SA777 NEW YORK STATE EDUCATION DEPARTMENT 10/10/08
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 641001 --- HARTFORD
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0001 FP1 MAIN BUILDING $6,980 SA-4
0001 001 MAIN BUILDING FILE SA-139 $0 SA-4
0001 003 MAIN BUILDING 05/15/89 $200,000 SA-139
0001 004 MAIN BUILDING 04/19/89 $942,424 SA-139 PROCESSED
0001 005 MAIN BUILDING 04/02/91 $76,078 SA-139 PROCESSED
0001 007 MAIN BUILDING 11/03/94 $225,000 SA-139 PROCESSED
0001 008 MAIN BUILDING 10/09/97 $126,211 SA-139 PROCESSED
0001 009 MAIN BUILDING 04/27/98 $463,349 SA-139 PROCESSED
0001 010 MAIN BUILDING $0 SA-4
0001 013 MAIN BUILDING 04/21/08 $8,663,969 SA-139
0002 001 SHOP BUILDING 08/15/89 $108,000 SA-139 PROCESSED
0002 002 SHOP BUILDING 04/02/91 $31,365 SA-139 PROCESSED
0002 003 SHOP BUILDING 10/09/97 $21,800 SA-139 PROCESSED
0002 004 SHOP BUILDING 04/25/02 $895,000 SA-139 PROCESSED
0002 005 SHOP BUILDING 04/21/08 $1,305,030 SA-139
0003 001 ELEMENTARY BLDG 04/19/89 $148,576 SA-139 PROCESSED
0003 002 ELEMENTARY BLDG 12/10/91 $50,870 SA-139 PROCESSED
0003 004 ELEMENTARY BLDG 04/27/98 $924,519 SA-139 PROCESSED
0003 005 ELEMENTARY BLDG 04/21/08 $3,116,871 SA-139
5004 L01 HARTFORD BUS GARAGE 06/30/02 $60,000 SA-139
5004 L02 HARTFORD BUS GARAGE 09/05/05 $48,000 SA-139
5004 L03 HARTFORD BUS GARAGE 10/26/06 $12,000 SA-139
5004 L04 HARTFORD BUS GARAGE 03/13/07 $12,000 SA-139
5004 L05 HARTFORD BUS GARAGE 02/21/08 $12,000 SA-139
5004 001 HARTFORD BUS GARAGE FILE SA-139 $0 SA-4
5004 002 HARTFORD BUS GARAGE 10/09/97 $39,121 SA-139 PROCESSED
7009 001 04/21/08 $1,850,130 SA-139