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0382   Reconstruction               0-007-012  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-0123   Additions and Alterations    0-007-013  12/15/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001-BC11       26,620                  08/01/02   08/16/02    Structural Assoc.                   
                                                            001-E11        19,000                  03/18/02   03/05/03    Collins-Hammond Elec.               
                                                            001-P11        12,259                  01/10/02   03/22/02    Brosh Mech.                         
                                                            001-S11        21,833                  05/22/02   05/29/02    Cory Wisinski Excavating            
                                                            001-S12        14,000                  01/10/02   03/22/02    John O'Rourke Water Developing      
                                                            001ACM11       16,922                  08/21/01   02/06/02    Balsam Lane Contractors             
                                                            002-BC11       17,336                  01/13/03   02/12/03    Structural Assoc.                   
                                                            002-E11         8,734                  07/26/02   08/16/02    Collins-Hammond Elec.               
                                                            002-P11        16,085                  01/10/02   03/22/02    Brosh Mech.                         
                                                            002-S11       107,203                  10/18/02   11/07/02    Cory Wisinski Excavating            
                                                            003-BC11       13,330                  02/21/03   03/04/03    Structural Assoc.                   
                                                            003-E11        41,824                  11/29/02   12/04/02    Collins-Hammond Elec.               
                                                            003-P11        18,000                  03/18/02   03/05/03    Brosh Mech.                         
                                                            003-S11        10,571                  12/23/02   01/10/03    Cory Wisinski Excavating            
                                                            004-E11         9,364                  08/01/02   08/16/02    Collins-Hammond Elec.               
                                                            005-E11        19,000                  08/01/02   03/05/03    Collins-Hammond Elec.               
                                                            006-E11        19,000                  11/05/02   03/05/03    Collins-Hammond Elec.               
                                                            F-1           -56,171                  02/27/03   07/02/03    Robert Office Interiors             
                                                            F-1           -56,171                  06/25/03     /  /      Robert Office Interiors             
 
04-0807   Reconstruction               0-007-014  03/08/05  NO CHANGE ORDERS ON ELECTRONIC FILE
08-0072   Additions and Alterations    0-007-015  02/27/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00 005         31,000                  04/23/10   08/05/10    BETTE & CRING LLC                   
                                                            00 007         24,318                  01/18/11   02/28/11    BETTE & CRING LLC                   
                                                            01 002        -15,742                  02/05/10   04/13/10    PTL CONTRACTING CORPORATION         
                                                            02 001        -12,426                  09/03/09   09/25/09    M&N PLUMBING AND HEATING INC        
                                                            02 008         -3,317                  12/23/10   01/20/11    M&N PLUMBING AND HEATING INC        
                                                            03 001        -52,250                  09/10/09   09/20/11    COLLINS-HAMMOND ELECTRICAL CONT. INC
                                                            03 005         -7,700                  10/13/09   11/30/09    COLLINS-HAMMOND ELECTRICAL CONT INC 
                                                            03 006        -41,160                  03/15/10   05/25/10    COLLINS - HAMMOND ELECTRICAL INC.   
                                                            04B 001        20,000                  09/17/10   09/30/10    BROSH MECHANICAL INCORPORATED       
                                                            04B 002           204                  12/29/10   02/07/11    BROSH MECHANICAL INCORPORATED       
                                                            06 001        -12,006                  01/03/11   01/28/11    JOSEPH FILHAN CO                    
                                                            1              -1,000                  09/06/11   10/03/11    CONTINENTAL CONSTRUCTION LLC        
                                                            1              -2,000                  11/09/11   01/27/12    PUTRELO BUILDING ENTERPRISES        
 
14-0547   Additions and Alterations    0-007-016  11/24/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1 (NEP)        -1,000                  05/03/18   05/10/18    N.E.P. Glass Co., Ltd.              
                                                            EC-3           11,208                  06/28/18   07/24/18    S&L ELECTRIC                        
                                                            GeoTher2       13,288                  06/16/17   10/30/17    American Auger & Ditching Co., Inc. 
                                                            PC-1          -17,670                  05/11/18   06/04/18    Hyde-Stone Mechanical Contractors   
                                                            PH3-GC-2       20,099                  05/25/18   06/11/18    BETTE & CRING                       
                                                            PH3-GeoT      217,500                  03/08/17   03/17/17    American Auger & Ditching Co., Inc. 
                                                            PH3-MC-1      -52,432                  05/09/18   06/04/18    Lawman Heating & Cooling            
                                                            Site-1         45,900                  08/31/17   10/13/17    Adhan Piping Co., Inc.              
                                                            Site-3        -64,344                  05/11/18   06/01/18    Adhan Piping Co., INc.              
 
18-1883   Additions and Alterations    0-007-017  06/28/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E1             -5,138                  12/09/20   02/23/21    PANKO ELECTRIC & MAINT., INC.       
                                                            G1              4,140                  12/09/20   03/10/21    BETTE & CRING                       
                                                            G2            -37,766                  12/09/20   02/23/21    BETTE & CRING                       
 
19-1326   Reconstruction               0-007-018  04/29/20  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1961FP Reconstruction               0-007-FP1  05/21/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Theresa Primary School:
90-1685   Reconstruction               0-008-004  07/16/91  NO CHANGE ORDERS ON ELECTRONIC FILE
97-0942   Additions and Alterations    0-008-006  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0383   Reconstruction               0-008-007  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1195   Additions and Alterations    0-008-008  10/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001-S22       -10,000                  01/07/03   01/14/03    John O'Rourke Water Development     
                                                            002-BC21     -120,185                  04/28/03   05/05/03    Purcell Const.                      
                                                            002-E21         8,180                  11/29/02   01/03/03    Ridley Elec.                        
                                                            004-P21        54,068                  08/14/03   08/20/03    Brosh Mech.                         
                                                            F-1          -261,619                  11/22/02     /  /      Roberts Office Interiors            
                                                            F-7           -13,443                  02/27/03   07/01/03    Roberts Office Interior             
 
04-0808   Reconstruction               0-008-009  03/08/05  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2050   Reconstruction               0-008-010  11/13/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00 006         28,387                  12/22/10   01/06/11    BETTE & CRING LLC                   
 
13-1581   Reconstruction               0-008-011  03/25/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            PH1-GC1        13,328                  03/21/16   05/09/16    Bette & Cring                       
 
19-1328   Reconstruction               0-008-012  04/29/20  NO CHANGE ORDERS ON ELECTRONIC FILE
22-0229FA Reconstruction               0-008-013  12/14/22  NO CHANGE ORDERS ON ELECTRONIC FILE

          Indian River Middle School:
92-0304   Additions and Alterations    0-010-004  12/02/92  NO CHANGE ORDERS ON ELECTRONIC FILE
94-0653   Additions and Alterations    0-010-005  02/22/95  NO CHANGE ORDERS ON ELECTRONIC FILE
97-0944   Additions and Alterations    0-010-006  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0384   Reconstruction               0-010-007  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1198   Reconstruction               0-010-008  10/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              -2,250                  03/19/04   04/28/04    Burns Brothers Contractors          
                                                            F-2          -186,882                  06/25/03   07/01/03    Robert Office Interiors             
                                                            F-3             3,133                  02/27/03   07/01/03    Robert Office Interiors             
 
07-2280   Reconstruction               0-010-010  12/16/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            01 003        -44,807                  02/05/10   03/25/10    PTL CONTRACTING CORPORATION         
                                                            02 005        -12,825                  09/03/09   09/25/09    M&N PLUMBING AND HEATING INC        
                                                            03 004         -8,230                  09/10/09   09/20/11    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            1              -2,000                  12/05/11   02/28/12    MURNANE BUILDING CONTRACTORS        
                                                            2              -1,000                  11/09/11   01/27/12    PUTRELO BUILDING ENTERPRISES        
 
11-1354   Reconstruction               0-010-011  06/01/12  NO CHANGE ORDERS ON ELECTRONIC FILE
14-0548   Additions and Alterations    0-010-012  11/24/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2 (NEP)        -1,000                  05/03/18   05/10/18    N.E.P. Glass Co., Ltd.              
                                                            EC-1            8,820                  05/25/18   06/18/18    S&L ELECTRIC                        
                                                            EC-2           15,189                  06/28/18   07/24/18    S&L ELECTRIC                        
                                                            GC-1           37,892                  05/25/18   06/11/18    BETTE & CRING                       
                                                            MC2           -34,894                  05/09/18   07/03/18    LAWMAN HEATING AND COOLING          
                                                            PC-2          -11,778                  05/11/18   06/04/18    Hyde-Stone Mechanical Contractors   
                                                            Site-2         89,100                  08/31/17   10/13/17    Adhan Piping Co., Inc.              
 
20-0813   Additions and Alterations    0-010-013  04/06/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            TC-03         -60,596                  08/29/22   04/20/23    American Auger& Ditch Co            
                                                            gc-09          34,068                  06/07/23     /  /      BLACK HORSE CONST.                  
 
02-1960FP Reconstruction               0-010-FP1  05/21/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Calcium Primary School:
97-0941   Additions and Alterations    0-027-003  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0385   Reconstruction               0-027-004  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1199   Reconstruction               0-027-005  10/12/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            004-E21         1,287                  11/29/02   01/03/03    Ridley Elec.                        
                                                            F-6              -336                  02/27/03   07/01/03    Robert Office Interiors             
 
07-2281   Additions and Alterations    0-027-008  12/16/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00 003        513,571                  02/05/10   03/25/10    BETTE & CRING LLC                   
                                                            00 004         23,161                  04/23/10   08/05/10    BETTE & CRING LLC                   
                                                            01 005        -18,161                  02/05/10   03/25/10    PTL CONTRACTING CORPORATION         
                                                            01 007        -22,950                  10/21/10   11/03/10    PTL CONTRACTING CORPORATION         
                                                            01 008         21,600                  10/21/10   11/03/10    PTL CONTRACTING CORPORATION         
                                                            01 009        -54,777                  01/03/11   01/28/11    PTL CONTRACTING CORPORATION         
                                                            02 003        -15,105                  09/03/09   09/25/09    M&N PLUMBING AND HEATING INC        
                                                            03 002        -18,290                  09/10/09   09/20/11    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            03 008        -40,984                  03/15/10   05/25/10    COLLINS - HAMMOND ELECTRICAL INC.   
                                                            03 009         -4,936                  05/13/10   07/20/10    COLLINS-HAMMOND ELECT. CONTRACTORS  
                                                            03 010          6,596                  01/10/11   02/11/11    COLLINS-HAMMOND ELECTRICAL CONT. INC
                                                            04A 001       -17,956                  12/29/10   02/07/11    TOWN MECHANICAL INC                 
                                                            3              -1,000                  11/09/11   01/27/12    PUTRELO BUILDING ENTERPRISES        
 
13-1582   Reconstruction               0-027-009  03/25/15  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0814   Reconstruction               0-027-010  04/06/21  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1959FP Reconstruction               0-027-FP1  05/21/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Indian River Intermediate School:
00-0124   New Construction             0-032-001  12/15/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001-H11       -10,680                  02/03/03   02/27/03    M&N Plumbing                        
                                                            001-R11        -2,544                  03/14/03   03/20/03    Sands Brothers Roofing              
                                                            001-W11       -10,500                  03/14/03   03/20/03    Northern Glass Company              
                                                            002-H11        -6,114                  04/28/03   05/05/03    M&N Plumbing                        
                                                            004-P11         5,544                  12/23/02   01/10/03    Brosh Mech.                         
                                                            007-E11         8,632                  11/29/02   12/04/02    Collins-Hammond Elec.               
                                                            008-E11       114,256                  11/29/02   12/04/02    Collins-Hammond Elec.               
                                                            009-E11        -7,358                  04/01/03   04/21/03    Collins-Hammond Elec.               
                                                            010-E11        -6,089                  04/01/03   04/21/03    Collins Hammond Elec.               
                                                            F-2          -186,882                  02/27/03   09/05/03    Robert Office Interiors             
 
07-2103   Additions and Alterations    0-032-002  01/16/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            01 004         -4,540                  02/05/10   03/25/10    PTL CONTRACTING CORPORATION         
                                                            02 004         -5,130                  09/03/09   09/25/09    M&N PLUMBING AND HEATING INC        
                                                            03 003         -8,230                  09/10/09     /  /      COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            03 007        -34,836                  03/15/10   05/25/10    COLLINS - HAMMOND ELECTRICAL INC.   
                                                            05 001        -17,754                  10/20/10   10/29/10    LOOPMASTER INTERNATIONAL INC        
 
14-0300   Additions and Alterations    0-032-003  06/29/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PH2-Ge-1      -80,142                  11/21/16   11/28/16    Purcell Construction                
                                                            PH2-MC-1      -68,172                  02/17/17   09/14/17    Lawman Heating & Cooling            
                                                            PH2-PV-1       21,542                  03/14/16   03/17/16    S&L Electric                        
                                                            PH2-PV-2        2,553                  05/08/17   06/06/17    S&L Electric                        
                                                            PH2SITE3        9,242                  10/24/16   11/02/16    Barber Corporation                  
                                                            PH2SITE4        9,009                  10/24/16   11/02/16    Barber Corporation                  
 
19-1329   Reconstruction               0-032-004  04/29/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-24               0                  03/03/22   02/22/23    PAC ASSOCIATES OF OSWEGO            
 
02-1958FP Reconstruction               0-032-FP1  05/21/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXTemporary Greenhouse Removed2006-7:
00-1774   New Construction             0-038-001  06/27/01  NO CHANGE ORDERS ON ELECTRONIC FILE

          HS Support Bldg - Toilet/StorageBldg:
14-0549   New Construction             2-044-001  11/24/15  NO CHANGE ORDERS ON ELECTRONIC FILE

          New Storage Building:
18-1884   New Construction             2-046-001  06/28/19  NO CHANGE ORDERS ON ELECTRONIC FILE

          Maintenance Center (fmly 5-002):
18-1885   Additions and Alterations    3-002-001  06/28/19  NO CHANGE ORDERS ON ELECTRONIC FILE
19-1327   Reconstruction               3-002-002  04/29/20  NO CHANGE ORDERS ON ELECTRONIC FILE

          Calcium Storage (frmrly Bus Garage):
94-0719   Reconstruction               4-009-003  02/27/95  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0386   Reconstruction               4-009-004  01/28/99  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2282   Reconstruction               4-009-005  12/16/08  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0815   Reconstruction               4-009-006  04/06/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXMaintenance Center (see 3-002):
92-1205   Reconstruction               5-002-002  05/04/93  NO CHANGE ORDERS ON ELECTRONIC FILE
97-0938   Reconstruction               5-002-003  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2051   Additions and Alterations    5-002-005  11/13/08  NO CHANGE ORDERS ON ELECTRONIC FILE
13-1583   Reconstruction               5-002-006  03/25/15  NO CHANGE ORDERS ON ELECTRONIC FILE

          Transportation Facility:
97-0946   New Construction             5-031-001  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2104   Reconstruction               5-031-002  01/16/09  NO CHANGE ORDERS ON ELECTRONIC FILE
07-1899   Reconstruction               5-031-003  04/03/08  NO CHANGE ORDERS ON ELECTRONIC FILE
11-1375   Reconstruction               5-031-004  07/13/12  NO CHANGE ORDERS ON ELECTRONIC FILE
13-1584   Reconstruction               5-031-005  03/25/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PH1-GC2        12,777                  03/21/16   05/09/16    Bette & Cring                       
 
19-1330   Reconstruction               5-031-006  04/29/20  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXPress Box @ HS (demo 2015):
93-1391   New Construction             7-030-001  06/21/94  NO CHANGE ORDERS ON ELECTRONIC FILE

          Athletic Field Hse-Concession/StgToi:
97-0947   New Construction             7-033-001  04/24/98  NO CHANGE ORDERS ON ELECTRONIC FILE

          Press Box @ Field #8:
01-0157   Reconstruction               7-037-001  06/17/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Press Box @ HS:
15-0744   New Construction             7-045-001  11/24/15  NO CHANGE ORDERS ON ELECTRONIC FILE

          Fitness Pavillion @HS:
22-2228FC New Construction             7-047-001  08/22/23  NO CHANGE ORDERS ON ELECTRONIC FILE

GENERAL BROWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-04-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Brownville-Glen Park Elementary:
99-1123   Reconstruction               0-001-002  06/06/00  NO CHANGE ORDERS ON ELECTRONIC FILE
08-0772   Reconstruction               0-001-003  04/22/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2-01           -2,562                  01/13/12   05/03/12    LAWMAN HEATING & COOLING            
                                                            5-01          -37,000                  05/27/10   08/05/10    GOUVERNEUR ROOFING                  
                                                            5-02          -66,500                  05/27/10   08/05/10    GOUVERNEUR ROOFING                  
 
08-1595   Reconstruction               0-001-004  08/20/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01R          22,605                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-02            2,360                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-03           -2,043                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-03             -270                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-04            6,357                  10/29/10   12/01/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-04           -3,408                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-05             -594                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-06           -6,687                  12/16/11     /  /      CONTINENTAL CONSTRUCTION            
                                                            1-07            5,624                  10/29/10   12/01/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-08            3,281                  12/03/10   12/28/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-09           -8,364                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-10           -1,834                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-11           -2,193                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-12           -1,899                  12/16/11     /  /      CONTINENTAL CONSTRUCTION            
                                                            1-14              333                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-19             -390                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-20             -551                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            2-03           -1,518                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-04            7,796                  09/29/10   10/12/10    LAWMAN HEATING & COOLING            
                                                            2-05             -939                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-06            1,163                  02/03/11   03/03/11    LAWMAN HEATING & COOLING            
                                                            2-08           -1,065                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-13           -5,593                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-14           -3,499                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-16           -4,448                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            3-01           -1,468                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-03            3,453                  04/13/11   06/16/11    BILLITIER ELECTRIC INC              
                                                            3-06           -1,577                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-09           -1,040                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-17           -5,054                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-18           -2,698                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            4-02             -403                  01/13/12   05/23/12    SANDS BROTHERS ROOFING              
                                                            AA 1-01        15,000                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
 
10-0858   Reconstruction               0-001-005  06/07/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            4 - 04            184                  10/16/12   07/17/13    S & L Electric, Inc                 
 
14-1447   Reconstruction               0-001-006  06/30/16  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0330   Reconstruction               0-001-007  12/13/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-004             578                  11/19/18   01/28/19    CONTINENTAL CONSTRUCTION, LLC.      
                                                            1-101               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-102               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-103               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-105               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-106               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-110               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            2-101               0                  02/19/19   06/11/20    PTL CONTRACTING CORP                
                                                            3-001             909                  10/10/18     /  /      HYDE STONE MECHANICAL CONTRACTORS IN
                                                            4-001         -29,883                  02/26/19   03/08/19    BARRETT PAVING MATERIALS, INC.      
                                                            4-106               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
                                                            4-109               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
 
18-1879   Reconstruction               0-001-008  07/18/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            5-01           37,029                  12/03/20   05/10/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-04            2,421                  12/03/20   05/10/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-08           -3,129                  02/18/21   04/15/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            501-01              0                  04/21/21   05/18/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            6-02           18,865                  12/03/20   02/03/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-06           13,830                  02/18/21   04/09/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-08            1,914                  02/18/21   04/09/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            601-01              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            601-02              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            7-01            4,122                  03/18/20   07/06/20    J.E.SHEEHAN CONTRACTING CORP.       
                                                            7-02           -2,500                  02/18/21   04/09/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            8-01            8,600                  12/03/20   02/03/21    WATSON ELECTRIC, INC.               
                                                            8-03              746                  02/18/21   04/09/21    WATSON ELECTRIC, INC.               
 
21-0125FC Reconstruction               0-001-009  11/10/21  NO CHANGE ORDERS ON ELECTRONIC FILE
22-2276FA Reconstruction               0-001-010  07/19/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1481FP Reconstruction               0-001-FP1  05/27/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Dexter Elementary:
99-1122   Reconstruction               0-002-002  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2              11,494                  06/28/01   02/06/02    E.D. Young                          
 
08-0773   Reconstruction               0-002-003  04/22/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -33,600                  10/28/09   12/21/09    34 & COMPANY                        
                                                            1-02          -46,147                  10/28/09   12/21/09    34 & COMPANY                        
                                                            1-03          -62,789                  10/28/09   12/21/09    34 & COMPANY                        
                                                            1-04         -119,099                  10/28/09   12/21/09    34 & COMPANY                        
                                                            1-05           16,994                  02/02/10   04/16/10    34 & COMPANY                        
                                                            1-06           17,260                  09/29/10   10/29/10    34 & COMPANY                        
                                                            1-07            4,500                  11/22/11   03/30/12    34 & COMPANY                        
                                                            1-08            1,574                  11/22/11   03/30/12    34 & COMPANY                        
                                                            1-09            4,570                  11/22/11   03/30/12    34 & COMPANY                        
                                                            2-01           -1,215                  03/31/10   05/14/10    HOOVER HEATING & COOLING            
                                                            3-01           -5,575                  03/31/10   05/14/10    HOOVER HEATING & COOLING            
                                                            3-02              843                  09/03/10   09/24/10    HOOVER HEATING & COOLING            
                                                            4-01           34,800                  05/19/10   07/21/10    34 & COMPANY                        
                                                            4-02            4,740                  01/20/12   04/06/12    34 & COMPANY                        
                                                            4-03            4,567                  01/20/12   04/06/12    34 & COMPANY                        
                                                            FO 1-01             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            FO 1-02             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            FO 1-03             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            FO 1-04             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            FO 1-05             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            FO 1-06             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            FO 1-07             0                  11/22/11   03/30/12    34 & COMPANY                        
                                                            S1-01               0                  11/22/11   03/30/12    34 & COMPANY                        
 
10-0859   Reconstruction               0-002-004  06/07/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            4-01           -4,376                  02/03/12   05/15/12    S&L ELECTRIC INC                    
                                                            4-07            3,022                  12/07/12   08/16/13    S&L ELECTRIC INC                    
 
14-1448   Reconstruction               0-002-005  06/30/16  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0331   Reconstruction               0-002-006  12/13/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001             500                  08/03/18   08/17/18    CONTINENTAL CONSTRUCTION LLC        
                                                            1-003           2,894                  11/19/18   01/28/19    CONTINENTAL CONSTRUCTION, LLC.      
                                                            1-107               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-108               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            1-109               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            3-101               0                  02/19/19   07/15/19    HYDE-STONE MECHANICAL CONTRACTORS IN
                                                            4-107               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
 
18-1880   Reconstruction               0-002-007  07/18/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            5-06            8,130                  12/03/20   05/10/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-09           -7,396                  02/18/21   04/15/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            502-01              0                  04/21/21   05/18/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            502-02              0                  04/21/21   05/18/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            6-01           27,433                  12/03/20   02/03/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-09           -2,679                  02/18/21   04/09/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-10            1,449                  03/05/21   04/29/21    BLACK RIVER PLUMBING,HEATING & AC   
                                                            602-01              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            602-02              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            602-03              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            602-04              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            7-03           -4,249                  02/18/21   04/09/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            7-05            7,643                  04/02/21   05/05/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            702-01              0                  05/18/21   08/16/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            702-02              0                  04/22/21   06/30/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            8-04           -2,339                  02/18/21   04/09/21    WATSON ELECTRIC, INC.               
                                                            802-01              0                  04/22/21   06/30/21    WATSON ELECTRIC, INC.               
                                                            802-02              0                  04/22/21   06/30/21    WATSON ELECTRIC, INC.               
                                                            802-03              0                  04/22/21   06/30/21    WATSON ELECTRIC, INC.               
 
21-0126FC Reconstruction               0-002-008  11/10/21  NO CHANGE ORDERS ON ELECTRONIC FILE
22-2277FA Reconstruction               0-002-009  07/19/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          High School:
94-0873   Additions and Alterations    0-003-001  03/14/95  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1121   Additions and Alterations    0-003-002  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1               2,405                  08/02/01   01/30/02    Gaffney & Singer Ent.               
                                                            1                -620                  06/28/01   02/06/02    E.D.Young                           
                                                            1              12,246                  01/17/02   03/25/02    Empire Northeast                    
                                                            1A             15,625                  06/28/01   02/06/02    Jareco Assoc.                       
                                                            2                 506                  07/16/01   01/30/02    Northern Mech.                      
                                                            2              -1,713                  04/09/02   05/10/02    Empire Northeast                    
                                                            2               4,301                  04/09/02   05/10/02    Gaffney & Singer Ent.               
                                                            2A             14,755                  06/28/01   02/06/02    Jareo Assoc.                        
                                                            3               4,413                  07/16/01   01/30/02    Northern Mech.                      
                                                            31              3,943                  01/17/02   03/25/02    Northland Assoc.                    
                                                            32             -4,850                  04/09/02   05/10/02    Northland Assoc.                    
                                                            4               3,105                  04/09/02   05/10/02    Northern Mech.                      
                                                            4               1,597                  04/09/02   05/10/02    E.D.Young                           
                                                            4A                465                  05/09/02   06/04/02    Jareco Assoc.                       
                                                            4B             -7,577                  05/09/02   06/04/02    Jareco Assoc.                       
                                                            5               4,090                  04/09/02   05/10/02    E.D. Young                          
                                                            5A            -38,005                  05/09/02   06/04/02    Jareco Assoc.                       
                                                            6              22,196                  02/22/02   04/01/02    Northern Mech.                      
                                                            7              -1,413                  02/22/02   04/01/02    Northern Mech.                      
                                                            9              -3,807                  01/17/02   03/25/02    E.D. Young                          
 
08-1596   Reconstruction               0-003-003  10/21/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           15,580                  08/18/10   09/27/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-01             -259                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-02           -5,546                  10/22/10   11/23/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-02             -675                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-03           30,336                  10/29/10   12/01/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-05            9,233                  10/29/10   12/01/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-06           95,472                  10/29/10   12/01/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-07           -4,170                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-08             -506                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-09            1,683                  12/03/10   12/28/10    CONTINENTAL CONSTRUCTION LLC        
                                                            1-10          -21,473                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION LLC        
                                                            1-13           -4,985                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-15           -6,961                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-16             -825                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-17           -3,153                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-18           -2,151                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            1-21             -445                  12/16/11   03/16/12    CONTINENTAL CONSTRUCTION            
                                                            2-01           -2,225                  11/12/10   12/01/10    LAWMAN HEATING & COOLING            
                                                            2-01           -2,562                  01/13/12     /  /      LAWMAN HEATING & COOLING            
                                                            2-02            6,083                  09/17/10   09/28/10    LAWMAN HEATING & COOLING            
                                                            2-02           -1,624                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-03           10,593                  09/29/10   10/12/10    LAWMAN HEATING & COOLING            
                                                            2-04             -315                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-05           -1,737                  10/29/10   12/02/10    LAWMAN HEATING & COOLING            
                                                            2-06           -6,214                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-07          -14,727                  04/13/11   06/20/11    LAWMAN HEATING & COOLING            
                                                            2-07          -12,307                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-08          -19,554                  08/18/11   09/30/11    LAWMAN HEATING & COOLING            
                                                            2-09          -18,178                  01/31/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-09           -3,032                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-10              259                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-11           -6,700                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-12           -2,194                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-15           -1,416                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            2-17           -3,648                  01/13/12   05/11/12    LAWMAN HEATING & COOLING            
                                                            3-01          -23,866                  11/12/10   12/01/10    BILLITIER ELECTRIC INC              
                                                            3-02            4,860                  04/13/11   06/16/11    BILLITIER ELECTRIC INC              
                                                            3-02             -688                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-03              -95                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-04            1,704                  05/24/11   07/15/11    BILLITIER ELECTRIC INC              
                                                            3-04           -9,288                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-05            3,714                  05/24/11   07/15/11    BILLITIER ELECTRIC INC              
                                                            3-05            2,436                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-06            3,196                  01/24/12   04/16/12    BILLITIER ELECTRIC INC              
                                                            3-07            4,190                  01/24/12   04/16/12    BILLITIER ELECTRIC INC              
                                                            3-07           -2,986                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-08            1,885                  01/27/12   05/11/12    BILLITIER ELECTRIC INC              
                                                            3-08           -2,119                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-09 R3       -20,000                  04/24/13   10/11/13    BILLITIER ELECTRIC INC              
                                                            3-10           -4,284                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-10             -747                  04/24/13   10/11/13    BILLITIER ELECTRIC INC              
                                                            3-11           -4,300                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-12           -2,953                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-13           -4,257                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-14           -1,496                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-15           -1,604                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-16             -656                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            3-19             -160                  01/13/12   05/11/12    BILLITIER ELECTRIC                  
                                                            4-01          -19,058                  01/04/11   01/28/11    SANDS BROTHERS ROOFING              
                                                            4-01             -538                  01/13/12   05/23/12    SANDS BROTHERS ROOFING              
                                                            4-02              763                  03/28/11   04/22/11    SANDS BROTHERS ROOFING              
                                                            5-01           35,350                  10/29/10   12/01/10    LANDMARK ENTERPRISES                
                                                            5-01           49,233                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
                                                            5-02           27,120                  10/29/10   12/01/10    LANDMARK ENTERPRISES                
                                                            5-02           -7,923                  11/23/11   02/27/12    LANDMARK ENTEPRRISES                
                                                            5-03            3,491                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
                                                            5-03           -2,824                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
                                                            5-04            3,951                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
                                                            5-05            4,645                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
                                                            5-06            2,625                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
                                                            5-07           -8,699                  02/28/12   07/23/12    LANDMARK ENTERPRISES                
                                                            R5-01         -10,000                  11/23/11   02/27/12    LANDMARK ENTERPRISES                
 
10-0860   Reconstruction               0-003-004  06/07/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1 - 04          2,840                  10/16/12   02/15/13    Continetal Construction, LLC        
                                                            1-01           40,425                  03/23/12   08/30/12    CONTINENTAL CONSTRUCTION            
                                                            1-02           12,532                  03/23/12   08/30/12    CONTINENTAL CONSTRUCTION            
                                                            1-03           28,876                  08/31/12   12/20/12    CONTINENTAL CONSTRUCTION            
                                                            2-01                0                  01/07/13   07/17/13    BURNS BROTHERS                      
                                                            2-02           -7,405                  01/07/13   07/17/13    BURNS BROTHERS                      
                                                            4-02            2,450                  02/28/12   09/07/12    S&L ELECTRIC INC                    
                                                            4-03            2,338                  03/27/12   08/22/12    S&L ELECTRIC INC                    
                                                            4-05           -4,951                  11/30/12   04/05/13    S & L Electric, Inc.                
                                                            4-06              588                  12/07/12   07/17/13    S&L ELECTRIC INC                    
                                                            5-01           -1,148                  07/23/12   02/19/13    BARRETT PAVING MATERIALS INC        
                                                            5-02           -5,357                  09/07/12   12/20/12    BARRETT PAVING MATERIALS INC        
 
14-1449   Reconstruction               0-003-005  06/30/16  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0332   Reconstruction               0-003-006  12/19/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2-001         -50,295                  01/18/19   02/11/19    PTL CONTRACTING CORP.               
                                                            4-101               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
                                                            4-104               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
                                                            4-108               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
 
18-1881   Reconstruction               0-003-007  07/18/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            5-02           14,065                  12/03/20   02/19/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-03           36,380                  08/11/20   10/02/20    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-05           15,432                  12/03/20   02/19/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-07           24,333                  12/03/20   02/18/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-10           35,876                  02/18/21   04/15/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-11           22,718                  02/18/21   04/15/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-12           29,777                  02/18/21   04/15/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            5-13            1,337                  02/18/21   04/15/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            503-01              0                  04/21/21   05/18/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            503-02              0                  04/21/21   05/18/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            6-03           25,855                  12/03/20   02/03/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-04           27,659                  02/18/21   04/09/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-05           14,612                  02/18/21   04/09/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            6-07           13,822                  02/18/21   04/09/21    BLACK RIVER PLUMBING, HEATING & AC  
                                                            603-01              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            603-02              0                  04/22/21   06/30/21    BLACK RIVER PLUMBING, HEATING & AIR 
                                                            7-04           -2,500                  02/18/21   04/09/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            8-02           13,361                  12/03/20   02/03/21    WATSON ELECTRIC, INC.               
                                                            8-05            1,776                  02/18/21   04/09/21    WATSON ELECTRIC, INC.               
                                                            803-01              0                  04/22/21   06/30/21    WARSON ELECTRIC, INC.               
                                                            803-02              0                  04/22/21   06/30/21    WATSON ELECTRIC, INC.               
 
19-1423   Additions and Alterations    0-003-008  04/06/20  NO CHANGE ORDERS ON ELECTRONIC FILE
21-0127FC Reconstruction               0-003-009  11/10/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01              713                  09/29/22   12/06/23    Trane US Inc                        
 

          Elementary School:
96-0305   Reconstruction               0-010-002  10/25/96  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage:
94-0872   Additions and Alterations    5-004-001  03/14/95  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1124   Additions and Alterations    5-004-002  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            20              4,377                  04/09/02   05/10/02    Northland Assoc.                    
                                                            3A              2,999                  04/09/02   05/10/02    Jareco Assoc.                       
                                                            3B             11,735                  04/09/02   05/10/02    Jareco Assoc.                       
 
09-1209   Reconstruction               5-004-004  01/18/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -9,236                  11/18/11   03/16/12    BLACK HORSE GROUP LLC               
                                                            100-01              0                  02/10/12   05/17/12    BLACK HORSE GROUP LLC               
                                                            2-01           -4,662                  11/10/11   01/18/12    NORWOOD PLUMBING                    
                                                            3-01           -5,745                  12/15/11   03/16/12    SC SPENCER ELECTRIC                 
                                                            300-01              0                  02/10/12   05/15/12    S.C. SPENCER ELECTRIC INC           
                                                            4-01          -13,035                  11/23/11   03/19/12    LAVALLEY BROTHERS CONSTRUCTION      
                                                            400-01              0                  02/10/12   05/17/12    LAVALLEY BROTHERS CONSTRUCTION      
                                                            400-02              0                  02/10/12   05/17/12    LAVALLEY BROTHERS CONSTRUCTION      
 
14-1450   Reconstruction               5-004-005  06/30/16  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0333   Reconstruction               5-004-006  12/13/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-002         -13,600                  11/19/18   01/28/19    CONTINENTAL CONSTRUCTION, LLC.      
                                                            1-002         -13,600                  02/15/19   03/08/19    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-005            -341                  02/15/19   03/08/19    CONTINENTAL CONSTRUCTION,LLC        
                                                            1-104               0                  02/19/19   07/15/19    CONTINENTAL CONSTRUCTION LLC        
                                                            4-102               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
                                                            4-103               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
                                                            4-105               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
                                                            4-110               0                  02/19/19   07/15/19    BARRETT PAVING MATERIALS INC        
 
23-0512   Reconstruction               5-004-008  10/25/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Press Box:
08-1597   New Construction             7-014-001  08/20/09  NO CHANGE ORDERS ON ELECTRONIC FILE

          District-Wide:
16-0909   Reconstruction               7-999-001  05/04/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01             -836                  05/08/18   05/17/18    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            1-101               0                  08/15/19   08/20/19    COLLINS-HAMMOND ELECTRICAL          
                                                            1-102               0                  08/15/19   08/20/19    COLLINS-HAMMOND ELECTRICAL          
                                                            REV-1         -17,423                  02/22/19   03/07/19    COLLINS-HAMMOND ELECTRICAL CONTRACTO
 

THOUSAND ISLANDS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-07-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Guardino Elem. (fmly Clayton):
97-1406   Additions and Alterations    0-003-001  05/20/98  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            0001             -828                  06/19/02   06/19/02    PTL Contracting                     
                                                            0001              828                  06/19/02   06/19/02    S&S Environ. USA                    
                                                            0001           22,695                  06/19/02   06/19/02    Ajay Glass & Mirror                 
                                                            0004R           3,238                  07/18/02   07/19/02    Ajay Glass & Mirror                 
                                                            0005            3,625                  07/18/02   07/19/02    Ajay Glass & Mirror                 
 
07-0108   Reconstruction               0-003-002  11/21/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001             4,439                  02/02/09   03/04/09    CORY WISINSKI EXCAVATING            
                                                            002                 0                  02/02/09   04/10/09    M&N PLUMBING & HEATING, INC.        
                                                            002            -7,000                  09/27/10     /  /      CORY WISINSKI EXCAVATING            
                                                            007          -115,722                  03/09/09   06/17/09    CORY WISINSKI EXCAVATING            
 
07-0044   Reconstruction               0-003-003  04/09/08  NO CHANGE ORDERS ON ELECTRONIC FILE
11-1026   Reconstruction               0-003-004  10/09/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-001            -246                  12/10/13   01/27/14    Jordstat Construction               
                                                            P-002               0                  02/21/14   03/21/14    Skelly Contractors Inc.             
 
11-1338   Reconstruction               0-003-005  05/29/12  NO CHANGE ORDERS ON ELECTRONIC FILE
14-0002   Reconstruction               0-003-006  12/03/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001                 0                  01/15/16   03/18/16    Hyde-Stone                          
                                                            003            -4,156                  03/15/16   03/18/16    Hyde-Stone                          
                                                            007            10,040                  09/27/16   10/18/16    S & L Electric                      
                                                            008            14,510                  09/27/16   10/18/16    S & L Electric                      
                                                            EC-002              0                  07/15/16   10/06/16    S&L ELECTRIC                        
                                                            GC-001              0                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
 
13-1312   Reconstruction               0-003-007  08/20/14  NO CHANGE ORDERS ON ELECTRONIC FILE
15-0822   Reconstruction               0-003-008  12/15/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001            140                  04/21/16   05/04/16    Northern Tier Contracting, Inc.     
 
16-2149   Reconstruction               0-003-009  03/29/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0719   Reconstruction               0-003-010  08/10/17  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0801   Reconstruction               0-003-011  02/06/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001         -8,088                  04/20/18   04/25/18    New Century Electric, Inc.          
                                                            EC002          -5,000                  06/26/18   07/24/18    NEW CENTURY ELECTRIC INC            
 
18-0624   Reconstruction               0-003-012  12/17/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001         -5,000                  09/25/19   10/01/19    S&L ELECTRIC, INC.                  
 
18-1806   Reconstruction               0-003-013  05/06/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001             2,085                  12/09/19   12/19/19    ELEVATTITT, INC.                    
                                                            002            -5,000                  06/28/21   11/16/21    Elevattitt Inc                      
 

          Bashaw Elementary School:
97-1407   Additions and Alterations    0-005-001  05/20/98  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            0001            3,499                  06/19/02     /  /      Lawman Heating                      
                                                            0001           -2,428                  06/19/02   06/19/02    Point to Point Network              
 
07-0109   Reconstruction               0-005-002  11/21/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001            20,568                  11/02/09   03/19/10    RUSTON PAVING CO., INC.             
                                                            002            61,915                  11/02/09   12/04/09    RUSTON PAVING CO., INC.             
                                                            003                 0                  02/02/09   03/04/09    CORY WISINISKI EXCAVATING           
                                                            006          -136,805                  03/09/09   06/17/09    CORY WISINSKI EXCAVATING            
 
07-0045   Reconstruction               0-005-003  04/09/08  NO CHANGE ORDERS ON ELECTRONIC FILE
11-1027   Reconstruction               0-005-004  10/09/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-002               0                  12/10/13     /  /      Jordstat Construction               
                                                            GC-001              0                  06/12/14   09/02/14    Contech Building Systems            
 
11-1339   Reconstruction               0-005-005  05/29/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001           -10,140                  06/12/13   07/26/13    PTL CONTRACTING CORP                
 
14-0003   Reconstruction               0-005-006  12/03/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            002                 0                  03/15/16   03/18/16    Hyde-Stone                          
                                                            005            13,572                  09/27/16   10/18/16    S&L Electric                        
                                                            006             3,546                  09/27/16   10/18/16    S&L Electric                        
                                                            009            20,685          11,207  09/27/16   10/24/16    S&L Electric                        
                                                            GC-004          6,874                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
 
13-1313   Reconstruction               0-005-007  08/20/14  NO CHANGE ORDERS ON ELECTRONIC FILE
16-2150   Reconstruction               0-005-008  03/29/18  NO CHANGE ORDERS ON ELECTRONIC FILE
23-1037FA Reconstruction               0-005-012  12/22/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Cape Vincent Annex:
11-1028   Reconstruction               0-008-001  10/09/12  NO CHANGE ORDERS ON ELECTRONIC FILE

          Middle School/High School:
95-1587   Reconstruction               0-011-003  06/21/96  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            P 001               0                  12/14/09     /  /      LAFRANCE PLUMBING & HEATING INC     
 
97-1408   Additions and Alterations    0-011-004  05/20/98  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            0002           -3,000                  07/18/02   07/19/02    PTL Contracting                     
                                                            0011            1,923                  06/19/02     /  /      Lawman Heating                      
                                                            0020            3,300                  06/19/02   06/19/02    Barry, Bette and LeDuke             
 
03-1647   Reconstruction               0-011-005  07/06/04  NO CHANGE ORDERS ON ELECTRONIC FILE
04-1378   Reconstruction               0-011-006  07/27/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              -9,365                  11/28/05   05/25/06    S and l Electric                    
 
07-0110   Additions and Alterations    0-011-007  11/21/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001                 0                  11/16/09     /  /      S&L ELECTRIC                        
                                                            002                 0                  11/16/09   02/09/10    S&L ELECTRIC                        
                                                            003             3,117                  11/16/09   02/08/10    S&L ELECTRIC                        
                                                            004               995                  10/13/09   11/17/09    BETTE & CRING                       
                                                            005          -139,625                  03/09/09   06/17/09    CORY WISINSKI EXCAVATING            
                                                            GC 005          1,668                  07/27/09   08/06/09    BETTE & CRING                       
                                                            H 004          -3,049                  07/27/09   08/06/09    M&N PLUMBING & HEATING              
                                                            P 004               0                  07/27/09   08/06/09    LAFRANCE PLUMBING & HEATING INC     
                                                            P-003           3,255                  11/02/09   12/04/09    LAFRANCE PLUMBING & HEATING, INC.   
                                                            R-1 001         1,566                  07/27/09   08/10/09    GOUVERNEUR ROOFING SIDING SHEETMETAL
 
06-0799   Reconstruction               0-011-008  02/01/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            R-001          -9,000                  01/24/08   04/07/08    PTL CONTRACTING CORP.               
 
07-0046   Reconstruction               0-011-009  04/09/08  NO CHANGE ORDERS ON ELECTRONIC FILE
10-1440   Reconstruction               0-011-010  07/20/11  NO CHANGE ORDERS ON ELECTRONIC FILE
11-1029   Reconstruction               0-011-011  10/09/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            E-003          17,196                  12/10/13   02/10/14    Jordstat Construction               
                                                            GC-002              0                  06/11/14   08/01/14    Contech Building Systems            
                                                            GC-03         -17,651                  06/11/14   08/01/14    Contech Building Systems            
                                                            GC-04             898                  06/11/14   08/01/14    Contech Building Systems            
                                                            H-001           1,527                  02/24/14   03/31/14    Black River Plumbing Heating        
                                                            P-001          -1,275                  02/24/14   03/31/14    Skelly Contracting Inc.             
                                                            P-003            -889                  02/21/14   03/21/14    Skelly Contractors Inc.             
 
13-0207   Reconstruction               0-011-012  01/14/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PC-001          1,001                  06/16/14   07/31/14    Hyde-Stone Mechanical Contractors   
 
14-0004   Reconstruction               0-011-013  12/03/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001             5,346                  09/27/16   10/18/16    Siemens Industry, Inc.              
                                                            001            -4,091                  09/27/16   10/18/16    Annese & Associates, Inc.           
                                                            002             9,304                  11/21/16   01/06/17    Black Riber Plumbing & Heating, Inc.
                                                            EC-001              0                  07/15/16   10/06/16    S&L ELECTRIC                        
                                                            EC-004         19,634                  07/15/16   10/06/16    S&L ELECTRIC                        
                                                            GC-002         27,264                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
                                                            GC-003         28,937                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
                                                            GC-006         21,725                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
                                                            GC-07          63,857                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
 
14-0423   Reconstruction               0-011-014  11/04/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001             9,966                  09/02/15   09/09/15    Black Horse Group                   
                                                            002             8,502                  09/02/15   09/09/15    Black Horse Group                   
                                                            003            11,858                  09/02/15   09/09/15    Black Horse Group                   
 
16-0662   Reconstruction               0-011-015  11/07/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001            -2,800                  03/23/17   06/06/17    Tri County Carpet & Linoleum, Inc.  
                                                            GC-02          -4,000                  06/15/17   07/05/17    Tri County Carpets & Linoleum, Inc. 
 
16-2151   Reconstruction               0-011-016  03/29/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01         -41,500                  01/16/19   02/25/19    DOW ELECTRIC INC                    
                                                            EC-04               0                  01/16/19   02/25/19    DOW ELECTRIC INC                    
                                                            EC-05               0                  10/16/19   10/18/19    DOW ELECTRIC, INC.                  
                                                            EC-06           2,449                  11/07/19   11/08/19    DOW ELECTRIC, INC.                  
                                                            GC-02               0                  10/15/19   10/18/19    BLACK HORSE GROUP LLC               
                                                            MC-01          -5,000                  06/03/19   06/04/19    HYDE-STONE MECHANICAL CONTRACTORS, I
                                                            PC-02          -5,000                  06/03/19   06/04/19    LAWMAN HEATING & COOLING, INC.      
                                                            PC-03          -1,106                  06/03/19   06/04/19    LAWMAN HEATING & COOLING, INC.      
                                                            SC-01        -131,693                  01/11/19   02/06/19    CUNNINGHAM EXCAVATING, INC.         
                                                            SC-02          88,605                  01/11/19   02/06/19    CUNNINGHAM ECAVATING, INC.          
                                                            SC-03               0                  12/12/19   01/02/20    CUNNINGHAM EXCAVATING, INC.         
 
17-1846   Reconstruction               0-011-017  05/15/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            #1             25,087                  06/06/19   06/11/19    ONTARIO HVAC SOLUTIONS, INC.        
 
23-0759   Reconstruction               0-011-020  12/19/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0471FP Reconstruction               0-011-FP1  11/18/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Building -Clayton:
14-0005   Additions and Alterations    2-012-002  12/03/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-003          1,463                  07/15/16   10/06/16    S&L ELECTRIC                        
                                                            GC-005         15,306                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
                                                            MC-001              0                  07/15/16   10/06/16    CONTECH BUILDING SYSTEMS            
 

          Bus Garage/Clayton:
92-1558   Reconstruction               5-001-001  08/31/93  NO CHANGE ORDERS ON ELECTRONIC FILE
95-0107   Reconstruction               5-001-002  08/31/95  NO CHANGE ORDERS ON ELECTRONIC FILE
01-1209   Reconstruction               5-001-003  08/08/02  NO CHANGE ORDERS ON ELECTRONIC FILE
02-2234   Reconstruction               5-001-004  05/29/03  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0111   Reconstruction               5-001-005  11/21/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            002                 0                  02/02/09   03/04/09    CORY WISINSKI EXCAVATING            
                                                            P-002               0                  11/02/09   12/04/09    LAFRANCE PLUMBING & HEATING, INC.   
 
07-0004   Reconstruction               5-001-007  07/24/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PC-001         11,712                  12/07/00   01/07/08    BACH & CO                           
                                                            PC-002         13,281                  02/20/08   04/04/08    Bach & Co                           
 
14-0006   Reconstruction               5-001-008  12/03/14  NO CHANGE ORDERS ON ELECTRONIC FILE
16-1515   Reconstruction               5-001-009  06/16/16  NO CHANGE ORDERS ON ELECTRONIC FILE
21-1188   Reconstruction               5-001-011  04/06/22  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage @ Cape Vincent:
95-1588   Reconstruction               5-004-002  06/21/96  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0112   Reconstruction               5-004-003  11/21/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            H 003               0                  07/27/09   08/06/09    M&N PLUMBING & HEATING INC          
 
06-0800   Reconstruction               5-004-004  02/01/07  NO CHANGE ORDERS ON ELECTRONIC FILE
14-0007   Reconstruction               5-004-006  12/03/14  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0707   Reconstruction               5-004-007  01/29/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          Concession Building:
16-2152   New Construction             7-015-001  03/29/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-02          -5,516                  01/16/19   02/25/19    DOW ELECTRIC INC                    
                                                            EC-07           2,072                  11/07/19   11/08/19    DOW ELECTRIC, INC.                  
                                                            GC-01               0                  01/11/19   02/06/19    BLACK HORSE GROUP LLC               
                                                            GC-03         -11,565                  10/15/19   10/18/19    BLACK HORSE GROUP LLC               
                                                            GC-04          -5,370                  02/24/20   06/12/20    BLACK HORSE GROUP, LLC              
 

          Press Box @ HS/MS:
16-2153   New Construction             7-016-001  03/29/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-03          -9,193                  01/26/19   02/25/19    DOW ELECTRIC INC                    
 

          Districtwide:
95-0108   Reconstruction               7-999-001  08/31/95  NO CHANGE ORDERS ON ELECTRONIC FILE

BELLEVILLE HENDERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-09-09-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Henderson Elementary:
02-1445FP Reconstruction               0-001-FP1  05/09/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          K-12 School:
98-1093   Additions and Alterations    0-010-002  06/01/99  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            15             11,640                  01/18/02   03/27/02    RE Alexander                        
                                                            16             12,827                  01/18/02   03/27/02    RE Alexander                        
                                                            4               2,928                  10/25/01   01/08/02    Jareo Assoc.                        
                                                            5              12,050                  10/25/01   01/08/02    Jareo Assoc.                        
 
09-1565   Additions and Alterations    0-010-005  03/02/11  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            1-01           10,588                  10/13/11   12/20/11    MARCELLUS CONSTRUCTION INC          
                                                            1-01           -2,482                  04/02/12   08/31/12    BETTE & CRING GROUP                 
                                                            1-02           21,736                  10/13/11   12/20/11    MARCELLUS CONSTRUCTION INC          
                                                            1-02           -7,966                  07/26/12   01/24/13    BETTE & CRING GROUP                 
                                                            1-03          -11,264                  02/21/12   08/31/12    MARCELLUS CONSTRUCTION INC          
                                                            1-03           -5,269                  12/05/12   03/14/13    BETTE & CRING GROUP                 
                                                            1-04          -26,850                  12/05/12   03/14/13    BETTE & CRING GROUP                 
                                                            1-05           -3,397                  04/19/13   07/12/13    BETTE & CRING GROUP                 
                                                            1-06           -4,395                  10/16/13   11/15/13    BETTE & CRING GROUP                 
                                                            1-07           -1,998                  10/16/13   11/15/13    BETTE & CRING GROUP                 
                                                            100-01              0                  03/07/13   05/17/13    MARCELLUS CONSTRUCTION INC          
                                                            100-01              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-02              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-03              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-04              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-05              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-06              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-07              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-08              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            100-09              0                  04/07/14   04/18/14    Bette & Cring Construction Group    
                                                            2-01          -15,420                  12/05/12   08/16/13    DW & CREW MECHANICALS               
                                                            2-02            6,648                  04/04/13   12/04/13    DW & CREW MECHANICALS               
                                                            200-01              0                  09/24/13   02/14/14    DW & Crew Mechanicals, Inc.         
                                                            200-02              0                  09/24/13   10/11/13    DW & Crew Mechanicals, Inc.         
                                                            200-03              0                  09/24/13   02/14/14    DW & Crew Mechancials, Inc.         
                                                            200-04              0                  09/24/13   02/14/14    DW & Crew Mechanicals, Inc.         
                                                            200-05              0                  09/24/13   10/11/13    DW & Crew Mechanicals, Inc.         
                                                            3-01           -3,422                  02/27/12   09/18/12    SKELLY CONTRACTORS INC              
                                                            3-02            4,910                  02/01/13   09/19/13    SKELLY CONTRACTORS INC              
                                                            3-03              -35                  03/07/13   07/03/13    SKELLY CONTRACTORS INC              
                                                            300-01              0                  04/07/14   04/18/14    Skelly Contractors, Inc.            
                                                            300-02              0                  04/07/14   04/18/14    Skelly Contractors, Inc.            
                                                            4-01           -1,990                  10/08/13   02/14/14    S&L ELECTRIC                        
                                                            4-02            1,144                  11/19/13   01/30/14    S & L Electric                      
                                                            400-01              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-02              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-03              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-04              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-05              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-06              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-07              0                  04/07/14   04/18/14    S & L Electric                      
                                                            400-08              0                  04/07/14   04/18/14    S & L Electric                      
                                                            5-01            1,317                  12/21/12   03/22/13    DAVIS WALBRIDGE                     
                                                            501-01              0                  04/07/14   04/18/14    Davis Walbridge, Inc.               
                                                            501-02              0                  04/07/14   04/18/14    Davis Walbridge, Inc.               
                                                            502-01              0                  04/07/14   04/18/14    Davis Walbridge, Inc.               
                                                            6-01          -14,798                  06/14/13   07/18/13    Northern Glass Co.                  
                                                            6-02           -1,650                  12/09/13   01/24/14    Northern Glass Co.                  
 
08-1608   Reconstruction               0-010-006  05/12/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -7,885                  10/27/09   11/20/09    WJ FARELY ROOFING CORP              
                                                            1-01           19,848                  11/05/09   02/05/10    WJ FARELY ROOFING CORP              
                                                            1-01WOOD       -4,887                  10/27/09   11/20/09    WJ FARELY ROOFING CORP              
                                                            1-02          -16,114                  10/27/09   11/20/09    WJ FARELY ROOFING CORP              
                                                            1-02            1,113                  12/02/09   12/29/09    WJ FARELY ROOFING CORP              
                                                            1-02           13,771                  12/07/09   02/04/10    W.J. FARELY ROOFING CORP            
 
14-1289   Reconstruction               0-010-007  04/30/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001             8,287                  06/06/16   07/11/16    D.C.BUILDING SYSTEMS INC            
                                                            1              12,000                  06/06/16   10/05/16    SULLIVAN CONTRACTING                
 
15-0344   Reconstruction               0-010-008  03/10/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            002-008         1,416                  12/11/17   06/05/18    J & R Electric, Inc.                
                                                            1-Electr      -11,700                  08/16/17   10/04/17    J & R Electric, Inc.                
                                                            Mech-1         -5,000                  08/16/17   10/04/17    Black River Plumbing, Heating & Air 
                                                            Site-1         -5,000                  08/16/17   09/07/17    Bach Plumbing & Heating Co. of Clayt
 
17-1509   Reconstruction               0-010-009  05/17/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            GC-01               0                  09/30/19   10/21/19    CON TECH BUILDING SYSTEMS           
                                                            GC-03           2,829                  11/15/19   12/04/19    CON TECH BUILDING SYSTEMS           
                                                            SC-01         140,000                  11/29/19   12/12/19    EDGE CIVIL CORP.                    
                                                            SC-02           3,405                  12/13/21   01/13/23    Edge Civil Corp                     
                                                            SC-03         -10,000                  12/13/21   01/13/23    Edge Civil Corp                     
 
17-1893   Reconstruction               0-010-010  07/24/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-1675   Reconstruction               0-010-011  05/21/18  NO CHANGE ORDERS ON ELECTRONIC FILE
17-2059   Reconstruction               0-010-012  11/28/18  NO CHANGE ORDERS ON ELECTRONIC FILE
18-1972   Reconstruction               0-010-013  06/14/19  NO CHANGE ORDERS ON ELECTRONIC FILE
19-1301   Reconstruction               0-010-014  01/30/20  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0357   Reconstruction               0-010-015  10/26/20  NO CHANGE ORDERS ON ELECTRONIC FILE
20-1770   Reconstruction               0-010-016  06/23/21  NO CHANGE ORDERS ON ELECTRONIC FILE
21-2047   Reconstruction               0-010-017  08/02/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            MC-01           5,866                  06/28/23   12/29/23    ENI MECHANICAL                      
 
23-0638   Reconstruction               0-010-018  11/16/23  NO CHANGE ORDERS ON ELECTRONIC FILE
22-1960   Reconstruction               0-010-019  08/18/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage (Union)sold:
95-1117   New Construction             5-003-001  04/25/96  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage-Belleville:
90-1594   Reconstruction               5-004-001  07/08/91  NO CHANGE ORDERS ON ELECTRONIC FILE
14-1290   Reconstruction               5-004-002  04/30/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            001            15,414                  06/06/16   07/11/16    BARRETT PAVING MATERIALS            
                                                            Asbest-2       -5,000                  08/16/17   09/07/17    Sullivan Contracting, Inc.          
                                                            Site-1         15,414                  08/16/17   09/07/17    Barrett Paving Materials, Inc.      
 
15-0345   Reconstruction               5-004-003  03/10/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            Abesto-3       51,000                  08/16/17   09/07/17    Sullivan Contracting, Inc.          
 
17-1508   Reconstruction               5-004-004  05/17/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-02          13,311                  09/30/19   10/21/19    CON TECH BUILDING SYSTEMS           
                                                            GC-04           3,879                  10/30/19   10/31/19    CON TECH BUILDING SYSTEMS           
 
17-2060   Reconstruction               5-004-005  11/28/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01          -5,000                  12/13/21   01/13/23    J&R Elec                            
                                                            MC-01          -2,868                  10/30/19   11/01/19    ENI MECHANICAL, INC.                
                                                            MC-02          -5,000                  12/13/21   01/13/23    ENI Mech Inc                        
                                                            PC-01           1,272                  09/30/19   10/07/19    BLACK RIVER PHAC                    
                                                            PC-02          -1,060                  12/13/21   01/13/23    Black River PHAC                    
 
22-1961   Reconstruction               5-004-006  08/18/23  NO CHANGE ORDERS ON ELECTRONIC FILE

SACKETS HARBOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-10-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Building K-12:
91-1314   Alterations                  0-001-004  06/17/92  NO CHANGE ORDERS ON ELECTRONIC FILE
98-1667   Additions and Alterations    0-001-006  08/17/99  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            8              14,917                  11/22/00   12/01/03    ED Young                            
                                                            9               7,412                  11/22/00   12/01/03    ED Young                            
 
07-0119   Reconstruction               0-001-007  02/29/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1A-01         -37,209                  09/10/08   01/28/09    PUTRELO CONSTRUCTION                
                                                            1A-02         -17,021                  10/29/08   02/02/09    PUTRELO CONSTRUCTION                
                                                            1A-03           2,291                  05/29/09   07/14/09    PUTRELO CONSTRUCTION                
                                                            1A-04           2,836                  05/29/09   07/14/09    PUTRELO CONSTRUCTION                
                                                            1A-05           3,908                  06/29/09   07/22/09    PUTRELO CONSTRUCTION                
                                                            1A-06           2,253                  06/29/09   08/06/09    PUTRELO CONSTRUCTION                
                                                            1A-07           1,630                  08/26/09   09/18/09    PUTRELO CONSTRUCTION                
                                                            2-01           11,082                  11/02/09   07/20/10    NORTHERN MECHANICALS                
                                                            2-02              569                  11/02/09   07/20/10    NORTHERN MECHANICALS                
                                                            2-03            4,842                  11/02/09   07/20/10    NORTHERN MECHANICALS                
                                                            2-04            1,293                  07/21/09   08/06/09    NORTHERN MECHANICAL                 
                                                            2-05           12,104                  07/21/09   08/06/09    NORTHERN MECHANICAL                 
                                                            3-01            1,899                  09/01/09   09/17/09    OSWEGO MECHANICAL                   
                                                            4-01            5,395                  11/23/09   03/12/10    COLLINS-HAMMOND ELECTRICAL          
                                                            4-02             -217                  11/12/09   08/23/12    COLLINS-HAMMOND ELECTRICAL          
 
07-0326   Reconstruction               0-001-008  01/18/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1B-01         -23,700                  07/15/08   10/07/08    A. J. MONTCLAIR                     
                                                            1B-02          11,491                  08/27/08   02/05/09    A.J. Montclair                      
                                                            1B-03           1,963                  10/02/08   05/14/09    A.J. MONTCLAIR                      
                                                            2-02              569                  03/19/09   07/06/09    NORTHERN MECHANCIALS                
                                                            2-03            4,842                  03/19/09   07/06/09    NORTHERN MECHANICALS                
                                                            2-04            1,293                  04/24/09   07/22/09    NORTHERN MECHANICALS                
                                                            2-05          -12,104                  05/06/09   07/30/09    NORHTERN MECHANCIALS                
 
17-0313   Reconstruction               0-001-009  10/25/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           34,370                  07/10/18   08/06/18    LAWMAN HEATING & COOLING INC        
                                                            1-02            3,846                  07/10/18   08/06/18    LAWMAN HEATING & COOLING INC        
                                                            1-03            5,717                  07/16/18   08/06/18    LAWMAN HEATING & COOLING INC        
                                                            1-04           10,565                  10/10/18   01/25/19    LAWMAN HEATING & COOLING INC        
                                                            1-05 V2        -3,057                  01/18/19   03/12/19    LAWMAN HEATING & COOLING, INC.      
                                                            1-101               0                  07/22/19   10/07/19    LAWMAN HEATING & COOLING, INC.      
                                                            1-102               0                  07/22/19   10/07/19    LAWMAN HEATING & COOLING, INC.      
                                                            106             4,370                  03/06/19   03/12/19    LAWMAN HEATING & COOLING            
                                                            2-01          -27,827                  05/15/18   08/06/18    RSI ROOFING, INC.                   
                                                            2-02          -31,365                  11/27/18   01/24/19    RSI Roofing, INC.                   
                                                            2-101               0                  07/22/19   10/07/19    RSI ROOFING, INC.                   
                                                            2-103               0                  07/22/19   10/07/19    RSI ROOFING INC.                    
                                                            2-104               0                  07/22/19   10/07/19    RSI ROOFING INC.                    
 
17-0379   Reconstruction               0-001-010  09/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           29,933                  06/27/19   07/05/19    NORTHERN TIER CONTRACTING INC.      
                                                            1-02           22,509                  06/27/19   07/05/19    NORTHERN TIER CONTRACTING INC.      
                                                            1-03           19,595                  06/27/19   07/05/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-04           20,806                  06/27/19   07/05/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-05           15,069                  06/27/19   07/05/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-06           76,306                  09/25/19   10/07/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-07           32,022                  10/29/19   11/04/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-08           15,570                  11/22/19   12/18/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-09           25,817                  11/22/19   12/18/19    NORTHERN TIER CONTRACTING, INC.     
                                                            1-10           36,114                  01/07/20   01/30/20    NORTHERN TIER CONTRACTING, INC.     
                                                            1-11           -1,126                  01/17/20   02/13/20    NORTHERN TIER CONTRACTING, INC.     
                                                            1-12           15,008                  01/17/20   02/13/20    NORTHERN TIER CONTRACTING, INC.     
                                                            1-13           -4,616                  03/09/20   07/06/20    NORTHERN TIER CONTRACTING, INC.     
                                                            2-01          -35,528                  01/17/20   02/10/20    BLACK RIVER PLUMBING, HEATING & AC  
                                                            3-01           -3,846                  02/05/20   03/06/20    J.E. SHEEHAN CONTRACTING CORP.      
                                                            4-01           24,000                  10/29/19   10/31/19    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            4-02           29,558                  01/17/20   02/10/20    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            4-03           26,484                  01/17/20   02/10/20    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            4-05            1,300                  02/27/20   06/29/20    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            AA101-01            0                  10/20/21   12/05/22    Northern Tier Contracting           
                                                            AA101-02            0                  10/20/21     /  /      Northern Tier Contracting           
                                                            AA101-03            0                  10/20/21   12/05/22    Northern Tier Contracting           
                                                            AA101-04            0                  10/20/21   12/05/22    Northern Tier Contracting           
                                                            AA101-05            0                  10/20/21   12/05/22    Northern Tier Contracting           
                                                            AA201-01            0                  10/20/21   12/05/22    Black River PlumbHeatAir Con Inc    
                                                            AA201-02            0                  10/20/21   12/05/22    Black River Plumb Heat&Air          
                                                            AA201-03            0                  10/20/21   12/05/22    Black River Plumbing Heat&Air       
                                                            AA301-01            0                  10/20/21   12/05/22    J.E. Sheehan Contracting            
                                                            AA301-02            0                  10/20/21   12/05/22    JE Sheehan Contracting              
                                                            AA401-01            0                  10/20/21   12/05/22    Collins-Hammond Electric Contrs     
                                                            AA401-02            0                  10/20/21   12/05/22    Collins-Hammond Electric            
                                                            CC-01           2,090                  01/17/20   02/10/20    TRANE BUILDING SYSTEMS              
 
19-0963   Reconstruction               0-001-011  02/20/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           24,422                  12/28/20   03/16/21    SIERRA DELTA CONTRACTING, INC.      
                                                            1-02           18,807                  12/28/20   03/16/21    SIERRA DELTA CONTRACTING, INC.      
                                                            101-02AA            0                  12/15/21   10/11/22    Sierra Delta Contr LLC              
                                                            101-03AA            0                  12/15/21   10/11/22    Sierra Delta Contr LLC              
                                                            2-01           11,640                  12/28/20   03/02/21    ONTARIO HVAC SOLUTIONS, INC.        
                                                            2-02           -2,044                  05/10/21   08/27/21    ONTARIO HVAC SOLUTIONS, INC.        
                                                            201-01AA            0                  12/15/21   09/27/22    Ontario HVAC Sols                   
                                                            3-01             -588                  03/03/21   04/20/21    ONTARIO HVAC SOLUTIONS, INC.        
                                                            301-01AA            0                  12/15/21   09/27/22    Ontario HVAC Sols                   
                                                            4-01            3,346                  03/03/21   04/20/21    TEL, INC.                           
                                                            401-01AA            0                  12/15/21   09/27/22    TEL Inc                             
                                                            402-01AA            0                  12/15/21   09/27/22    TEL Inc                             
 
02-0523FP Reconstruction               0-001-FP1  11/21/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Garage:
91-1315   Reconstruction               5-002-001  06/17/92  NO CHANGE ORDERS ON ELECTRONIC FILE
98-1668   Reconstruction               5-002-002  08/17/99  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0314   Reconstruction               5-002-003  10/25/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2-102               0                  07/22/19   10/07/19    RSI ROOFING, INC.                   
                                                            2-105               0                  07/22/19   10/07/19    RSI ROOFING INC.                    
 
17-0380   Reconstruction               5-002-004  09/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            4-04            4,463                  01/17/20   02/10/20    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            AA101-01            0                  10/20/21     /  /      Northern Tier Contracting           
                                                            AA101-03            0                  10/20/21     /  /      Northern Tier Contracting           
                                                            AA301-01            0                  10/20/21     /  /      JE Sheehan Contracting              
                                                            AA301-03            0                  10/20/21     /  /      JE Sheehan Contracting              
 
19-0964   Reconstruction               5-002-005  02/25/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            101-01AA            0                  12/15/21   10/11/22    Sierra Delta Contr LLC              
                                                            301-02AA            0                  12/15/21   09/27/22    Ontario HVAC Sols                   
                                                            401-02AA            0                  12/15/21   09/27/22    TEL Inc                             
 

          Outdoor Classroom Pavilion:
22-1762FA New Construction             7-006-001  05/24/23  NO CHANGE ORDERS ON ELECTRONIC FILE

LYME CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-13-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Building:
95-1094   Additions and Alterations    0-002-001  06/04/96  NO CHANGE ORDERS ON ELECTRONIC FILE
98-0329   Reconstruction               0-002-002  12/15/98  NO CHANGE ORDERS ON ELECTRONIC FILE
00-1463   Additions and Alterations    0-002-003  09/28/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001           9,649                  12/22/04   12/23/04    ConTech Building Systems            
                                                            1-002         -39,842                  12/22/04   12/23/04    ConTech Building Systems            
                                                            1-003          21,250                  12/22/04   06/05/06    ConTech Building Systems            
                                                            1-004          10,206                  03/25/03   04/17/03    ConTech Building Systems            
                                                            1-005          37,561                  05/15/03   05/23/03    ConTech Building Systems            
                                                            1-006             684                  07/07/03   07/09/03    ConTech Building Systems            
                                                            2-002          -5,746                  09/22/03   11/26/03    Edward Galvin                       
                                                            2-003             700                  09/22/03   12/17/03    Edward Galvin                       
                                                            3-001            -399                  08/28/03   10/23/03    Hyde Stone Mech.                    
                                                            4-002           4,777                  09/22/03   11/26/03    New Century Elec.                   
                                                            4-004R          6,702                  10/29/03   06/05/06    New Century Elec.                   
 
09-0668   Additions and Alterations    0-002-005  04/29/10  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            1-01           16,897                  02/03/11   03/02/11    MCK BUILDING ASSOCIATES             
                                                            1-01                0                  02/13/14   03/20/14    MCK Building Associates, Inc.       
                                                            1-02           12,274                  02/03/11   03/02/11    MCK BUILDING ASSOCIATES             
                                                            1-02                0                  02/13/14   03/20/14    MCK Building Associates, Inc.       
                                                            1-03           16,586                  02/03/11   03/02/11    MCK BUILDING ASSOCIATES             
                                                            1-03                0                  02/13/14   03/20/14    MCK Building Associates, Inc.       
                                                            1-04            6,902                  02/03/11   03/02/11    MCK BUILDING ASSOCIATES             
                                                            1-04                0                  02/13/14   03/20/14    MCK Building Associates, Inc.       
                                                            1-05           10,331                  03/23/11   04/22/11    MCK BUILDING ASSOCIATES             
                                                            1-05                0                  02/13/14   03/20/14    MCK Building Associates, Inc.       
                                                            1-06           -3,967                  07/26/11   09/21/11    MCK BUILDING ASSOCIATES             
                                                            1-07            5,460                  07/29/11   09/07/11    MCK BUILDING ASSOCIATES             
                                                            2-01            5,178                  07/20/11   08/05/11    BLACK RIVER PLUMBING & HEATING INC  
                                                            2-01                0                  02/13/14   03/20/14    Black River Plumbing & Heating, Inc.
                                                            2-02            9,203                  05/22/12   07/03/13    BLACK RIVER PLUMBING & HEATING INC  
                                                            2-02                0                  02/13/14   03/20/14    Black River Plumbing & Heating, Inc.
                                                            3-01            4,922                  02/14/11   03/02/11    EMPIRE NORTHEAST INC                
                                                            3-01                0                  02/13/14   03/20/14    Empire Northeast, Inc.              
                                                            3-01PR              0                  02/13/14   03/20/14    Empire Northeast, Inc.              
                                                            4-01           70,216                  11/29/10   12/31/10    JORDSTAT CONSTRUCTION INC           
                                                            4-01                0                  02/13/14   03/20/14    Jordstat Construction, Inc.         
                                                            4-02            3,854                  11/29/10   12/31/10    JORDSTAT CONSTRUCTION INC           
                                                            4-03            6,739                  01/25/11   03/14/11    JORDSTAT CONSTRUCTION INC           
                                                            4-04            6,392                  02/25/11   03/18/11    JORDSTAT CONSTRUCTION INC           
                                                            5-01            1,823                  02/25/11   03/18/11    PTL CONTRACTING CORP                
                                                            5-01                0                  02/13/14   03/20/14    PTL Contracting Corp.               
                                                            6-01           15,085                  10/22/10   11/23/10    FIACCO & RILEY CONSTRUCTION INC     
                                                            6-01                0                  02/13/14   03/20/14    Fiacco & Riley Construction, Inc.   
                                                            6-02           10,286                  10/22/10   11/23/10    FIACCO & RILEY CONSTRUCTION INC     
                                                            6-03           76,152                  11/16/10   11/30/10    FIACCO & RILEY CONSTRUCTION INC     
                                                            6-04            6,000                  03/21/11   06/10/11    FIACCO & RILEY CONSTRUCTION INC     
                                                            6-05           25,207                  06/20/11   07/01/11    FIACCO & RILEY CONSTRUCTION INC     
 
12-1211   Reconstruction               0-002-007  05/24/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -4,603                  09/25/13   11/01/13    RSI Roofing                         
                                                            1-02          -14,964                  03/06/14   05/30/14    RSI Roofing                         
                                                            100-01              0                  03/06/14   05/30/14    RSI Roofing                         
                                                            100-02              0                  03/06/14   05/30/14    RSI Roofing                         
                                                            100-03              0                  03/06/14   05/30/14    RSI Roofing                         
                                                            100-04              0                  03/06/14   05/30/14    RSI Roofing                         
                                                            100-05              0                  03/06/14   05/30/14    RSI Roofing                         
 
13-1148   Reconstruction               0-002-008  08/04/14  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -51,605                  01/21/15   01/29/15    Continental Construciton            
                                                            1-02           25,498                  03/21/16     /  /      Continental Construction            
                                                            1-03           -2,256                  06/15/16   07/08/16    CONTINENTAL CONSTRUCTION            
 
02-0343FP Reconstruction               0-002-FP1  11/18/02  NO CHANGE ORDERS ON ELECTRONIC FILE
06-0892SC Visual Structural Inspection 0-002-SC1  02/07/07  NO CHANGE ORDERS ON ELECTRONIC FILE

          Bus Maintenance Garage:
95-1093   Reconstruction               5-001-001  06/04/96  NO CHANGE ORDERS ON ELECTRONIC FILE

          Fuel Station:
98-0330   New Construction             5-005-001  12/15/98  NO CHANGE ORDERS ON ELECTRONIC FILE

          New Bus Garage:
00-1464   New Construction             5-006-001  09/28/01  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            2-001          -6,665                  10/24/03   06/05/06    Edward Galvin                       
                                                            4-001           3,370                  09/22/03   12/17/03    New Century Elec.                   
                                                            4-003           6,019                  10/29/03   06/05/06    New Century Elec.                   
                                                            5-001          10,921                  12/22/04   12/23/04    Jareo Assoc.                        
                                                            5-002          -3,607                  12/22/04   12/23/04    Jareo Assoc.                        
                                                            5-003          -1,700                  05/31/06   06/05/06    Jareo Associatesx                   
 

LAFARGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-14-01-04
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Main Building:
94-0026   Additions and Alterations    0-001-001  09/14/94  NO CHANGE ORDERS ON ELECTRONIC FILE
94-1545   Reconstruction               0-001-002  06/07/95  NO CHANGE ORDERS ON ELECTRONIC FILE
95-0781   Reconstruction               0-001-003  03/22/96  NO CHANGE ORDERS ON ELECTRONIC FILE
97-1476   Reconstruction               0-001-004  07/10/98  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0133   Reconstruction               0-001-005  11/29/99  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1               6,544                  06/17/02   07/10/02    RE Alexander Co.                    
                                                            2              11,496                  01/10/02   03/26/02    RE Alexander Co.                    
                                                            3               1,665                  01/10/02   03/26/02    RE Alexander Co.                    
                                                            4              -7,500                  04/30/02   05/09/02    RE Alexander Co.                    
 
01-1026   Reconstruction               0-001-006  05/03/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1             -10,055                  03/25/03   03/28/03    PTL Contracting                     
 
04-0023   Reconstruction               0-001-007  08/25/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1               1,550                  12/02/04   12/17/04    Ritchie Brothers                    
                                                            2               4,339                  03/31/05   04/27/05    Ritchie Brothers                    
 
08-0761   Additions and Alterations    0-001-008  05/07/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01            7,484                  09/14/10   09/29/10    MCK BUILDING ASSOCIATES             
                                                            1-02           31,292                  09/14/10   09/29/10    MCK BUILDING ASSOCIATES             
                                                            1-03           17,452                  09/14/10   09/29/10    MCK BUILDING ASSOCIATES             
                                                            1-04            2,868                  09/14/10   09/29/10    MCK BUILDING ASSOCIATES             
                                                            1-05          -57,723                  01/14/11   02/18/11    MCK BUILDING ASSOCIATES             
                                                            1-06            5,010                  01/14/11   02/18/11    MCK BUILDING ASSOCIATES             
                                                            1-07           -3,932                  01/14/11   02/18/11    MCK BUILDING ASSOCIATES             
                                                            1-08            9,939                  01/14/11   02/18/11    MCK BUILDING ASSOCIATES             
                                                            1-09            7,356                  01/14/11   02/18/11    MCK BUILDING ASSOCIATES             
                                                            1-10            8,941                  02/08/11   02/25/11    MCK BUILDING ASSOCIATES             
                                                            1-11           13,751                  02/08/11   05/18/11    MCK BUILDING ASSOCIATES             
                                                            1-12            2,459                  02/08/11   02/25/11    MCK BUILDING ASSOCIATES             
                                                            1-13            2,497                  02/08/11   02/25/11    MCK BUILDING ASSOCIATES             
                                                            1-14            9,043                  02/08/11   02/25/11    MCK BUILDING ASSOCIATES             
                                                            1-15           19,500                  02/22/11   03/18/11    MCK BUILDING ASSOCIATES             
                                                            1-16            2,597                  03/24/11   04/22/11    MCK BUILDING ASSOCIATES             
                                                            1-17            9,763                  03/24/11   04/22/11    MCK BUILDING ASSOCIATES             
                                                            1-18           -7,396                  10/12/12   02/22/13    MCK BUILDING ASSOCIATES             
                                                            10-01         -30,391                  09/20/11   12/22/11    SUSTAINABLE ENERGY DEVELOPMENTS     
                                                            10-02             930                  11/10/11   01/30/12    SUSTAINABLE ENERGY DEVELOPMENTS     
                                                            2-01          -21,747                  05/02/12   09/07/12    BURNS BROS CONTRACTORS              
                                                            3-01             -871                  05/09/11   05/20/11    TMECHANICAL INC                     
                                                            4-01          -87,690                  10/20/09   11/12/09    HUEN NEW YORK INC                   
                                                            4-02          -17,894                  03/26/10   05/14/10    HUEN NEW YORK INC                   
                                                            4-03           15,948                  11/17/10   11/17/10    HUEN NEW YORK INC                   
                                                            4-04            2,650                  12/06/10   12/28/10    HUEN NEW YORK INC                   
                                                            4-05              637                  01/14/11   02/18/11    HUEN NEW YORK INC                   
                                                            4-06            7,257                  03/24/11   04/22/11    HUEN NEW YORK INC                   
                                                            4-07            3,229                  06/17/11   07/13/11    HUEN NEW YORK INC                   
                                                            4-08            4,525                  01/24/12   07/17/12    HUEN NEW YORK INC                   
                                                            5-01           13,572                  02/05/10   03/19/10    WD BACH EXCAVATING                  
                                                            5-02           10,278                  11/17/10   11/17/10    WD BACH EXCAVATING                  
                                                            5-03            5,522                  11/17/10   11/17/10    WD BACH EXCAVATING                  
                                                            5-04              637                  05/04/11   05/20/11    WD BACH EXCAVATING                  
                                                            5-05            4,300                  07/07/11   07/28/11    WD BACH EXCAVATING                  
                                                            5-06            1,775                  06/07/12   10/24/12    WD BACH EXCAVATING                  
                                                            6-01           -6,580                  10/15/09   11/12/09    RSI ROOFING                         
                                                            6-02              309                  01/14/11   02/18/11    RSI ROOFING                         
                                                            6-03              690                  01/27/11   02/24/11    RSI ROOFING                         
                                                            6-04           20,477                  05/23/11   07/13/11    RSI ROOFING                         
                                                            7-01            1,556                  03/24/11   04/22/11    PROFESSIONAL FURNISHINGS & EQUIPMENT
                                                            8-01           -6,318                  12/07/12   03/14/13    SYRACUSE SCENERY & STAGE LIGHTING CO
                                                            9-01           -2,692                  12/08/09   01/08/10    B&D ENTERPRISES                     
                                                            9-02          -43,008                  11/17/10   11/17/10    B&D ENTERPRISES                     
                                                            FO 1-01             0                  12/04/12   03/08/13    MCK BUILDING ASSOCIATES             
                                                            FO 1-02             0                  12/04/12   03/08/13    MCK BUILDING ASSOCIATES             
                                                            FO 1-03             0                  12/04/12   03/08/13    MCK BUILDING ASSOCIATES             
                                                            FO 1-04             0                  12/04/12   03/08/13    MCK BUILDING ASSOCIATES             
                                                            FO 1-05             0                  12/04/12   03/08/13    MCK BUILDING ASSOCIATES             
                                                            FO 2-01             0                  12/04/12   06/28/13    BURNS BROS CONTRACTORS              
                                                            FO 2-02             0                  12/04/12   06/28/13    BURNS BROS CONTRACTORS              
                                                            FO 2-03             0                  12/04/12   06/28/13    BURNS BROS CONTRACTORS              
                                                            FO 3-01             0                  12/04/12   06/28/13    TMACHANICAL INC                     
                                                            FO 3-02             0                  12/04/12   06/28/13    TMACHANICAL INC                     
                                                            FO 3-03             0                  12/04/12   06/28/13    TMACHANICAL INC                     
                                                            FO 3-04             0                  12/04/12     /  /      TMACHANICAL INC                     
                                                            FO 3-05             0                  12/04/12   06/28/13    TMACHANICAL INC                     
                                                            FO 3-06             0                  12/04/12   06/28/13    TMACHANICAL INC                     
                                                            FO 4-01             0                  12/04/12   06/28/13    HUEN NY                             
                                                            FO 4-02             0                  12/04/12   06/28/13    HUEN NY                             
                                                            FO 4-03             0                  12/04/12   06/28/13    HUEN NEW YORK                       
                                                            FO 4-04             0                  12/04/12   06/28/13    HUEN NEW YORK                       
                                                            FO 4-05             0                  12/04/12   06/28/13    HUEN NEW YORK                       
                                                            FO 4-06             0                  12/04/12   06/28/13    HUEN NEW YORK                       
                                                            FO 5-01             0                  12/04/12   03/08/13    WD BACH EXCAVATING                  
                                                            FO 5-02             0                  12/04/12   03/08/13    WD BACH EXCAVATING                  
                                                            FO 5-03             0                  12/04/12   03/08/13    WD BACH                             
                                                            FO 5-04             0                  12/04/12   03/08/13    WD BACH                             
                                                            FO 6-01             0                  12/04/12   03/08/13    RSI ROOFING                         
                                                            FO 6-02             0                  12/04/12   03/08/13    RSI ROOFING                         
                                                            FO 6-03             0                  12/04/12   03/08/13    RSI ROOFING                         
                                                            FO 6-04             0                  12/04/12   03/08/13    RSI ROOFING                         
                                                            FO5-01r             0                  12/04/12   03/08/13    WD BACH EXCAVATING                  
                                                            WNYF-1          6,342                  10/31/12   03/08/13    WESTERN NEW YORK FLOOR CO           
 
09-1301   Reconstruction               0-001-009  06/18/10  NO CHANGE ORDERS ON ELECTRONIC FILE
17-0010   Reconstruction               0-001-010  04/23/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01 R1        10,626                  05/01/19   06/05/19    DOW ELECRTRIC, INC.                 
 
17-0493   Reconstruction               0-001-011  08/29/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -9,900                  02/01/18   02/21/18    AAC Contracting, Inc.               
 
19-0629   Reconstruction               0-001-012  12/31/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -10,237                  04/21/20   07/22/20    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-02              249                  12/03/20   05/10/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            101-01              0                  12/03/20   05/10/21    CONTINENTAL CONSTRUCTION, LLC       
 
20-0157   Reconstruction               0-001-013  10/02/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           49,347                  03/31/21   05/05/21    BRG CORP.                           
                                                            1-02            2,985                  06/08/21   11/02/21    BRG Corporation                     
                                                            1-03            9,544                  06/11/21   03/15/22    BRG Corporation                     
 

          Field Storage Building:
97-1475   New Construction             2-004-001  07/10/98  NO CHANGE ORDERS ON ELECTRONIC FILE

          Transporatation Building:
97-1474   New Construction             5-003-001  07/10/98  NO CHANGE ORDERS ON ELECTRONIC FILE

          District-Wide:
17-0011   Reconstruction               7-999-001  04/23/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01            2,847                  02/27/20   06/30/20    WHITTON CONSTRUCTION, LLC           
                                                            2-01            1,038                  09/23/19   09/30/19    DOW ELECTRIC, INC.                  
 

WATERTOWN CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-20-00-01
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          XXCase Junior High School:
93-1513   Reconstruction               0-009-003  08/02/94  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0101   Reconstruction               0-009-005  12/23/99  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            R-1            -4,535                  10/23/01   01/08/02    Ritter & Paratore Contracting       
                                                            R-2           -10,512                  09/23/02   10/28/02    Ritter &d ParatoreContracting       
 

          North Elementary:
92-0557   Reconstruction               0-010-002  04/23/93  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1334   Reconstruction               0-010-003  05/11/00  NO CHANGE ORDERS ON ELECTRONIC FILE
03-1692   Reconstruction               0-010-004  07/26/04  NO CHANGE ORDERS ON ELECTRONIC FILE
05-0863   Reconstruction               0-010-005  03/16/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-002          45,446                  09/18/06   11/30/06    Bette Cring                         
                                                            1-003          19,239                  10/13/06   12/19/06    Bette Cring                         
                                                            2-001          27,820                  09/18/06   01/30/07    M and N Plumbing                    
                                                            3-004           3,695                  04/27/09   07/28/09    NORWOOD PLUMBING INC                
                                                            4-008             960                  09/05/08   04/23/09    COLLINS - HAMMOND ELECTRICAL        
 
08-1324   Reconstruction               0-010-006  09/04/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001          10,245                  03/25/10   05/14/10    BETTE & CRING                       
                                                            1-08            1,206                  11/16/10   11/17/10    BETTE & CRING                       
                                                            1-10                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            4-03            6,612                  09/03/10   09/24/10    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            4-07           -4,400                  11/12/10   11/16/10    COLLINS-HAMMOND ELECT. CONTRACTORS  
 
10-0413   Reconstruction               0-010-007  11/17/10  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -73,604                  09/13/11   11/04/11    RSI ROOFING INC                     
 
11-0233   Reconstruction               0-010-008  08/09/11  NO CHANGE ORDERS ON ELECTRONIC FILE
11-0837   Reconstruction               0-010-009  06/15/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-09            2,244                  10/08/13   12/09/13    BETTE & CRING                       
                                                            100-04              0                  05/02/14   05/21/14    Bette & Cring, LLC                  
                                                            3-03             -770                  09/11/13     /  /      Dow Electric                        
                                                            300-03              0                  02/20/14   03/13/14    Dow Electric                        
 
15-0118   Reconstruction               0-010-010  05/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            10-02          -2,925                  01/04/18     /  /      COMALLI TECH SYSTEMS                
                                                            10-09           6,800                  03/09/18   03/27/18    Comalli Tech Systems                
                                                            5-13            7,350                  11/13/18   01/22/19    BETTE & CRING, LLC                  
                                                            8-15              779                  04/23/18   05/31/18    Collins-Hammond Electrical Cont.    
 
17-1962   Reconstruction               0-010-011  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-03              690                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            100-03              0                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            3-02              361                  02/09/21   03/30/21    DOW ELECTRIC, INC.                  
                                                            3-07              -73                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
                                                            300-02              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
 
02-0734FP Reconstruction               0-010-FP1  12/24/02  NO CHANGE ORDERS ON ELECTRONIC FILE
08-1369SC Visual Structural Inspection 0-010-SC1  03/17/09  NO CHANGE ORDERS ON ELECTRONIC FILE

          Knickerbocker Elementary:
95-0574   Additions and Alterations    0-011-002  03/29/96  NO CHANGE ORDERS ON ELECTRONIC FILE
05-0864   Additions and Alterations    0-011-003  03/16/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-017          24,024                  07/18/08   09/29/08    BETTE & CRING, LLC                  
                                                            5-004           7,627                  12/08/06   01/19/07    Cory Wisinski Excavating            
                                                            6-001         189,000                  07/27/06   08/25/06    RSi roofing                         
 
08-1325   Additions and Alterations    0-011-004  09/04/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-002               0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            3-01           -1,901                  10/31/11   12/29/11    BROSH MECHANICAL INC                
                                                            4-04            5,750                  09/03/10   09/24/10    COLLINS-HAMMOND ELECTRICAL CONT.    
 
11-0838   Reconstruction               0-011-005  06/15/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-08           -2,300                  09/24/13   11/01/13    Bette & Cring                       
 
15-0119   Reconstruction               0-011-006  05/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            10-03          -4,820                  02/05/18   03/27/18    Comalli Tech Systems                
                                                            10-04             860                  03/09/18   05/21/18    Comalli Tech Systems                
                                                            5-10            5,145                  11/09/17   02/02/18    Bette & Cring, LLC                  
                                                            8-06           21,009                  10/11/17   06/17/19    Collins-Hammond Electrical Contracto
                                                            8-07           17,960                  10/11/17   10/31/17    Collins-Hammond Electrical Contracto
                                                            8-08              507                  11/06/17   11/16/17    Collins-Hammond Electrical Contracto
                                                            8-12            1,346                  01/04/18   03/27/18    COLLINS-HAMMOND ELECTRICAL          
                                                            800-001          -877                  08/08/18   01/02/19    COLLINS-HAMMOND ELECTRICAL CONTRACTO
                                                            9-02           24,300                  09/12/17   09/14/17    PTL Contracting Corp.               
                                                            AA-01          -4,820                  01/04/18     /  /      COMALLI TECH SYSTEMS                
 
17-1963   Reconstruction               0-011-007  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-02             -780                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            3-04              295                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
                                                            300-04              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
 
22-0706   Reconstruction               0-011-008  01/13/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Sherman Elementary School:
05-0865   Additions and Alterations    0-012-003  03/16/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001          16,922                  07/27/06   08/25/06    Bette Cring                         
                                                            1-004           9,633                  04/10/07   05/25/07    Bette Cring                         
                                                            1-010           2,371                  01/16/08   01/23/08    Bette & Cring                       
                                                            1-015           4,275                  05/13/08   12/09/08    Bette & Cring                       
                                                            5-006           7,960                  12/08/06   01/19/07    Cory Wisinski Excavating            
 
08-1326   Reconstruction               0-012-004  09/04/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-04            1,241                  09/30/10   10/29/10    BETTE & CRING                       
                                                            1-07            6,033                  11/16/10   11/17/10    BETTE & CRING                       
                                                            1-09                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-11                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-13                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-15                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-20                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-22                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            3-03            1,885                  12/24/10   02/22/11    BROSH MECHANICAL INC                
                                                            3-04              301                  02/17/11   03/09/11    BROSH MECHANICAL INC                
                                                            3-04           -3,286                  10/31/11   12/29/11    BROSH MECHANICAL INC                
                                                            4-06            6,037                  09/03/10   09/24/10    COLLINS-HAMMOND ELECTRICAL CONT.    
 
08-1430   Reconstruction               0-012-005  04/30/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            11B-001       -20,065                  10/06/09   10/28/09    RSI ROOFING                         
 
11-0839   Reconstruction               0-012-006  06/15/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                                                0                    /  /       /  /                                          
                                                            1-03           -3,456                  08/13/13   11/25/13    Bette & Cring                       
                                                            1-07             -869                  09/11/13   09/13/13    Bette & Cring                       
                                                            100-02              0                  10/26/13   12/06/13    Cunningham Excavation               
                                                            3-02             -682                  08/20/13   03/07/14    Dow Electric                        
 
15-0120   Reconstruction               0-012-007  05/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            10-06             430                  03/09/18   05/21/18    Comalli Tech Systems                
                                                            1000-003            0                  08/08/18   01/03/19    COMALLI TECHNOLOGY SYSTEMS          
                                                            1000-004            0                  08/08/18   01/03/19    COMALLI TECHNOLOGY SYSTEMS          
                                                            5-01            2,517                  09/12/17   09/14/17    Bette & Cring, LLC                  
                                                            5-03           15,017                  10/03/17   10/13/17    Bette & Cring, LLC                  
                                                            8-13            1,367                  02/23/18   05/16/18    Collins-Hammond Electrical Cont.    
 
17-1964   Reconstruction               0-012-008  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-08            1,186                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            100-04              0                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            3-03              197                  02/09/21   03/30/21    DOW ELECTRIC, INC.                  
                                                            300-03              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
 

          Watertown High School:
92-0776   Reconstruction               0-015-002  04/23/93  NO CHANGE ORDERS ON ELECTRONIC FILE
96-1125   Reconstruction               0-015-003  03/28/97  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0477   Additions and Alterations    0-015-004  03/17/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              25,044                  03/28/02   04/26/02    Professional Furnishings            
                                                            1              28,501                  11/22/02   01/02/03    Barrett Paving                      
                                                            1              -2,477                  04/08/03   04/21/03    M&N Plumbing                        
                                                            1              -5,704                  12/16/03   12/17/03    M&N Plumbing                        
                                                            2              55,510                  03/28/02   04/26/02    Professional Furnishings & Equip.   
                                                            CT-1           29,239                  10/10/01   01/08/02    ConTech Building Systems            
                                                            CT-11          11,251                  07/30/02   08/28/02    ConTech Building Systems            
                                                            CT-12           9,131                  02/12/03   02/19/03    COnTech Building Systems            
                                                            CT-13           5,480                  02/19/03   03/24/03    ConTech Building Systems            
                                                            CT-14          14,348                  02/19/03   03/24/03    ConTech Building Systems            
                                                            CT-15          56,000          56,000  12/23/03   12/30/03    ConTech Building Systems            
                                                            CT-16           2,730           2,730  12/23/03   03/19/04    ConTech Building Systems            
                                                            CT-17           9,358           9,358  12/23/03   03/19/04    ConTech Building Systems            
                                                            CT-2            3,207                  06/16/03   06/17/03    ConTech Building Systems            
                                                            CT-3            3,030                  01/10/02   03/26/02    ConTech Building Systems            
                                                            CT-4           10,205                  02/13/02   04/01/02    ConTech Building Systems            
                                                            CT-5           23,395                  02/28/02   06/17/03    ConTech Building Systems            
                                                            CT-6           20,564                  02/28/02   04/25/02    ConTech Building Systems            
                                                            CT-7           27,650                  02/28/02   04/25/02    ConTech Building Systems            
                                                            CT-8            5,958                  03/28/02   04/26/02    ConTech Building Systems            
                                                            CT-9            7,909                  05/24/02   06/04/02    ConTech Building Systems            
                                                            CT-9           25,586                  07/16/02   07/24/02    ConTEch Building Systems            
                                                            SL-1            2,718                  01/28/02   03/06/02    S&L Elec.                           
                                                            SL-2          105,560                  03/11/02   06/17/03    S&L Elec.                           
                                                            SL-3            3,440                  06/03/02   06/05/02    S&L Elec.                           
                                                            SL-3          247,055         247,055  10/18/00   12/01/03    S&L Elec.                           
                                                            SL-4           27,582                  06/16/03   06/17/03    S&L Elec.                           
                                                            SL-5            5,622                  02/12/03   02/19/03    S&L Elec.                           
 
05-0866   Additions and Alterations    0-015-005  03/16/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-012          12,182                  03/07/08   08/18/08    Bette & Cring, LLC.                 
                                                            2-004          22,584                  08/21/07   08/07/08    M&N Plumbing and Heating            
                                                            5 - 007         8,676                  10/09/07   01/14/08    WISINSKI EXCAVATING                 
                                                            5-001          19,493                  09/18/06   12/19/06    Cory Wisinski Excavating            
                                                            5-003          14,872                  11/17/06   01/09/07    Cory Wisinski Excavating            
 
08-1327   Reconstruction               0-015-007  09/04/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-03            6,693                  09/14/10   09/29/10    BETTE & CRING LLC                   
                                                            1-09              790                  11/16/10   11/17/10    BETTE & CRING                       
                                                            1-12                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-14                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-17                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-18                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-19           10,819                  06/13/11   07/15/11    BETTE & CRING                       
                                                            1-20           10,819                  06/13/11   07/15/11    BETTE & CRING                       
                                                            1-21                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            2-01           31,586                  07/06/10   08/20/10    BURNS BROTHERS CONTRACTORS          
                                                            2-02           19,482                  07/15/10   09/03/10    BURNS BROTHERS CONTRACTORS          
                                                            2-03            8,150                  07/11/11   07/28/11    BURNS BROTHERS CONTRACTORS          
                                                            2-04           23,628                  11/07/11   01/24/12    BURNS BROTHERS CONTRACTORS          
                                                            2-05             -688                  11/04/11   01/11/12    BURNS BROTHERS CONTRACTORS          
                                                            3-01            3,665                  09/16/10   09/28/10    BROSH MECHANICAL INC                
                                                            3-05            8,140                  02/17/11   03/09/11    BROSH MECHANICAL INC                
                                                            4-01            9,775                  09/03/10   09/24/10    COLLINS-HAMMOND ELECTRICAL CONTR.   
                                                            4-04           18,286                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-05              465                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-06            1,538                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-08            7,764                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-09            2,620                  03/22/11   04/08/11    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            4-10          -23,591                  02/15/12   07/20/12    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            4-11            1,625                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-12            9,844                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            5-001         -35,000                  12/07/10   12/28/10    PTL CONTRACTING                     
 
08-1431   Reconstruction               0-015-008  04/30/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            11A-01        -22,536                  09/07/10   09/22/10    RSI ROOFING                         
                                                            11A-02        -22,186                  10/22/10   11/23/10    RSI ROOFING                         
 
11-0840   Reconstruction               0-015-009  06/15/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -10,109                  05/14/13   07/26/13    BETTE & CRING                       
                                                            1-02            7,980                  05/23/13   06/28/13    Bette & Cring                       
                                                            1-04            4,601                  08/13/13   11/25/13    Bette & Cring                       
                                                            1-05           20,135                  08/13/13   11/25/13    Bette & Cring                       
                                                            1-06           -2,225                  09/05/13   09/13/13    Bette & Cring                       
                                                            1-10            3,167                  10/08/13   12/09/13    BETTE & CRING                       
                                                            1-11            1,288                  12/18/13   06/27/14    Bette & Cring                       
                                                            1-12          -19,730                  05/02/14   05/21/14    Bette & Cring                       
                                                            100-02              0                  05/02/14   05/21/14    Bette & Cring, LLC                  
                                                            100-03              0                  05/02/14   05/21/14    Bette & Cring, LLC                  
                                                            3-01             -721                  08/20/13   03/07/14    Dow Electric                        
                                                            3-04          -11,238                  02/20/14   03/13/14    Dow Electric                        
                                                            300-02              0                  02/20/14   03/13/14    Dow Electric                        
 
14-0984   Reconstruction               0-015-010  02/04/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            100-01         -2,862                  03/27/17   07/14/17    Eagle Associates of Cazenovia       
                                                            100-01              0                  05/02/19   05/02/19    EAGLE ASSOCIATES OF CAZENOVIA       
                                                            100-04         -1,250                  03/27/17   07/14/17    Eagle Associates of Cazenovia       
                                                            400-01              0                  05/02/19   05/02/19    BLACK RIVER PLUMBING,HEATING & AC   
                                                            400-02              0                  05/02/19   05/02/19    BLACK RIVER PLUMBING,HEATING & AC   
                                                            400-03              0                  05/02/19   05/02/19    BLACK RIVER PLUMBING,HEATING & AC   
                                                            400-04              0                  05/02/19   05/02/19    BLACK RIVER PLUMBING, HEATING & AC  
                                                            500-01        -16,731                  08/08/18   12/31/18    BETTE & CRINGE, LLC                 
                                                            500-02              0                  08/08/18   01/02/19    BETTE & CRINGE, LLC                 
                                                            500-03              0                  08/29/17   10/13/17    Bette & Cringe, LLC                 
                                                            500-03              0                  05/02/19   05/02/19    BETTE & CRINGE,LLC                  
                                                            600-01              0                  09/12/17   09/14/17    Burns Brothers Contractors, Inc.    
 
15-0121   Reconstruction               0-015-011  05/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            10-01          -4,500                  01/04/18   03/27/18    COMALLI TECH SYSTEMS                
                                                            10-08             430                  03/09/18   05/21/18    Comalli Tech Systems                
                                                            10-11         -11,742                  07/26/18   07/31/18    COMALLI TECH SYSTEMS                
                                                            1000-001            0                  11/01/17   11/16/17    Comalli Technology Systems          
                                                            1000-001            0                  05/02/19   05/02/19    COMALLI TECHNOLOGY SYSTEMS          
                                                            4-01              750                  08/18/17   10/04/17    Black River Plumbing, Heating and AC
                                                            4-02             -810                  08/18/17   10/04/17    Black River Plumbing, Heating and AC
                                                            4-03           18,273                  11/15/17   06/05/18    Black River Plumbing, Heating and AC
                                                            4-04          -39,300                  03/06/18   05/21/18    Black River Plumbing, Htg & AC      
                                                            4-05          -14,055                  03/06/18   05/21/18    Black River Plumbing, Htg & AC      
                                                            4-06                0                  02/20/18   04/18/18    Black River Plumb/Heat/AC           
                                                            4-07            3,220                  03/27/18   05/31/18    Black River Plumbing, Htg & AC      
                                                            400-01              0                  08/18/17   10/04/17    Black River Plumbing, Heating & AC  
                                                            400-02              0                  08/18/17   10/04/17    Black River Plumbing, Heating & AC  
                                                            400-03              0                  08/18/17   10/04/17    Black River Plumbing, Heating & AC  
                                                            400-04              0                  08/18/17   10/04/17    Black River Plumbing, Heating & AC  
                                                            400-05              0                  09/07/17   10/12/17    Black River Plumbing, Heating & AC  
                                                            400-06              0                  09/12/17   10/12/17    Black River Plumbing, Heating & AC  
                                                            400-07              0                  10/12/17   10/31/17    Black River Plumbing, Heating & AC  
                                                            400-08              0                  11/01/17   11/16/17    Black River Plumbing, Heating & AC  
                                                            400-09              0                  11/01/17   11/16/17    Black River Plumbing, Heating & AC  
                                                            400-10         -9,961                  08/08/18   08/28/18    BLACK RIVER PLUMBING HEATING & AC   
                                                            5-02            1,150                  08/29/17   09/14/17    Bette & Cring, LLC                  
                                                            5-04           19,302                  10/03/17   10/13/17    Bette & Cring, LLC                  
                                                            5-08            8,592                  10/17/17   11/10/17    Bette & Cring, LLC                  
                                                            5-09            7,140                  10/17/17   11/10/17    Bette & Cring, LLC                  
                                                            5-11            2,472                  02/20/18   02/28/18    Bette & Cring, LLC                  
                                                            5-12            2,625                  07/16/18   07/31/18    BETTE & CRING LLC                   
                                                            6-01           13,500                  11/17/17   06/05/18    Burns Bros. Contractors, Inc.       
                                                            6-02           19,970                  06/22/18   07/26/18    BURNS BROS CONTRACTORS INC          
                                                            6-03            1,215                  11/27/18   01/02/19    Burns Bros. Contractors, INC.       
                                                            7-01            2,970                  08/08/18   01/02/19    BURNS BROS. CONTRACTORS, INC.       
                                                            7-02           43,261                  06/12/18   07/26/18    BURNS BROS CONTRACTORS INC          
                                                            7-03           30,424                  07/03/18   07/26/18    BURNS BROS CONTRACTORS INC          
                                                            7-04            1,158                  11/06/18   01/02/19    BURNS. BROS. CONTRACTORS, INC.      
                                                            8-01            2,628                  11/17/17   06/05/18    Collins Hammond                     
                                                            8-04            1,459                  09/12/17   10/12/17    Collins-Hammond Electrical Contracto
                                                            8-10              640                  01/04/18   03/27/18    Collins-Hammond Electrical Contracto
                                                            8-14            2,841                  04/23/18   05/31/18    Collins-Hammond Electrical Cont.    
                                                            9-01            3,800                  09/12/17   09/14/17    PTL Contracting Corp.               
                                                            9-03            4,830                  04/06/18   04/18/18    PTL Contracting Corp.               
                                                            9-04          -15,000                  08/29/18   09/12/18    PTL CONTRACTING CORP                
                                                            900-001             0                  08/29/17   09/14/17    PTL Contracting Corp.               
                                                            900-001             0                  05/02/19   05/29/19    PTL CONTRACTING CORP.               
 
17-1965   Reconstruction               0-015-012  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01             -741                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-05           -1,675                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-06           21,454                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-07            6,145                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-09            2,576                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            1-10              862                  06/22/21   03/14/22    Continental Construction LLC        
                                                            100-01              0                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            100-02              0                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            2-01          -10,980                  02/09/21   03/31/21    BURNS BROTHERS CONTRACTORS          
                                                            200-01              0                  02/09/21   03/31/21    BURNS BROTHERS CONTRACTORS          
                                                            3-06              957                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
                                                            300-06              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
                                                            300-07              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
 
19-1273   Reconstruction               0-015-013  02/28/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  06/12/20   07/14/20    WHITTON CONSTRUCTION, LLC           
 
20-0193   Reconstruction               0-015-014  10/01/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            PC-01               0                  02/23/21   04/05/21    POWIS CONTRACTING, INC.             
 
21-1289   Reconstruction               0-015-015  08/22/22  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0735FP Reconstruction               0-015-FP1  12/24/02  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0881SC Visual Structural Inspection 0-015-SC1  11/21/07  NO CHANGE ORDERS ON ELECTRONIC FILE
08-1368SC Visual Structural Inspection 0-015-SC2  03/17/09  NO CHANGE ORDERS ON ELECTRONIC FILE
08-1701SC Visual Structural Inspection 0-015-SC3  06/18/09  NO CHANGE ORDERS ON ELECTRONIC FILE

          Ohio Street Elementary:
92-0770   Additions and Alterations    0-016-001  04/28/93  NO CHANGE ORDERS ON ELECTRONIC FILE
01-1372   Reconstruction               0-016-002  06/03/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1R              9,351                  02/11/04   03/03/04    Charles Garlock and Sons            
 
06-1250   Reconstruction               0-016-004  06/29/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001           7,882                  02/11/08   02/23/08    bette & cring                       
 
08-1328   Additions and Alterations    0-016-005  09/04/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001               0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-003               0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-02           15,296                  06/03/11   07/15/11    BETTE & CRING                       
                                                            1-04                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-05            3,490                  10/20/10   11/05/10    BETTE & CRING                       
                                                            1-05                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-06            9,809                  11/16/10   11/17/10    BETTE & CRING                       
                                                            1-06                0                  10/31/11   01/24/12    BETTE & CRING, LLC                  
                                                            1-07                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-08                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-10            8,134                  11/29/10   12/22/10    BETTE & CRING                       
                                                            1-11            3,553                  11/29/10   02/09/11    BETTE & CRING                       
                                                            1-14            2,662                  12/24/10   02/09/11    BETTE & CRING                       
                                                            1-16           -4,200                  01/14/11   02/22/11    BETTE & CRING                       
                                                            1-16                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            1-19             -916                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            3-02              312                  11/23/10   12/08/10    BROSH MECHANICAL INC                
                                                            3-02             -532                  10/31/11   12/29/11    BROSH MECHANICAL INC                
                                                            3-03             -518                  10/31/11   12/29/11    BROSH MECHANICAL INC                
                                                            3-05           -6,967                  10/31/11   12/29/11    BROSH MECHANICAL INC                
                                                            3-06           -1,793                  10/31/11     /  /      BROSH MECHANICAL INC                
                                                            4-0001         -7,423                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-02          -18,633                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-03            1,281                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL\         
                                                            4-05            6,037                  09/03/10   09/24/10    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            4-08            1,423                  03/22/11   04/08/11    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            4-10            3,405                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
 
11-0841   Reconstruction               0-016-006  06/15/12  NO CHANGE ORDERS ON ELECTRONIC FILE
15-0122   Reconstruction               0-016-007  05/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            10-07           1,830                  03/09/18   05/21/18    Comalli Tech Systems                
                                                            1000-002            0                  08/08/18   01/03/19    COMALLI TECHNOLOGY SYSTEMS          
                                                            1000-002            0                  05/02/19   05/02/19    COMALLI TECHNOLOGY SYSTEMS          
                                                            5-07           14,245                  11/01/17   11/24/17    Bette & Cring LLC                   
 
17-1966   Reconstruction               0-016-008  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            3-01              708                  02/09/21   03/30/21    DOW ELECTRIC, INC.                  
                                                            300-01              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
 
02-0736FP Reconstruction               0-016-FP1  12/24/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Starbuck Elementary School:
90-1606   Reconstruction               0-017-002  06/24/91  NO CHANGE ORDERS ON ELECTRONIC FILE
07-0970   Reconstruction               0-017-003  05/20/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001          34,206                  09/05/08   05/12/09    BETTE & CRING                       
                                                            1-002          20,940                  09/05/08   05/12/09    BETTE & CRING                       
                                                            1-003           4,436                  10/09/08   03/13/09    BETTE & CRING                       
                                                            1-004          10,055                  11/25/08   06/16/09    BETTE & CRING                       
                                                            1-005          21,617                  05/03/10   05/26/10    BETTE & CRING                       
                                                            1-006          20,627                  03/09/09   06/02/09    BETTE & CRING                       
                                                            1-007           3,425                  03/18/09   07/03/09    BETTE & CRING                       
                                                            1-008           6,780                  10/28/09   12/30/09    BETTE & CRING                       
                                                            1-009          -6,050                  10/30/09   12/30/09    BETTE & CRING                       
                                                            2-001         -17,606                  06/12/09   07/29/09    EDWARD F. GALVIN                    
                                                            3-001         -10,334                  01/28/10   05/07/10    NORWOOD PLUMBING                    
                                                            4-001          26,161                  10/09/08     /  /      COLLINS - HAMMOND                   
                                                            4-001          26,161                  05/07/10   08/23/10    COLLINS-HAMMOND ELECTRICAL          
                                                            4-002          10,073                  10/20/08     /  /      COLLINS - HAMMOND                   
                                                            4-002          10,073                  05/07/10   08/23/10    COLLINS-HAMMOND ELECTRICAL          
                                                            4-003           7,971                  12/15/08   01/16/09    COLLINS-HAMMOND ELECTRICAL          
                                                            4-004         -14,253                  01/21/10   05/27/10    COLLINS-HAMMOND ELECTRICAL          
                                                            4-004         -14,253                  05/07/10   08/23/10    COLLINS-HAMMOND ELECTRICAL          
                                                            5-001         -27,732                  11/07/08   03/10/09    RSI ROOFING                         
                                                            6-001           3,884                  06/29/09   07/29/09    A.A.C. CONTRACTING INC.             
 
11-0842   Reconstruction               0-017-004  06/15/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            100-01              0                  10/26/13   12/06/13    Cunningham Excavation               
 
23-1051   Reconstruction               0-017-005  12/21/23  NO CHANGE ORDERS ON ELECTRONIC FILE

          Wiley Intermediate School:
91-0509   Reconstruction               0-021-004  12/26/91  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0100   Reconstruction               0-021-007  12/23/99  NO CHANGE ORDERS ON ELECTRONIC FILE
05-0867   Reconstruction               0-021-008  03/16/06  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            #5 - SIT            0                  10/26/07     /  /      QISINSKI EXCAVATING                 
                                                            1 - 008         3,105                  10/09/07   01/14/08    BETTE & CRING, LLC.                 
                                                            1-005          11,909                  07/11/07   08/07/07    Bette Cring                         
                                                            1-006          22,829           6,844  08/21/07   08/23/07    BETTE & CRING, LLC                  
                                                            1-007           8,051                  08/21/07   08/23/07    BETTE & CRING, LLC                  
                                                            1-009          17,500                  12/24/07   04/04/08    BETTE & CRING, LLC                  
                                                            1-011          15,741                  03/07/08   08/18/08    Bette & Cring, LLC.                 
                                                            1-013          11,020                  03/07/08   08/18/08    Bette & Cring, LLC                  
                                                            1-014          16,530                  04/04/08   02/06/09    BETTE & CRING, LLC                  
                                                            1-016          14,411                  07/16/08   09/29/08    BETTE & CRING, LLC                  
                                                            2-002          18,810                  05/03/07   08/20/07    M and N Plumbing                    
                                                            2-003           6,312                  02/09/09   06/08/09    M&N PLUMBING AND HEATING, INC.      
                                                            2-005          38,452                  04/25/08   02/18/09    M&N PLUMBING AND HEATING, INC.      
                                                            3 - 001        24,031                  08/21/07   04/03/08    NORWOOD PLUMBING                    
                                                            3-002           8,400                  01/16/08   08/05/08    Norwood Plumbing                    
                                                            3-003           6,173                  02/12/09   07/07/09    NORWWOOD PLUMBING, INC.             
                                                            4-001           5,700                  08/21/07   01/16/08    COLLINS - HAMMOND ELECTRICAL        
                                                            4-002           1,667                  08/07/07   10/18/07    Collins Hammond Electrical          
                                                            4-003           2,545                  09/13/07   01/15/08    COLLINS - HAMMOND ELECTRICAL        
                                                            4-004           5,480                  10/09/07   01/16/08    COLLINS - HAMMOND ELECTRICAL        
                                                            4-005           2,460                  11/13/07   01/16/08    Collins-Hammond Electrical          
                                                            4-007           1,278                  05/13/08   08/12/08    COLLINS - HAMMOND ELECTRICAL        
                                                            5 - 008        19,937                  10/09/07   01/14/08    WISINSKI EXCAVATING                 
                                                            5-005           1,426                  12/08/06   01/19/07    Cory Wisinski                       
                                                            5-009          26,938                  10/26/07   01/14/08    Wisinski Excavating                 
                                                            6-002           2,188                  08/21/07   08/23/07    RSI ROOFING                         
 
06-1462   Reconstruction               0-021-009  09/12/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001          18,412                  06/29/08   09/29/08    ConTech Building Systems            
                                                            1-002             664                  09/09/08   09/29/08    ConTech Building Systems            
                                                            1-003           1,570                  10/31/08   05/21/09    CONTECH BUILDING SYSTEMS            
                                                            1-004           9,567                  12/15/08   01/22/09    CONTECH BUILDING SYSTEMS            
                                                            2-001          -5,000                  10/07/10   10/25/10    EMPIRE NORTHEAST                    
                                                            3-005          -5,000                  02/26/10   08/22/11    NORWOOD PLUMBING INC                
 
08-1329   Reconstruction               0-021-010  09/04/09  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-12           13,255                  11/29/10   12/22/10    BETTE & CRING                       
                                                            1-13           20,388                  11/29/10   12/22/10    BETTE & CRING                       
                                                            1-15           -1,825                  01/14/11   02/22/11    BETTE & CRING                       
                                                            1-17            5,557                  02/14/11   03/29/11    BETTE & CRING                       
                                                            1-18              630                  03/29/11   04/22/11    BETTE & CRING                       
                                                            1-23                0                  10/31/11   01/24/12    BETTE & CRING LLC                   
                                                            4-02            8,912                  09/03/10   09/24/10    COLLINS-HAMMOND ELECTRICAL CONT.    
                                                            4-07            2,600                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
                                                            4-09              655                  03/01/12   08/29/12    COLLINS-HAMMOND ELECTRICAL          
 
11-0843   Reconstruction               0-021-011  06/15/12  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01              -58                  10/28/13   01/21/14    Cunningham Excavation               
                                                            100-01              0                  05/02/14   05/21/14    Bette & Cring, LLC                  
                                                            300-01              0                  02/20/14   03/13/14    Dow Electric                        
 
15-0123   Reconstruction               0-021-012  05/27/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            10-05           1,620                  03/09/18   05/21/18    Comalli Tech Systems                
                                                            5-05            1,380                  09/19/17   10/18/17    Bette & Cring, LLC                  
                                                            5-06           19,976                  10/03/17   10/13/17    Bette & Cring, LLC                  
                                                            8-02              469                  11/17/17   06/05/18    Collins-Hammond Electrical Contracto
                                                            8-03           17,940                  10/30/17   06/18/19    Collins-Hammond Electrical Contracto
                                                            8-05           16,532                  10/20/17   06/19/19    Collins-Hammond Electrical Contracto
                                                            8-09            4,649                  11/06/17   06/19/19    Collins-Hammond Electrical Contracto
                                                            8-11            4,368                  01/04/18   03/27/18    COLLINS-HAMMOND ELECTRICAL          
                                                            800-002             0                  08/08/18   01/03/19    COLLINS-HAMMOND ELECTRICAL CONTRACTO
 
17-1967   Reconstruction               0-021-013  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-04           -1,277                  02/09/21   04/14/21    CONTINENTAL CONSTRUCTION, LLC       
                                                            3-05              427                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
                                                            300-05              0                  02/09/21   03/31/21    DOW ELECTRIC, INC.                  
 
21-1290   Reconstruction               0-021-014  08/22/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01               0                  09/11/23   12/22/23    BETTE & CRING LLC                   
                                                            GC-02               0                  09/11/23   12/18/23    BETTE & CRING LLC                   
                                                            MC-01               0                  08/21/23   01/09/24    CROSBY-BROWNLIE                     
 
02-0737FP Reconstruction               0-021-FP1  12/24/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Case Middle School:
99-0099   New Construction             0-023-001  12/23/99  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            34C-2          -1,279                  10/23/01   01/08/02    34 & Company                        
                                                            AR-18           4,235                  08/22/01   01/08/02    AR Mack Const.                      
                                                            AR-21          10,681                  10/25/01   01/08/02    AR Mack Const.                      
                                                            AR-22          16,574                  01/30/02   03/27/02    AR Mack Const.                      
                                                            AR-23           2,672                  09/23/02   10/28/02    AR Mack Const.                      
                                                            AR-24          10,512                  09/23/02   10/28/02    AR Mack Const.                      
                                                            AR-25           4,167                  02/12/03   02/20/03    AR Mack Const.                      
                                                            AR-26           2,763                  04/08/03   04/18/03    AR Mack Const.                      
                                                            MN-3            2,281                  01/10/02   03/18/02    M&N Plumbing                        
                                                            MN-4              824                  03/28/02   04/29/02    M&N Plumbing                        
                                                            SL-10           8,753                  08/14/02   10/28/02    S&L Elec.                           
                                                            SL-11           1,519                  12/11/02   01/10/03    S&L Elec.                           
                                                            SL-12           2,061                  12/11/02   01/10/03    S&L Elec.                           
                                                            SL-13           3,125                  12/11/02   01/10/03    S&L Elec.                           
                                                            SL-14            -192                  03/04/03   03/13/03    S&L Elec.                           
                                                            SL-3          247,055                  06/16/03   08/26/03    S&L Elec.                           
                                                            SL-7            4,375                  12/18/01   02/28/02    S&L Elec.                           
                                                            SL-8            5,502                  01/28/02   03/18/02    S&L Elec.                           
                                                            SL-9            3,820                  03/13/02   04/29/02    S&L Elec.                           
 
16-0987   Reconstruction               0-023-003  09/25/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            12-001              0                  05/02/19   05/03/19    RSI INC.                            
                                                            12-002              0                  05/02/19   05/03/19    RSI INC.                            
                                                            12-01          -8,480                  11/06/18   01/24/19    RSI ROOFING INC.                    
                                                            12-02         -33,196                  01/15/19   03/12/19    RSI ROOFING INC                     
                                                            13-001              0                  05/02/19   06/05/19    LAWMAN HEATING AND COOLING, INC.    
                                                            13-002              0                  05/02/19   06/05/19    LAWMAN HEATING AND COOLING, INC.    
                                                            13-003              0                  05/02/19   06/10/19    LAWMAN HEATING AND COOLING, INC.    
                                                            13-004              0                  05/02/19   06/05/19    LAWMAN HEATING AND COOLING, INC.    
                                                            13-01           5,335                  05/10/18   06/04/18    Lawman Heating & Cooling, Inc.      
                                                            13-02          17,272                  03/13/19   06/06/19    LAWMAN HEATING & COOLING, INC.      
                                                            13-03          -8,715                  05/22/19   06/05/19    LAWMAN HEATING & COOLING, INC.      
 
21-0073   Reconstruction               0-023-004  08/02/21  NO CHANGE ORDERS ON ELECTRONIC FILE
21-0112   Reconstruction               0-023-006  08/02/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            MC-01          -4,000                  01/21/22   05/04/23    Burns Bros Contrs LLC               
 
21-1291   Reconstruction               0-023-007  08/22/22  NO CHANGE ORDERS ON ELECTRONIC FILE
02-0738FP Reconstruction               0-023-FP1  12/24/02  NO CHANGE ORDERS ON ELECTRONIC FILE

          Administration Building:
91-1084   Reconstruction               1-001-001  04/30/92  NO CHANGE ORDERS ON ELECTRONIC FILE
10-0346   Reconstruction               1-001-002  10/12/10  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           24,683                  04/13/11   06/20/11    EMPIRE DISMANTLEMENT CORP           
                                                            1-02           35,381                  04/13/11   06/20/11    EMPIRE DISMANTLEMENT CORP           
                                                            1-03           26,200                  05/05/11   05/25/11    EMPIRE DISMANTLEMENT CORP           
                                                            1-04           41,889                  06/13/11   06/24/11    EMPIRE DISMANTLEMENT CORP           
                                                            1-05           43,660                  08/08/11   09/08/11    EMPIRE DISMANTLEMENT CORP           
 

          Storage Bldg. #1 @ HS:
99-0102   Additions and Alterations    2-014-002  12/23/99  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Bldg. #3:
14-0985   New Construction             2-026-001  02/04/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            100-02         -5,046                  03/27/17   07/14/17    Eagle Associates of Cazenovia       
                                                            100-02              0                  05/02/19   05/02/19    Eagle Associates of Cazenovia       
                                                            2-01           -3,200                  02/09/17   02/15/17    Lawman Heating & Cooling, Inc.      
                                                            3-02           15,617                  08/10/16   09/30/16    Northern Pioneer                    
                                                            3-03               95                  03/24/17   03/30/17    Northern Pioneer                    
                                                            300-01           -983                  03/27/17   06/20/19    Northern Pioneer                    
                                                            300-01              0                  05/02/19   05/02/19    NORTHERN PIONEER                    
 

          Field House:
03-0512   Reconstruction               7-004-001  06/02/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-001          -1,613                  12/14/04   12/30/04    Con-Tech Building Systems           
 
14-0986   Reconstruction               7-004-003  02/04/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           14,066                  08/10/16   09/30/16    Eagle Associates of Cazenovia       
 

          Press Box:
14-0987   New Construction             7-027-001  02/04/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-02           -1,672                  08/26/16   11/21/16    Eagle Associates of Cazenovia       
                                                            1-03           -6,361                  03/24/17   07/14/17    Eagle Associates of Casenovia       
                                                            100-02         -6,481                  03/27/17   07/14/17    Eagle Associates of Cazenovia       
                                                            100-03              0                  05/02/19   05/02/19    EAGLES ASSOCIATES OF CAZENOVIA      
                                                            100-04              0                  05/02/19   05/02/19    EAGLE ASSOCIATES OF CAZENOVIA       
                                                            3-01            1,723                  06/29/16   07/29/16    Northern Pioneer                    
 

          District-Wide:
18-0343   Reconstruction               7-999-002  04/23/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            7-02          -34,862                  10/11/22   05/18/23    Watson Elec Inc                     
 

CARTHAGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-22-01-06
last updated on 01/10/24

REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          High School:
94-0596   Additions and Alterations    0-001-002  02/14/95  NO CHANGE ORDERS ON ELECTRONIC FILE
93-1724   Reconstruction               0-001-003  08/05/94  NO CHANGE ORDERS ON ELECTRONIC FILE
94-0516   Reconstruction               0-001-004  01/25/95  NO CHANGE ORDERS ON ELECTRONIC FILE
95-0744   Reconstruction               0-001-005  03/11/96  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
 
99-0481   Additions and Alterations    0-001-006  12/27/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            11-02          -8,445                  07/14/04   07/15/04    Agway Energy Products               
                                                            A9-02         -17,000                  04/18/03   05/02/03    Western NY Flooring                 
                                                            COMM-01         1,275                  05/14/03   05/27/03    Gaffney Communications              
                                                            COMM-02         2,665                  05/14/03   05/27/03    Gaffney Communications              
                                                            COMM-03         4,648                  12/08/04   12/28/04    Gaffney Communication               
                                                            HS1-01         11,876                  05/14/03   05/27/03    Avala Contracting                   
                                                            HS1-02            706                  05/14/03   05/27/03    Avala Contracting                   
                                                            HS1-03            450                  05/14/03   03/01/04    Avala Contracting                   
                                                            HS1-04R         1,589                  05/14/03   05/27/03    Avala Contracting                   
                                                            HS1-05         -2,178                  05/14/03   05/27/03    Avala Contracting                   
                                                            HS10-01        15,997                  05/14/03   05/27/03    Brosh Mechanical                    
                                                            HS10-02        10,876                  05/14/03   05/27/03    Brosh Mechanical                    
                                                            HS10-03        11,848                  05/14/03   05/27/03    Brosh Mechanical                    
                                                            HS10-04        10,303                  05/14/03   05/27/03    Brosh Mechanical                    
                                                            HS12-01         3,640                  05/14/03   05/27/03    Watson Electric                     
                                                            HS2-01        -26,647                  05/14/03   05/27/03    Ballard Const.                      
                                                            HS3-01        -15,318                  05/14/03   05/27/03    AR Mack Const.                      
                                                            HS3-02        -62,719                  05/14/03   05/27/03    AR Mack Const.                      
                                                            HS3-03         -4,000                  12/19/03   12/29/03    AR Mack Const.                      
                                                            HS4-01         -2,960                  11/05/03   11/12/03    Paragon Glass                       
                                                            HS5-01         17,698                  05/14/03   05/27/03    Bette & Cring                       
                                                            HS5-02          4,623                  05/14/03   07/03/03    Bette & Cring                       
                                                            HS6-01          8,639                  05/14/03   05/27/03    Belott Carpet Interiors             
                                                            HS6-02        -15,085                  05/14/03   05/27/03    RLI Surety Divison                  
                                                            HS7-01         -8,250                  09/24/03   10/03/03    Dick Tile Marble Co.                
                                                            HS8-01         -8,788                  05/14/03   05/27/03    Buffalo Hotel Supply Company        
                                                            HS9-01         -1,200                  05/14/03   05/27/03    Nickerson Corp                      
                                                            HS9-02         15,743                  05/14/03   05/27/03    Nickerson Corp.                     
                                                            HSFUR-01         -804                  05/14/03   05/27/03    Roberts Office Interiors            
 
99-1248   Reconstruction               0-001-007  03/26/01  NO CHANGE ORDERS ON ELECTRONIC FILE
01-1181   Reconstruction               0-001-008  06/14/02  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              -5,000                  01/21/03   02/05/03    MEC Elec.                           
                                                            1              23,996                  01/16/03   02/11/03    Paragon Environ.                    
                                                            1                -736                  02/24/03   03/11/03    R&S Associates                      
                                                            1              -7,200                  06/19/03   06/20/03    Facilities Equip.                   
                                                            1              -1,316                  08/28/03   09/22/03    Hyde Stone Mech.                    
 
03-1375   Reconstruction               0-001-009  05/02/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1A              3,585                  04/04/05   06/21/05    PTL Contracting Corp                
                                                            1C             -5,335                  04/04/05   06/21/05    PTL Contracting                     
 
04-0378   Reconstruction               0-001-010  01/14/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            01-01         -12,715                  12/09/05   06/26/06    Midlanti Environmental              
                                                            01-03           1,000                  10/12/06   12/18/06    Midlantic Environmental             
                                                            01-03           1,000                  04/17/07   05/15/07    Midlantic Environmental             
                                                            02A-01         -3,182                  04/17/07   05/15/07    PTL Contracting Corp                
                                                            05-01          -7,921                  09/14/06   10/27/06    Empire Northeast                    
                                                            06-01         -19,000                  09/14/06   10/27/06    M and Plumbing Heating              
                                                            07-01           1,152                  12/20/05     /  /      MEC Electric                        
                                                            07-02             393                  04/11/06   05/26/06    Mec Electric                        
 
06-0571   Additions and Alterations    0-001-011  03/09/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            CO 01-01       -5,000                  04/18/11   05/19/11    MIDLANTIC ENVIRONMENTAL INC         
                                                            CO 01-02       18,433                  04/18/11   05/19/11    MIDLANTIC ENVIRONMENTAL INC         
                                                            CO 01-03        2,400                  04/18/11   05/19/11    MIDLANTIC ENVIRONMENTAL INC         
                                                            CO 02-01      150,000                  03/06/08   03/19/08    Cory Wisinski Excavating            
                                                            CO 03-03       19,000                  03/06/08   03/19/08    Bette & Cring LLC                   
                                                            CO 03-04       60,231                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 03-06       10,977                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 03-07        3,650                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 03-08        9,213                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 03-09        3,697                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 03-10       16,690                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 03-11          675                  04/18/11   05/19/11    BETTE & CRING LLC                   
                                                            CO 04-02       -5,975                  04/18/11   05/19/11    PTL CONTRACTING CORPORATION         
                                                            CO 07-03      -25,061                  04/18/11   05/19/11    EMPIRE NORTHEAST INC                
                                                            CO 08-01       33,000                  03/06/08   08/12/08    Watson Electric, Incorp.            
                                                            CO 08-06       -6,143                  04/18/11     /  /      WATSON ELECTRIC INC                 
                                                            CO 08-07       17,499                  04/18/11   05/19/11    WATSON ELECTRIC INC                 
                                                            CO 09-02       12,425                  04/18/11   05/19/11    M&N PLUMBING & HEATING INC          
 
13-0284   Reconstruction               0-001-014  08/01/13  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            001            43,173                  01/30/14   07/24/14    Bette & Cring, LLC                  
                                                            002               649                  01/30/14   07/24/14    Bette & Cring, LLC                  
                                                            003           -10,000                  05/16/14   06/03/14    Bette & Cring, LLC                  
 
15-0463   Reconstruction               0-001-015  05/20/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-02          -1,022                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-03           2,126                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-05             629                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-07           2,697                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-14           1,068                  04/23/18   05/31/18    Dow Electric                        
                                                            EC-16           5,625                  02/04/21   03/26/21    DOW ELECTRIC                        
                                                            GC-05           4,803                  06/28/17   10/30/17    Bette & Cring, LLC                  
                                                            GC-09         -23,305                  07/12/17   07/27/17    Bette & Cring, LLC                  
                                                            GC-10          -2,481                  07/12/17   07/27/17    Bette & Cring, LLC                  
                                                            GC-15           4,597                  11/01/17   11/16/17    Bette & Cring, LLC                  
                                                            GC-21          -9,145                  11/24/17   12/19/17    Bette & Cring, LLC                  
                                                            GC-22           1,937                  11/24/17   12/19/17    Bette & Cring, LLC                  
                                                            GC-24           3,480                  01/23/18   02/05/18    Bette & Cring, LLC                  
                                                            GC-26           1,602                  01/23/18   02/05/18    Bette & Cring, LLC                  
                                                            GC-27          33,986                  02/06/18   02/21/18    Bette & Cring, LLC                  
                                                            GC-28          33,184                  02/06/18   02/21/18    Bette & Cring, LLC                  
                                                            GC-31           6,277                  05/09/18   06/04/18    Bette & Cring LLC                   
                                                            GC-33          -2,500                  10/05/18   11/13/18    BETTE & CRING LLC                   
                                                            HVAC-05        27,500                  10/29/19   10/31/19    BURNS BROS CONTRACTORS, INC.        
                                                            HVAC-06        -5,466                  02/17/21   04/09/21    BURNS BROS. CONTRACTORS, INC.       
                                                            MC-01           3,450                  12/06/17   06/05/18    Burns Bros Contractors, Inc.        
                                                            MC-02           1,925                  12/06/17   06/05/18    Burns Bros Contractors, Inc.        
                                                            MC-03          21,615                  12/06/17   06/05/18    Burns Bros Contractors, Inc.        
                                                            MC-04          29,719                  04/11/19   04/12/19    BURNS BROS CONTRACTORS, INC.        
                                                            PC-01         -19,702                  12/20/18   02/12/19    j.E. SHEEHAN CONTRACTING CORP.      
                                                            SC2-01         12,800                  08/23/17   09/07/17    JL Excavation LLC                   
                                                            SC2-02         14,125                  09/27/17   10/10/17    JL Excavation LLC                   
 
16-0753   Reconstruction               0-001-016  01/12/17  NO CHANGE ORDERS ON ELECTRONIC FILE
16-1766   Reconstruction               0-001-017  05/26/17  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01            8,487                  02/27/18   03/07/18    Bette And Cring LLC                 
 
20-0974   Additions and Alterations    0-001-019  04/06/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01               0                  08/09/21   04/21/22    S&L ELECTRIC INC.                   
                                                            EC-03         -12,410                  10/29/21   12/08/22    S&L Electric Inc                    
                                                            EC-06          -8,213                  12/29/21   10/18/22    S&L Elec Inc                        
                                                            EC-07          -6,598                  12/29/21   10/18/22    S&L Elec Inc                        
                                                            GC-14          27,990                  07/22/22   05/10/23    Bette&Cring LLC                     
                                                            GC-20          14,209                  10/28/22   12/12/23    Bette&Cring LLC                     
                                                            GC-33             708                  08/23/23     /  /      BETTE & CRING                       
                                                            PC-02          90,000                  09/13/22   10/31/23    Burns Bros Contrs                   
                                                            PC-04          25,020                  07/13/23   12/28/23    BURNS BROS CONTRACTORS              
                                                            PC-06           1,585                  08/23/23     /  /      BURNS BROS CONTRACTING              
                                                            gc-07         -50,453                  01/10/22   03/03/23    Bette&Cring LLC                     
 
19-0931   Reconstruction               0-001-020  04/13/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                                                0                    /  /       /  /                                          
                                                            AAEC-02             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-10             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-10             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAGC-09             0                  01/20/22   11/03/22    DC Bldg Systems                     
                                                            DC-02           6,198                  06/04/21   03/24/22    CoreBTS                             
                                                            DC-03           9,179                  06/04/21   03/24/22    CoreBTS                             
                                                            EC-02           3,238                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            TC-01           8,439                  08/20/21   04/26/22    IK SYSTEMS                          
                                                            TC-02           1,396                  12/22/21   01/10/23    IK SYSTEMS                          
 
20-1681   Reconstruction               0-001-021  07/03/21  NO CHANGE ORDERS ON ELECTRONIC FILE
20-1682   Reconstruction               0-001-022  05/14/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            SC-01R          7,246                  01/24/22   01/25/23    AstroTurf Corp                      
 
21-1895   Reconstruction               0-001-023  06/15/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -5,000                  07/05/23   01/02/24    BURNS BROS                          
 
22-1185   Reconstruction               0-001-024  03/28/23  NO CHANGE ORDERS ON ELECTRONIC FILE
94-0515EP Energy Project               0-001-E01  01/10/95  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1671FP Reconstruction               0-001-FP1  05/02/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Middle School:
94-0597   Additions and Alterations    0-002-001  02/14/95  NO CHANGE ORDERS ON ELECTRONIC FILE
04-0379   Reconstruction               0-002-004  01/14/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            07-02           4,083                  04/11/06   05/26/06    Mec Electric                        
 
12-1335   Reconstruction               0-002-006  06/19/13  NO CHANGE ORDERS ON ELECTRONIC FILE
15-0464   Reconstruction               0-002-007  05/20/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-10          -4,942                  11/24/17   06/01/18    Dow Electric                        
                                                            GC-001            947                  11/01/16     /  /      JL Excavation LLC                   
                                                            GC-006          1,200                  01/12/17   01/27/17    JL Excavation LLC                   
                                                            GC-02          -2,530                  06/12/17   06/19/17    Bette & Cring, LLC                  
                                                            GC-03          -2,530                  05/17/17   05/19/17    Bette & Cring, LLC                  
                                                            GC-29           3,396                  02/21/18   03/23/18    Bette & Cring, LLC                  
 
20-0975   Additions and Alterations    0-002-010  04/06/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-02               0                  08/09/21   04/21/22    S&L ELECTRIC INC                    
                                                            EC-08          -3,108                  12/29/21   10/18/22    S&L Elec Inc                        
                                                            GC-09           9,789                  03/02/22   02/23/23    Bette&Cring LLC                     
                                                            GC-19           6,802                  10/28/22   12/13/23    Bette & Cring LLC                   
                                                            PC-05           5,534                  08/23/23   12/18/23    BURNS BROS CONTRACTING              
 
19-0932   Reconstruction               0-002-011  04/13/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AADC-03             0                  01/20/22   11/08/22    CoreBTS                             
                                                            AAEC-01             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-03             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-15             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAGC-08             0                  01/20/22   11/03/22    DC Bldg Systems                     
                                                            DC-01             568                  06/04/21   03/24/22    CoreBTS                             
                                                            EC-08            -140                  01/10/22   11/08/22    Dow Elec                            
 
22-1912   Reconstruction               0-002-012  05/25/23  NO CHANGE ORDERS ON ELECTRONIC FILE
02-1672FP Reconstruction               0-002-FP1  05/02/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          Black River Elementary:
99-0482   Reconstruction               0-003-003  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            A1-01           9,400                  04/18/03   05/02/03    Clean Air Technology                
                                                            A15-01          1,051                  04/18/03   05/02/03    Brosh Mech.                         
                                                            A3-01           6,500                  04/18/03   05/02/03    Purcell Const.                      
                                                            A7-01           4,135                  04/18/03   05/02/03    Enjem's  Inc                        
 
99-1249   Reconstruction               0-003-004  03/26/01  NO CHANGE ORDERS ON ELECTRONIC FILE
03-1376   Reconstruction               0-003-005  05/02/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            00002          -9,469           3,300  03/28/06   10/13/06    PTl Contracting Corp                
                                                            1B             -8,723                  04/04/05   06/21/05    PTL Contracting Corp                
 
04-0380   Reconstruction               0-003-006  01/14/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1A-01          -6,345                  04/12/07   05/15/07    Richard ALexander                   
 
15-0465   Reconstruction               0-003-007  05/20/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-08             376                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-13           3,211                  12/06/17   06/05/18    Dow Electric                        
                                                            EC-15          13,479                  09/26/18   10/22/18    DOW ELECTRIC                        
                                                            GC-03             560                  11/01/16     /  /      JL Excavation LLC                   
                                                            GC-17          12,277                  11/03/17   11/24/17    Bette & Cring, LLC                  
                                                            GC-18          10,184                  11/03/17   11/24/17    Bette & Cring, LLC                  
                                                            GC-19          12,845                  11/15/17   12/04/17    Bette & Cring, LLC                  
                                                            GC-20             637                  11/24/17   12/19/17    Bette & Cring, LLC                  
                                                            GC-25           2,207                  01/23/18   02/05/18    Bette & Cring, LLC                  
                                                            GC-30            -275                  02/22/18   03/23/18    Bette & Cring, LLC                  
                                                            GC-34          -2,500                  09/26/18   11/13/18    BETTE & CRING LLC                   
 
17-1729   Reconstruction               0-003-009  06/15/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001         13,500                  03/14/19   03/15/19    HERTIAGE MASONRY RESTORATION, INC.  
 
21-0167   Reconstruction               0-003-010  01/06/22  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            MC-01          -3,028                  07/18/23   12/28/23    LAWMAN HEATING & COOLING            
 
20-0047   Reconstruction               0-003-011  08/14/20  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXWest Carthage Elem- sold 2006:
92-1452   Reconstruction               0-004-003  06/25/93  NO CHANGE ORDERS ON ELECTRONIC FILE
15-0466   Reconstruction               0-004-004  05/20/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-01          -2,530                  06/12/17   06/19/17    Bette & Cring, LLC                  
                                                            GC-02          -2,530                  05/17/17   05/19/17    Bette & Cring, LLC                  
                                                            GC-04           3,240                  12/08/16   12/27/16    JL Excavation LLC                   
                                                            GC-11           4,135                  09/08/17   10/10/17    Bette & Cring, LLC                  
                                                            GC-32         -26,674                  09/26/18   11/13/18    BETTE & CRING LLC                   
 
18-0772   Reconstruction               0-004-006  03/20/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-001        -10,000                  01/09/20   01/28/20    AMP ELECTRIC R.S.,LLC               
                                                            GC-001          1,967                  01/29/20   02/26/20    NORTHERN TIER CONTRACTING, INC.     
                                                            GC-002          4,659                  01/29/20   02/26/20    NORTHERN TIER CONTRACTING, INC.     
                                                            GC-003           -740                  01/29/20   02/26/20    NORTHERN TIER CONTRACTING, INC.     
                                                            MC-001        -10,000                  02/25/20   06/24/20    ONTARIO HVAC SOLUTIONS, INC.        
 
02-1674FP Reconstruction               0-004-FP1  05/02/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          XXGreat Bend School (SOLD 2/23):
99-0483   Reconstruction               0-008-002  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            A1-03          -2,212                  04/18/03   05/02/03    Clean Air Technology                
                                                            A15-03          2,814                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A15-10          8,489                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A7-02             241                  04/18/03   05/02/03    Enjem's Inc                         
 
99-1250   Reconstruction               0-008-003  03/26/01  NO CHANGE ORDERS ON ELECTRONIC FILE
04-0381   Reconstruction               0-008-004  01/14/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            01-02          17,000                  10/12/06   12/18/06    Midlantic Environmental             
                                                            01-02          17,000                  04/17/07   05/15/07    Midalantic Environmental            
                                                            03A-01         -5,000                  04/17/07   05/15/07    PTL Contracting Corp                
 
05-0702   Reconstruction               0-008-005  05/23/06  NO CHANGE ORDERS ON ELECTRONIC FILE
07-2338   Reconstruction               0-008-006  09/18/08  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1              -4,041                  02/03/10   01/18/12    J.J. DOMAGALA ELECTRIC              
 

          Carthage Elementary:
93-0920   Reconstruction               0-012-002  04/26/94  NO CHANGE ORDERS ON ELECTRONIC FILE
99-0484   Additions and Alterations    0-012-003  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            A1-02          -1,008                  04/18/03   05/02/03    Clean Air Technology                
                                                            A1-04           7,008                  04/18/03   05/02/03    Clean Air Technology                
                                                            A13-02         10,699                  04/18/03   05/02/03    Tougher Industries                  
                                                            A14-03          4,216                  04/18/03   05/02/03    Watson Electric                     
                                                            A15-02          2,577                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A15-06            963                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A15-07          1,984                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A15-09         17,127                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A4-01           5,800                  04/18/03   05/02/03    PTl Contracting                     
                                                            A5-01          -7,413                  03/18/04   03/30/04    Northern Glass                      
                                                            A6-1          -55,571                  04/21/03   05/02/03    Henderson-Johnson Company           
                                                            A7-04            -429                  04/18/03   05/02/03    Enjem's Inc                         
                                                            A7-05            -907                  04/18/03   05/02/03    Enjem's Inc                         
                                                            A7-07         -10,522                  04/18/03   05/02/03    Enjem's Inc                         
                                                            A9-03            -116                  04/18/03   05/02/03    Western NY Floor                    
 
99-1251   Reconstruction               0-012-004  03/26/01  NO CHANGE ORDERS ON ELECTRONIC FILE
03-1377   Reconstruction               0-012-005  05/02/04  NO CHANGE ORDERS ON ELECTRONIC FILE
04-0382   Reconstruction               0-012-006  01/14/05  NO CHANGE ORDERS ON ELECTRONIC FILE
15-0467   Reconstruction               0-012-007  05/20/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            EC-01            -846                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-04           2,714                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-06           1,139                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-09           1,876                  01/31/18   04/12/18    Dow Electric                        
                                                            EC-11            -157                  11/24/17   06/01/18    Dow Electric                        
                                                            EC-12           1,505                  12/06/17   06/05/18    Dow Electric                        
                                                            GC-06           6,279                  06/28/17   07/05/17    Bette & Cring, LLC                  
                                                            GC-08          18,440                  07/12/17   07/27/17    Bette & Cring, LLC                  
                                                            GC-12          13,176                  09/08/17   10/10/17    Bette & Cring, LLC                  
                                                            GC-14              20                  11/01/17   11/16/17    Bette & Cring, LLC                  
                                                            GC-16         -62,607                  11/03/17   11/24/17    Bette & Cring, LLC                  
                                                            GC-23           1,853                  01/23/18   02/05/18    Bette & Cring, LLC                  
                                                            GC-35            -200                  09/26/18   11/13/18    BETTE & CRING LLC                   
 
19-0934   Reconstruction               0-012-010  04/13/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AADC-01             0                  01/20/22   11/08/22    CoreBTS                             
                                                            AADC-010            0                  01/20/22     /  /      Dow Elec                            
                                                            AAEC-04             0                  01/20/22   11/08/22    Dow Electric                        
                                                            AAEC-09             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-11             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-13             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-13             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAGC-01             0                  01/20/22   11/03/22    DC Bldg Systems                     
                                                            AAGC-02             0                  01/20/22   11/03/22    DC Bldg Systems                     
                                                            AAGC-11             0                  01/20/22   11/03/22    DC Bldg Systems                     
                                                            AAPC-01             0                  01/20/22   11/08/22    Empire Northeast Mech               
                                                            AAPC-03             0                  01/20/22   11/08/22    Empire Northeast Mech               
                                                            AASC-02             0                  01/20/22   11/08/22    JL Excavation LLC                   
                                                            CG-01          -6,000                  06/04/21   01/13/22    DC Building Systems                 
                                                            EC-04          -6,587                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            EC-07         215,080                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            GC-04          16,394                  08/11/21   04/20/22    DC BLDG SYSTEMS                     
                                                            HC-03           3,148                  08/25/21   11/25/22    ONTARIO HVAC SOLUTIONS              
                                                            HC-04             936                  11/12/21   12/12/22    Ontario HVAC Solutions              
                                                            PC-03           5,350                  08/11/21   04/19/22    EMPIRE NORTHEAST MECH               
                                                            PC-04            -433                  11/12/21   12/12/22    Empire Northeast Mech               
 
02-1673FP Reconstruction               0-012-FP1  05/02/03  NO CHANGE ORDERS ON ELECTRONIC FILE

          West Carthage 2001 Elementary School:
99-0485   New Construction             0-017-001  06/06/00  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            A11-01         -2,000                  04/18/03   05/02/03    Kratworks                           
                                                            A12-01         -4,275                  04/18/03   05/02/03    Joseph Flihan                       
                                                            A13-01          8,015                  04/18/03   05/02/03    Tougher Industries                  
                                                            A14-01        -10,954                  04/18/03   05/02/03    Watson Electric                     
                                                            A14-02            268                  04/18/03   05/02/03    Watson Electric                     
                                                            A15-04          5,456                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A15-05            979                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A15-08         10,774                  04/18/03   05/02/03    Brosh Mechanical                    
                                                            A3-02         -20,250                  04/18/03   05/02/03    Purcell Construction Corp           
                                                            A3-03         -13,883                  04/18/03   05/02/03    Purcell Construction                
                                                            A7-03          -2,718                  04/18/03   05/02/03    Enjem's                             
                                                            A7-06            -338                  04/18/03   05/02/03    Enjem's                             
                                                            A9-01            -576                  04/18/03   05/02/03    Western NY Floor Company            
                                                            A9-04          -9,406                  04/18/03   05/02/03    Western NY Floor Company            
                                                            F&E-01        -18,561                  05/14/03   05/23/03    Roberts Office Interiors            
 
19-0933   Reconstruction               0-017-007  04/13/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AADC-02             0                  01/20/22   11/08/22    CoreBTS                             
                                                            AAEC-08             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-12             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-17             0                  06/17/22   05/04/23    Dow Elec                            
                                                            AAEC-18             0                  06/17/22   05/04/23    Dow Elec                            
                                                            AAGC-03             0                  01/20/22   11/03/22    DC Bldg Systems                     
                                                            AAGC-04             0                  01/20/22   12/27/22    DC Bldg Systems                     
                                                            EC-03          -5,214                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            EC-06         120,500                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            GC-05           9,800                  08/31/21   05/11/22    DC BUILDING SYSTEMS                 
                                                            PC-02           5,350                  08/11/21   04/19/22    EMPIRE NORTHEAST MECH               
 

          Pole Barn:
95-0145   New Construction             2-016-001  09/05/95  NO CHANGE ORDERS ON ELECTRONIC FILE

          Storage Building @ Transp. Dept.:
17-1256   New Construction             2-019-001  09/10/18  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01          -19,342                  02/11/19   02/27/19    CON TECH BUILDING SYSTEMS           
 

          Pole Barn:
94-0517   Reconstruction               3-006-001  01/25/95  NO CHANGE ORDERS ON ELECTRONIC FILE
06-0573   Reconstruction               3-006-002  03/09/07  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            CO 02-03        3,000                  03/06/08   03/19/08    Cory Wisinki Excavating             
                                                            CO 02-08        1,780                  04/18/11   05/19/11    CORY WISINSKI EXCAVATING            
                                                            CO 03-01      116,000                  03/06/08   03/19/08    Bette & Cring LLC.                  
                                                            CO 04-01        7,000                  04/18/11   05/19/11    PTL CONTRACTING CORPORATION         
                                                            CO 08-02       32,000                  03/06/08   08/12/08    Watson Electric, Incorp.            
                                                            CO 08-04          787                  04/18/11   05/19/11    WATSON ELECTRIC INC                 
                                                            CO 09-01       68,808                  03/06/08   08/12/08    M & N Plumbing & Heating, Incorp.   
                                                            CO07 -01       11,498                  03/06/08   08/12/08    Empire Northeast, Incorp.           
 

          Bus Garage:
94-0122   Additions and Alterations    5-005-001  09/20/94  NO CHANGE ORDERS ON ELECTRONIC FILE
99-1252   Reconstruction               5-005-002  03/26/01  NO CHANGE ORDERS ON ELECTRONIC FILE
04-0383   Reconstruction               5-005-003  01/14/05  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            02-01           5,500                  01/12/06   06/26/06    Cory Wisiniski Excavating           
                                                            07-04             602                  04/11/06   05/26/06    Mec Electric                        
 
15-0468   Reconstruction               5-005-004  05/20/16  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-002          6,106                  11/01/16     /  /      JL Excavation LLC                   
                                                            GC-005         -8,721                  01/12/17   01/27/17    JL Excavation LLC                   
                                                            GC-03           5,552                  06/16/17   06/23/17    Bette & Cring, LLC                  
                                                            GC-04           3,296                  06/16/17   06/23/17    Bette & Cring, LLC                  
                                                            GC-07           3,368                  06/28/17   07/05/17    Bette & Cring, LLC                  
                                                            GC-13          14,998                  09/20/17   10/10/17    Bette & Cring, LLC                  
 
19-0935   Reconstruction               5-005-006  04/13/20  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            AAEC-05             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-06             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-07             0                  01/20/22   11/08/22    Dow Elec                            
                                                            AAEC-16R            0                  06/17/22   05/04/23    Dow Elec                            
                                                            AAGC-05             0                  01/20/22   12/27/22    DC Bldg Systems                     
                                                            AAGC-06             0                  01/20/22   12/27/22    DC Bldg Systems                     
                                                            AAGC-07             0                  01/20/22   12/27/22    DC Bldg Systems                     
                                                            AAGC-10             0                  01/20/22   12/27/22    DC Bldg Systems                     
                                                            AAHC-01             0                  01/20/22   11/08/22    Ontario HVAC Solutions              
                                                            AAHC-02             0                  01/20/22   11/08/22    Ontario HVAC Solutions              
                                                            AAPC-02             0                  01/20/22   11/08/22    Empire Northeast Mech               
                                                            AASC-01             0                  01/20/22   01/25/23    JL Excavation LLC                   
                                                            EC-01               0                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            EC-05          -2,700                  08/10/21   04/19/22    DOW ELECTRIC                        
                                                            EC-09         -27,277                  06/03/22   05/01/23    Dow Elec                            
                                                            GC-02               0                  06/04/21   01/13/22    OC Building Systems                 
                                                            GC-03          -2,900                  06/04/21   01/13/22    DC Building Systems                 
                                                            HC-01               0                  06/04/21   03/24/22    Ontario HVAC Solutions              
                                                            HC-02           2,568                  06/04/21   03/24/22    Ontario HVAC Solutions              
                                                            PC-01               0                  08/11/21   04/19/22    EMPIRE NORTHEAST MECH               
                                                            SC-01R        -13,904                  06/04/21   01/13/22    JL Excavation LLC                   
 
19-0450   Reconstruction               5-005-007  10/22/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           -5,000                  10/02/20   12/01/20    WATSON ELECTRIC, INC.               
 

          Press Box Demolition:
94-0518   New Construction             7-013-001  01/25/95  NO CHANGE ORDERS ON ELECTRONIC FILE
20-0976   Reconstruction               7-013-002  04/06/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          New Press Box:
20-0977   New Construction             7-020-001  04/06/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          District-Wide:
04-0384   Reconstruction               7-999-001  12/28/04  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            07-05            -225                  04/11/06   05/26/06    Mec Electric                        
 
14-1319   Reconstruction               7-999-004  04/15/15  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            GC-001         -7,067                  05/09/17   05/13/19    Nfrastructure Technologies, Inc.    
 
15-0898   Reconstruction               7-999-005  03/28/16  NO CHANGE ORDERS ON ELECTRONIC FILE

BOCES JEF-LEW-HAM-HERK-ONEIDA STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-90-00-00
last updated on 01/10/24
REVIEW    BUILDING NAME/               BLDG./       SED     C. O.          C.O.        Disallowed  C. O.      C. O.                
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Number         Amount      Amount      Received   Approved    Contractor
__________________________________________________________________________________________________________________________________________

          Bohlen Voc Tech Center:
93-1326   Reconstruction               0-002-005  06/08/94  NO CHANGE ORDERS ON ELECTRONIC FILE
10-1111   Additions and Alterations    0-002-006  06/29/11  NO CHANGE ORDERS ON ELECTRONIC FILE
18-1470   Reconstruction               0-002-007  09/16/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-01           12,963                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-02                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-03                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-04                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-06            9,717                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-07                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-08                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-10           23,042                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-11           17,640                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-12           19,303                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-13           19,848                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-14           23,502                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-15           13,159                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-16           25,761                  08/20/20   10/29/20    BETTE & CRING, LLC                  
                                                            1-17            5,344                  11/06/20   01/29/21    BETTE & CRING, LLC                  
                                                            1-18           21,400                  11/06/20   01/29/21    BETTE & CRING, LLC                  
                                                            1-21                0                  11/06/20   01/29/21    BETTE & CRING, LLC                  
                                                            1-24           22,578                  12/11/20   03/09/21    BETTE & CRING, LLC                  
                                                            1-26           25,637                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-28           13,144                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-29            3,764                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-30                0                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-31                0                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-35            8,063                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-36           13,525                  03/25/21   05/06/21    BETTE & CRING, LLC                  
                                                            1-37                0                  08/05/21   04/08/22    BETTE & CRING, LLC                  
                                                            1-38                0                  08/05/21   04/08/22    BETTE & CRING, LLC                  
                                                            1-39           26,407                  08/05/21   04/08/22    BETTE & CRING, LLC                  
                                                            1-40           27,981                  08/05/21   04/08/22    BETTE & CRING, LLC                  
                                                            1-41           17,042                  08/05/21   04/08/22    BETTE & CRING, LLC                  
                                                            1-42                0                  08/26/21   05/06/22    BETTE & CRING, LLC                  
                                                            1-44           13,416                  11/08/21   08/30/22    Bette&Cring, LLC                    
                                                            1-48            6,951                  11/08/21   12/07/22    Bette&Cring, LLC                    
                                                            1-49            2,892                  11/08/21   12/07/22    Bette&Cring, LLC                    
                                                            2-02                0                  11/06/20   01/25/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            2-04                0                  12/11/20   02/25/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            2-09            1,550                  01/27/22   01/27/23    J.E. Sheehan Contr Corp             
                                                            2-10            4,894                  06/02/22   05/01/23    JE Sheehan Contrg Corp              
                                                            3-01                0                  08/20/20   10/29/20    EMPIRE NORTHEAST MECHANOICAL CONTRAC
                                                            3-02           22,458                  08/20/20   10/29/20    ENI MECHANICAL, INC.                
                                                            3-03                0                  11/06/20   01/25/21    EMPIRE NORTHEAST MECHANICAL CONTRACT
                                                            3-04                0                  11/06/20   01/25/21    EMPIRE NORTHEAST MECHANICAL CONTRACT
                                                            3-05                0                  03/25/21   05/25/21    EMPIRE NORTHEAST MECHANICAL CONTRACT
                                                            3-06                0                  05/26/21   07/02/21    Empire Northeast Mechanical         
                                                            3-07                0                  08/05/21   04/13/22    EMPIRE NORTHEAST MECH CONTRACTOR    
                                                            3-08                0                  08/05/21   04/13/22    EMPIRE NORTHEAST MECH CONTRACTOR    
                                                            3-13            4,665                  06/02/22     /  /      Empire Northeast Mech Contr         
                                                            3-14           15,980                  06/02/22   05/01/23    Empire Northeast Mech Contr         
                                                            4-17            3,270                  06/02/22     /  /      NYTRIC Elec Contrs LLC              
                                                            4.1-01         19,991                  07/30/20   10/27/20    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-02         33,781                  07/30/20   10/27/20    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-03          7,992                  07/30/20   10/27/20    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-04              0                  07/30/20   10/27/20    NYTRIC ELECTRICAL CONTRACTORS, LLC  
                                                            4.1-05              0                  11/06/20   01/25/21    NYTRIC ELECTRICAL CONTRACTORS, LLC  
                                                            4.1-07              0                  03/25/21   05/25/21    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-08         15,858                  03/25/21   05/25/21    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-09              0                  03/25/21   05/25/21    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-10          9,128                  03/25/21   05/25/21    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-11              0                  05/26/21   08/12/21    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-12         13,518                  08/05/21   04/13/22    NYTRIC ELECTRICAL CONTRACTORS       
                                                            4.1-14          8,895                  11/08/21   12/07/22    NYTRIC Electrical Contractors, LLC  
                                                            4.2-09         16,186                  08/05/21   04/13/22    S&L ELECTRIC                        
                                                            8-01            7,000                  11/10/22   12/08/23    ZERODRAFT OF CNY INC.               
                                                            AA3-09              0                  11/08/21   12/12/22    Empire Northeast Mech Contractor    
                                                            AA4.1-13            0                  11/08/21   12/07/22    NYTRIC Electrical Contractors, LLC  
 
19-1733   Reconstruction               0-002-008  02/08/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          Watertown Alt Ctr for Educ Srvcs:
91-0964   Reconstruction               0-003-001  05/20/92  NO CHANGE ORDERS ON ELECTRONIC FILE
18-1471   Reconstruction               0-003-002  09/16/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-45            5,178                  11/08/21   12/08/22    Bette&Cring, LLC                    
                                                            1-47            4,395                  11/08/21   12/08/22    Bette&Cring, LLC                    
                                                            1-51            3,142                  06/02/22   05/15/23    Bette&Cring LLC                     
                                                            2-11              441                  06/02/22   05/15/23    JE Sheehan Contrg Corp              
                                                            3-11                0                  02/14/22   02/13/23    Empire Northeast Mech Contr         
                                                            3-12                0                  02/14/22   02/13/23    Empire Northeast mech Contr         
                                                            4-16            7,502                  06/02/22   05/15/23    NYTRIC Elec Contrs LLC              
                                                            4.1-06              0                  11/06/20   03/08/21    NYTRIC ELECTRICAL CONTRACTORS, LLC  
                                                            4.1-15              0                  11/12/21   09/06/22    NYTRIC Electrical Contractors, LLC  
                                                            4.1-15              0                  11/18/21   12/09/22    NYTRIC Electrical Contrs LLC        
 
19-1734   Reconstruction               0-003-003  02/08/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          Sackett Ed Center:
18-1472   Reconstruction               0-009-004  09/16/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-05                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-09                0                  07/30/20   10/23/20    BETTE & CRING, LLC                  
                                                            1-19                0                  11/06/20   03/08/21    BETTE & CRING, LLC                  
                                                            1-20                0                  11/06/20   03/08/21    BETTE & CRING, LLC                  
                                                            1-23            4,247                  12/11/20   02/25/21    BETTE & CRING, LLC                  
                                                            1-25            8,375                  12/11/20   02/25/21    BETTE & CRING, LLC                  
                                                            1-27            4,407                  03/25/21   06/22/21    BETTE & CRING, LLC                  
                                                            1-32                0                  03/25/21   06/22/21    BETTE & CRING, LLC                  
                                                            1-33            5,739                  03/25/21   06/22/21    BETTE & CRING, LLC                  
                                                            1-34           12,201                  03/25/21   06/22/21    BETTE & CRING, LLC                  
                                                            1-43            7,344                  08/26/21   05/06/22    BETTE&CRING, LLC                    
                                                            2-01           19,585                  07/30/20   10/23/20    J.E. SHEEHAN CONTRACTING CORP.      
                                                            2-03                0                  12/11/20   02/25/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            2-05                0                  03/25/21   05/25/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            2-06            4,018                  03/25/21   05/25/21    J.E. SHEEHAN CONTRACTING CORP.      
                                                            4.2-01              0                  11/06/20   01/25/21    S&L ELECTRIC                        
                                                            4.2-04          8,520                  03/25/21   05/25/21    S&L ELECTRIC                        
                                                            4.2-05          7,802                  03/25/21   05/25/21    S&L ELECTRIC                        
                                                            4.2-06              0                  05/26/21   07/02/21    S&L Electric                        
                                                            4.2-08              0                  05/26/21   07/02/21    S&L Electric                        
                                                            4.2-12          5,317                  11/10/22   07/27/23    S&L ELECTRIC                        
                                                            402-03              0                  12/09/20   02/23/21    S&L ELECTRIC                        
 
19-1735   Reconstruction               0-009-005  02/08/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          Boak Educ Center (fmly 8-020):
18-1473   Reconstruction               0-020-002  09/16/19  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            1-22           31,859                  11/06/20   03/08/21    BETTE & CRING, LLC                  
                                                            1-46           11,429                  11/08/21   12/08/22    Bette&Cring, LLC                    
                                                            1-50            6,895                  11/08/21   08/30/22    Bette&Cring, LLC                    
                                                            1-52            2,248                  06/02/22   05/15/23    Bette&Cring LLC                     
                                                            2-07AA              0                  01/27/22   01/25/23    J.E Sheehan Contr Corp              
                                                            2-08                0                  01/27/22   01/25/23    J.E Sheehan Contr Corp              
                                                            4.2-02              0                  11/06/20   03/08/21    S&L ELECTRIC                        
                                                            4.2-07         29,597                  03/25/21   05/25/21    S&L ELECTRIC                        
                                                            4.2-10AA            0                  11/08/21   12/12/22    S&L Electric                        
                                                            4.2-11         10,242                  11/08/21   12/12/22    S&L Electric                        
 
19-1736   Reconstruction               0-020-003  02/08/21  NO CHANGE ORDERS ON ELECTRONIC FILE

          Special Ed Admin Bldg:
20-0995   Reconstruction               1-006-003  05/06/21  *CO No.*       Amount      Disallowed  Received   Approved    Contractor
                                                            3-10                0                  02/14/22   02/13/23    Empire Northeast Mech Contr         
                                                            5-01            1,575                  11/12/21   12/01/22    Continental Const, LLC              
                                                            5-02           28,500                  11/12/21   12/01/22    Continental Const, LLC              
                                                            5-03           22,545                  11/18/21   12/01/22    Continental Const LLC               
                                                            5-04           19,950                  12/01/21   12/01/22    Continetal Const LLC                
                                                            5-05            5,285                  02/14/22   12/01/22    Continental Const LLC               
                                                            5-06                0                  02/14/22   12/01/22    Continental Const LLC               
                                                            5-07            1,855                  06/02/22     /  /      Continetal Const LLC                
                                                            6-01AA              0                  11/12/21   12/12/22    Northern Pioneer Contractors, Inc   
                                                            6-02                0                  11/12/21   12/12/22    Northern Pioneer Contractors, Inc   
                                                            7-01                0                  02/14/22   02/13/23    J.E Sheehan Contr Corp              
                                                            7-02                0                  02/14/22   02/13/23    J.E. Sheehan Contr Corp             
                                                            7-03                0                  01/18/23   11/16/23    JE SHEEHAN CONTRACTING CORP         
                                                            7-04           -1,983                  01/18/23   11/16/23    JE SHEEHAN CONTRACTING CORP         
 

          K-Solar PPA Array-Ground Mounted:
16-0504   Reconstruction               7-021-001  09/27/16  NO CHANGE ORDERS ON ELECTRONIC FILE

          District-wide:
99-0773   Reconstruction               7-999-001  03/22/00  NO CHANGE ORDERS ON ELECTRONIC FILE