DISTRICT: 512902 --- POTSDAM
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0001 E01 POTSDAM HIGH SCHOOL 03/28/95 $16,895 SA-139 PROCESSED
0001 FP1 POTSDAM HIGH SCHOOL $6,132 SA-4
0001 002 POTSDAM HIGH SCHOOL 09/29/87 $460,808 SA-139 PROCESSED
0001 003 POTSDAM HIGH SCHOOL 08/04/88 $240,893 SA-139 PROCESSED
0001 005 POTSDAM HIGH SCHOOL 07/17/91 $1,062,200 SA-139 PROCESSED
0001 006 POTSDAM HIGH SCHOOL FILE SA-139 $15,000 SA-4
0001 007 POTSDAM HIGH SCHOOL 03/28/95 $3,406,100 SA-139 PROCESSED
0001 010 POTSDAM HIGH SCHOOL 06/25/98 $1,503,200 SA-139 PROCESSED
0001 012 POTSDAM HIGH SCHOOL 03/21/07 $12,862,897 SA-139
0002 E01 LAWRENCE AVE ELEM 03/28/95 $27,295 SA-139 PROCESSED
0002 FP1 LAWRENCE AVE ELEMENTARY S $5,919 SA-4
0002 001 LAWRENCE AVE ELEM 09/29/87 $175,730 SA-139 PROCESSED
0002 002 LAWRENCE AVE ELEM 09/29/87 $52,510 SA-139 PROCESSED
0002 003 LAWRENCE AVE ELEM 08/04/88 $1,505,207 SA-139 PROCESSED
0002 005 LAWRENCE AVE ELEM 07/17/91 $672,400 SA-139 PROCESSED
0002 006 LAWRENCE AVE ELEM 03/28/95 $3,876,760 SA-139 PROCESSED
0002 009 LAWRENCE AVE ELEMENTARY S 06/25/98 $1,228,620 SA-139 PROCESSED
0002 011 LAWRENCE AVE ELEMENTARY S 03/21/07 $7,186,550 SA-139
0005 E01 MIDDLE SCHOOL 03/28/95 $26,765 SA-139 PROCESSED
0005 FP1 MIDDLE SCHOOL $5,812 SA-4
0005 001 MIDDLE SCHOOL 09/30/87 $372,300 SA-139 PROCESSED
0005 002 MIDDLE SCHOOL 09/29/87 $55,400 SA-139 PROCESSED
0005 004 MIDDLE SCHOOL 05/27/93 $715,600 SA-139 PROCESSED
0005 006 MIDDLE SCHOOL 03/28/95 $1,765,000 SA-139 PROCESSED
0005 009 MIDDLE SCHOOL 06/25/98 $308,750 SA-139 PROCESSED
0005 011 MIDDLE SCHOOL 03/21/07 $3,890,883 SA-139
5004 001 BUS GARAGE 01/24/94 $15,500 SA-139 PROCESSED
5004 002 BUS GARAGE 07/17/91 $165,400 SA-139 PROCESSED
5004 006 BUS GARAGE $14,945 SA-4 PROCESSED
5004 007 BUS GARAGE 06/25/98 $53,369 SA-139 PROCESSED
5004 009 BUS GARAGE 03/21/07 $191,670 SA-139
7010 001 03/21/07 $30,000 SA-139
7999 E01 03/28/95 $403,800 SA-139 PROCESSED