490101 BERLIN CSD
_____________________________________________________________________________
REPORT OF SCHEDULE F1 BUS PAYMENTS ASSOCIATED WITH SCHEDULE
F2 BUS BORROWINGS ON FILE WITH SED AS OF 11/1/04.
_____________________________________________________________________________
DEA Schedule F2, School Year: 1998-99
_____________________________________________________________________________
Amount Borrowed: 384,321
Borrowing Date: 9/30/1997
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0033 30,360 30,360
1998-99 0 8,541 384,321 9/30/1997
1999-00 0 8,541 384,321 9/30/1997
2000-01 0 8,541 384,321 9/30/1997
2001-02 0 8,541 384,321 9/30/1997
2002-03 0 8,541 384,321 9/30/1997
_____________________________________________________________________________
0033 Total 0 42,705
_____________________________________________________________________________
0034 30,360 30,360
1998-99 0 8,541 384,321 9/30/1997
1999-00 0 8,541 384,321 9/30/1997
2000-01 0 8,541 384,321 9/30/1997
2001-02 0 8,541 384,321 9/30/1997
2002-03 0 8,541 384,321 9/30/1997
_____________________________________________________________________________
0034 Total 0 42,705
_____________________________________________________________________________
0035 30,360 30,360
1998-99 0 8,541 384,321 9/30/1997
1999-00 0 8,541 384,321 9/30/1997
2000-01 0 8,541 384,321 9/30/1997
2001-02 0 8,541 384,321 9/30/1997
2002-03 0 8,541 384,321 9/30/1997
_____________________________________________________________________________
0035 Total 0 42,705
_____________________________________________________________________________
0056 34,104 34,104
1998-99 0 8,540 384,321 9/30/1997
1999-00 0 8,540 384,321 9/30/1997
2000-01 0 8,540 384,321 9/30/1997
2001-02 0 8,540 384,321 9/30/1997
2002-03 0 8,540 384,321 9/30/1997
_____________________________________________________________________________
0056 Total 0 42,700
_____________________________________________________________________________
0057 34,104 34,104
1998-99 0 8,540 384,321 9/30/1997
1999-00 0 8,540 384,321 9/30/1997
2000-01 0 8,540 384,321 9/30/1997
2001-02 0 8,540 384,321 9/30/1997
2002-03 0 8,540 384,321 9/30/1997
_____________________________________________________________________________
0057 Total 0 42,700
_____________________________________________________________________________
0058 59,336 59,336
1998-99 0 8,540 384,321 9/30/1997
1999-00 0 8,540 384,321 9/30/1997
2000-01 0 8,540 384,321 9/30/1997
2001-02 0 8,540 384,321 9/30/1997
2002-03 0 8,540 384,321 9/30/1997
_____________________________________________________________________________
0058 Total 0 42,700
_____________________________________________________________________________
0059 59,336 59,336
1998-99 0 8,540 384,321 9/30/1997
1999-00 0 8,540 384,321 9/30/1997
2000-01 0 8,540 384,321 9/30/1997
2001-02 0 8,540 384,321 9/30/1997
2002-03 0 8,540 384,321 9/30/1997
_____________________________________________________________________________
0059 Total 0 42,700
_____________________________________________________________________________
0060 59,336 59,336
1998-99 0 8,540 384,321 9/30/1997
1999-00 0 8,540 384,321 9/30/1997
2000-01 0 8,540 384,321 9/30/1997
2001-02 0 8,540 384,321 9/30/1997
2002-03 0 8,540 384,321 9/30/1997
_____________________________________________________________________________
0060 Total 0 42,700
_____________________________________________________________________________
0061 47,025 44,384
1998-99 0 8,541 384,321 9/30/1997
1999-00 0 8,541 384,321 9/30/1997
2000-01 0 8,541 384,321 9/30/1997
2001-02 0 8,541 384,321 9/30/1997
2002-03 0 8,541 384,321 9/30/1997
_____________________________________________________________________________
0061 Total 0 42,705
_____________________________________________________________________________
A B C D
384,321 381,680 0 384,320 Grand Totals
A.Grand Total Net Cost: 384,321
B.Grand Total Approved Cost: 381,680
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 384,320
E.Total Aidable Cost: * 381,679
F.Approved Remaining Principal(B-E): 1
G.Remaining Life:** 1
H. 2005-06 Debt Service: *** 0
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 2000-01
_____________________________________________________________________________
Amount Borrowed: 361,729
Borrowing Date: 9/30/1999
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0062 41,350 41,350
2000-01 0 12,057 41,350 9/30/1999
2001-02 0 12,057 41,350 9/30/1999
2002-03 0 12,057 41,350 9/30/1999
2003-04 0 12,057 41,350 9/30/1999
_____________________________________________________________________________
0062 Total 0 48,228
_____________________________________________________________________________
0063 71,995 71,995
2000-01 0 12,057 71,995 9/30/1999
2001-02 0 12,057 71,995 9/30/1999
2002-03 0 12,057 71,995 9/30/1999
2003-04 0 12,057 71,995 9/30/1999
_____________________________________________________________________________
0063 Total 0 48,228
_____________________________________________________________________________
0064 62,096 62,096
2000-01 0 12,057 62,096 9/30/1999
2001-02 0 12,057 62,096 9/30/1999
2002-03 0 12,057 62,096 9/30/1999
2003-04 0 12,058 62,096 9/30/1999
_____________________________________________________________________________
0064 Total 0 48,229
_____________________________________________________________________________
0065 62,096 62,096
2000-01 0 12,058 62,096 9/30/1999
2001-02 0 12,058 62,096 9/30/1999
2002-03 0 12,058 62,096 9/30/1999
2003-04 0 12,058 62,096 9/30/1999
_____________________________________________________________________________
0065 Total 0 48,232
_____________________________________________________________________________
0066 62,096 62,096
2000-01 0 12,058 62,096 9/30/1999
2001-02 0 12,058 62,096 9/30/1999
2002-03 0 12,058 62,096 9/30/1999
2003-04 0 12,058 62,096 9/30/1999
_____________________________________________________________________________
0066 Total 0 48,232
_____________________________________________________________________________
0067 62,096 62,096
2000-01 0 12,058 62,096 9/30/1999
2001-02 0 12,058 62,096 9/30/1999
2002-03 0 12,058 62,096 9/30/1999
2003-04 0 12,058 62,096 9/30/1999
_____________________________________________________________________________
0067 Total 0 48,232
_____________________________________________________________________________
A B C D
361,729 361,729 0 289,381 Grand Totals
A.Grand Total Net Cost: 361,729
B.Grand Total Approved Cost: 361,729
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 289,381
E.Total Aidable Cost: * 289,381
F.Approved Remaining Principal(B-E): 72,348
G.Remaining Life:** 1
H. 2005-06 Debt Service: *** 73,640
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 2002-03
_____________________________________________________________________________
Amount Borrowed: 382,450
Borrowing Date: 9/18/2001
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0036 29,116 29,116
2002-03 0 9,561 382,450 9/18/2001
2003-04 0 9,561 29,116 9/18/2001
_____________________________________________________________________________
0036 Total 0 19,122
_____________________________________________________________________________
0037 29,116 29,116
2002-03 0 9,561 382,450 9/18/2001
2003-04 0 9,561 29,116 9/18/2001
_____________________________________________________________________________
0037 Total 0 19,122
_____________________________________________________________________________
0068 61,838 61,838
2002-03 0 9,561 382,450 9/18/2001
2003-04 0 9,562 61,838 9/18/2001
_____________________________________________________________________________
0068 Total 0 19,123
_____________________________________________________________________________
0069 61,838 61,838
2002-03 0 9,561 382,450 9/18/2001
2003-04 0 9,562 61,838 9/18/2001
_____________________________________________________________________________
0069 Total 0 19,123
_____________________________________________________________________________
0070 61,838 61,838
2002-03 0 9,561 382,450 9/18/2001
2003-04 0 9,561 61,838 9/18/2001
_____________________________________________________________________________
0070 Total 0 19,122
_____________________________________________________________________________
0071 61,838 61,838
2002-03 0 9,561 382,450 9/18/2001
2003-04 0 9,561 61,838 9/18/2001
_____________________________________________________________________________
0071 Total 0 19,122
_____________________________________________________________________________
0072 38,433 38,433
2002-03 0 9,562 382,450 9/18/2001
2003-04 0 9,561 38,433 9/18/2001
_____________________________________________________________________________
0072 Total 0 19,123
_____________________________________________________________________________
0073 38,433 38,433
2002-03 0 9,562 382,450 9/18/2001
2003-04 0 9,561 38,433 9/18/2001
_____________________________________________________________________________
0073 Total 0 19,123
_____________________________________________________________________________
A B C D
382,450 382,450 0 152,980 Grand Totals
A.Grand Total Net Cost: 382,450
B.Grand Total Approved Cost: 382,450
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 152,980
E.Total Aidable Cost: * 152,980
F.Approved Remaining Principal(B-E): 229,470
G.Remaining Life:** 1
H. 2005-06 Debt Service: *** 233,566
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
******************************************************************************
End of Report
NYSED HOME PAGE | STATE AID HOME PAGE | DISTRICT HOME PAGE