SA777 NEW YORK STATE EDUCATION DEPARTMENT 11/06/09
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 541401 --- SHARON SPRINGS
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0001 001 02/06/87 $105,996 SA-139 PROCESSED
0001 002 MAIN BUILDING 11/20/87 $80,000 SA-139 PROCESSED
0001 004 MAIN BUILDING 05/21/90 $50,383 SA-139 PROCESSED
0001 005 MAIN BUILDING 12/05/89 $110,889 SA-139 PROCESSED
0001 006 MAIN BUILDING 10/14/93 $168,000 SA-139 PROCESSED
0001 008 MAIN BUILDING 06/13/99 $5,243,646 SA-139 PROCESSED
0001 009 MAIN BUILDING 01/27/94 $349,921 SA-139 PROCESSED
0001 011 MAIN BUILDING 06/23/99 $955,600 SA-139 PROCESSED
0001 012 MAIN BUILDING 08/05/98 $148,124 SA-139 PROCESSED
0001 013 MAIN BUILDING 02/11/02 $5,212,170 SA-139
0002 001 TECHNOLOGIES BLDG/BUS GAR 10/20/93 $31,956 SA-139 PROCESSED
5005 001 XXXNEW BUS GARAGEXXX 02/11/02 $1,600,000 SA-139
7006 001 FILE SA-139 $250,000 SA-4