010402 RAVENA-COEYMANS-SELKIRK CSD
_____________________________________________________________________________
REPORT OF SCHEDULE F1 BUS PAYMENTS ASSOCIATED WITH SCHEDULE
F2 BUS BORROWINGS ON FILE WITH SED AS OF 11/1/04.
_____________________________________________________________________________
DEA Schedule F2, School Year: 1998-99
_____________________________________________________________________________
Amount Borrowed: 398,000
Borrowing Date: 8/27/1997
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0206 37,890 37,890
1998-99 0 79,600 398,000 8/27/1997
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
2002-03 0 0 398,000 8/27/1997
_____________________________________________________________________________
0206 Total 0 79,600
_____________________________________________________________________________
0207 37,890 37,890
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
2002-03 0 0 398,000 8/27/1997
_____________________________________________________________________________
0207 Total 0 0
_____________________________________________________________________________
0208 27,263 27,263
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
2002-03 0 0 398,000 8/27/1997
_____________________________________________________________________________
0208 Total 0 0
_____________________________________________________________________________
0209 27,263 27,263
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
2002-03 0 79,600 398,000 8/27/1997
_____________________________________________________________________________
0209 Total 0 79,600
_____________________________________________________________________________
0210 66,637 66,637
1999-00 0 79,600 398,000 8/27/1997
2000-01 0 79,600 398,000 8/27/1997
2001-02 0 79,600 398,000 8/27/1997
2002-03 0 0 398,000 8/27/1997
_____________________________________________________________________________
0210 Total 0 238,800
_____________________________________________________________________________
0211 66,637 66,637
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
2002-03 0 0 398,000 8/27/1997
_____________________________________________________________________________
0211 Total 0 0
_____________________________________________________________________________
0212 66,637 66,637
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
_____________________________________________________________________________
0212 Total 0 0
_____________________________________________________________________________
0213 66,637 66,637
2000-01 0 0 398,000 8/27/1997
2001-02 0 0 398,000 8/27/1997
2002-03 0 0 398,000 8/27/1997
_____________________________________________________________________________
0213 Total 0 0
_____________________________________________________________________________
A B C D
396,854 396,854 0 398,000 Grand Totals
A.Grand Total Net Cost: 396,854
B.Grand Total Approved Cost: 396,854
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 398,000
E.Total Aidable Cost: * 396,854
F.Approved Remaining Principal(B-E): 0
G.Remaining Life:** 0
H. 2005-06 Debt Service: *** 0
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 1999-00
_____________________________________________________________________________
Amount Borrowed: 327,000
Borrowing Date: 11/13/1998
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0214 66,982 66,982
2000-01 0 0 327,000 11/13/1998
2001-02 0 0 327,000 11/13/1998
2002-03 0 0 327,000 11/13/1998
2003-04 0 0 327,000 11/13/1998
_____________________________________________________________________________
0214 Total 0 0
_____________________________________________________________________________
0215 66,982 66,982
2000-01 0 0 327,000 11/13/1998
2001-02 0 0 327,000 11/13/1998
2002-03 0 65,407 327,000 11/13/1998
2003-04 0 65,393 327,000 11/13/1998
_____________________________________________________________________________
0215 Total 0 130,800
_____________________________________________________________________________
0216 66,982 66,982
1999-00 0 65,400 327,000 11/13/1998
2000-01 0 65,400 327,000 11/13/1998
2001-02 0 65,400 327,000 11/13/1998
2002-03 0 0 327,000 11/13/1998
2003-04 0 0 327,000 11/13/1998
_____________________________________________________________________________
0216 Total 0 196,200
_____________________________________________________________________________
0217 65,757 65,757
2000-01 0 0 327,000 11/13/1998
2001-02 0 0 327,000 11/13/1998
2002-03 0 0 327,000 11/13/1998
2003-04 0 0 327,000 11/13/1998
_____________________________________________________________________________
0217 Total 0 0
_____________________________________________________________________________
0218 52,939 52,939
2000-01 0 0 327,000 11/13/1998
2001-02 0 0 327,000 11/13/1998
2002-03 0 0 327,000 11/13/1998
2003-04 0 0 327,000 11/13/1998
_____________________________________________________________________________
0218 Total 0 0
_____________________________________________________________________________
A B C D
319,642 319,642 0 327,000 Grand Totals
A.Grand Total Net Cost: 319,642
B.Grand Total Approved Cost: 319,642
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 327,000
E.Total Aidable Cost: * 319,642
F.Approved Remaining Principal(B-E): 0
G.Remaining Life:** 0
H. 2005-06 Debt Service: *** 0
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 2000-01
_____________________________________________________________________________
Amount Borrowed: 336,000
Borrowing Date: 8/11/1999
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0219 36,900 36,900
2000-01 0 0 336,000 8/11/1999
2001-02 0 0 336,000 8/11/1999
2002-03 0 0 336,000 8/11/1999
2003-04 0 0 336,000 8/11/1999
_____________________________________________________________________________
0219 Total 0 0
_____________________________________________________________________________
0220 36,900 36,900
2000-01 0 0 336,000 8/11/1999
2001-02 0 0 336,000 8/11/1999
2002-03 0 0 336,000 8/11/1999
2003-04 0 0 336,000 8/11/1999
_____________________________________________________________________________
0220 Total 0 0
_____________________________________________________________________________
0221 67,420 67,420
2000-01 0 0 336,000 8/11/1999
2001-02 0 67,200 336,000 8/11/1999
2002-03 0 67,200 336,000 8/11/1999
2003-04 0 67,200 336,000 8/11/1999
_____________________________________________________________________________
0221 Total 0 201,600
_____________________________________________________________________________
0222 67,420 67,420
2000-01 0 67,200 336,000 8/11/1999
2001-02 0 0 336,000 8/11/1999
2002-03 0 0 336,000 8/11/1999
2003-04 0 0 336,000 8/11/1999
_____________________________________________________________________________
0222 Total 0 67,200
_____________________________________________________________________________
0223 67,420 67,420
2000-01 0 0 336,000 8/11/1999
2001-02 0 0 336,000 8/11/1999
2002-03 0 0 336,000 8/11/1999
2003-04 0 0 336,000 8/11/1999
_____________________________________________________________________________
0223 Total 0 0
_____________________________________________________________________________
0224 57,930 57,930
2001-02 0 0 336,000 8/11/1999
2002-03 0 0 336,000 8/11/1999
2003-04 0 0 336,000 8/11/1999
_____________________________________________________________________________
0224 Total 0 0
_____________________________________________________________________________
A B C D
333,990 333,990 0 268,800 Grand Totals
A.Grand Total Net Cost: 333,990
B.Grand Total Approved Cost: 333,990
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 268,800
E.Total Aidable Cost: * 267,192
F.Approved Remaining Principal(B-E): 66,798
G.Remaining Life:** 1
H. 2005-06 Debt Service: *** 67,990
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 2001-02
_____________________________________________________________________________
Amount Borrowed: 329,000
Borrowing Date: 8/14/2001
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0230 31,775 31,775
2002-03 0 65,800 329,000 8/14/2001
2003-04 0 65,800 329,000 8/14/2001
_____________________________________________________________________________
0230 Total 0 131,600
_____________________________________________________________________________
0231 79,301 79,301
2002-03 0 0 329,000 8/14/2001
2003-04 0 0 329,000 8/14/2001
_____________________________________________________________________________
0231 Total 0 0
_____________________________________________________________________________
0232 69,045 69,045
2002-03 0 0 329,000 8/14/2001
2003-04 0 0 329,000 8/14/2001
_____________________________________________________________________________
0232 Total 0 0
_____________________________________________________________________________
0233 69,045 69,045
2002-03 0 0 329,000 8/14/2001
2003-04 0 0 329,000 8/14/2001
_____________________________________________________________________________
0233 Total 0 0
_____________________________________________________________________________
0234 69,045 69,045
2002-03 0 0 329,000 8/14/2001
2003-04 0 0 329,000 8/14/2001
_____________________________________________________________________________
0234 Total 0 0
_____________________________________________________________________________
A B C D
318,211 318,211 0 131,600 Grand Totals
A.Grand Total Net Cost: 318,211
B.Grand Total Approved Cost: 318,211
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 131,600
E.Total Aidable Cost: * 127,284
F.Approved Remaining Principal(B-E): 190,927
G.Remaining Life:** 1
H. 2005-06 Debt Service: *** 194,334
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 2002-03
_____________________________________________________________________________
Amount Borrowed: 339,000
Borrowing Date: 8/14/2000
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0225 66,526 66,526
2001-02 0 0 339,000 8/14/2000
2002-03 0 0 339,000 8/14/2000
2003-04 0 0 339,000 8/14/2000
_____________________________________________________________________________
0225 Total 0 0
_____________________________________________________________________________
0226 67,420 67,420
2001-02 0 0 339,000 8/14/2000
2002-03 0 67,800 339,000 8/14/2000
2003-04 0 67,800 339,000 8/14/2000
_____________________________________________________________________________
0226 Total 0 135,600
_____________________________________________________________________________
0227 67,420 67,420
2001-02 0 67,800 339,000 8/14/2000
2002-03 0 0 339,000 8/14/2000
2003-04 0 0 339,000 8/14/2000
_____________________________________________________________________________
0227 Total 0 67,800
_____________________________________________________________________________
0228 67,420 67,420
2001-02 0 0 339,000 8/14/2000
2002-03 0 0 339,000 8/14/2000
2003-04 0 0 339,000 8/14/2000
_____________________________________________________________________________
0228 Total 0 0
_____________________________________________________________________________
0229 67,420 67,420
2001-02 0 0 339,000 8/14/2000
2002-03 0 0 339,000 8/14/2000
2003-04 0 0 339,000 8/14/2000
_____________________________________________________________________________
0229 Total 0 0
_____________________________________________________________________________
A B C D
336,206 336,206 0 203,400 Grand Totals
A.Grand Total Net Cost: 336,206
B.Grand Total Approved Cost: 336,206
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 203,400
E.Total Aidable Cost: * 201,724
F.Approved Remaining Principal(B-E): 134,482
G.Remaining Life:** 1
H. 2005-06 Debt Service: *** 136,882
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
_____________________________________________________________________________
DEA Schedule F2, School Year: 2003-04
_____________________________________________________________________________
Amount Borrowed: 278,800
Borrowing Date: 12/18/2002
_____________________________________________________________________________
Bus School NetCostApproved Budget DS Amount Borrowing Date
Num Year Cost Approp Principal Borrowed
_____________________________________________________________________________
0239 67,609 67,609
2003-04 0 55,760 278,800 12/18/2002
_____________________________________________________________________________
0239 Total 0 55,760
_____________________________________________________________________________
0240 33,394 33,394
2003-04 0 0 278,800 12/18/2002
_____________________________________________________________________________
0240 Total 0 0
_____________________________________________________________________________
0241 54,514 54,514
2003-04 0 0 278,800 12/18/2002
_____________________________________________________________________________
0241 Total 0 0
_____________________________________________________________________________
0242 60,247 60,247
2003-04 0 0 278,800 12/18/2002
_____________________________________________________________________________
0242 Total 0 0
_____________________________________________________________________________
0243 60,247 60,247
2003-04 0 0 278,800 12/18/2002
_____________________________________________________________________________
0243 Total 0 0
_____________________________________________________________________________
A B C D
276,011 276,011 0 55,760 Grand Totals
A.Grand Total Net Cost: 276,011
B.Grand Total Approved Cost: 276,011
C.Grand Total Cash Paid: 0
D.Grand Total Principal Paid: 55,760
E.Total Aidable Cost: * 55,202
F.Approved Remaining Principal(B-E): 220,809
G.Remaining Life:** 2
H. 2005-06 Debt Service: *** 113,702
*Click here to see how Total Aided Cost is calculated.
**Remaining Life is the number of years determined by subtracting the
difference between 7/01/2005 and the borrowing date from five years.
For borrowings with approved remaining principal greater than zero but
which calculate a remaining life <= zero, a remaining life of 1 year
and two assumed payments will be assigned.
***Debt service is calculated using a 2.375 percent statewide interest rate.
******************************************************************************
End of Report