SA777 NEW YORK STATE EDUCATION DEPARTMENT 09/05/08
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 512001 --- MASSENA
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0001 002 FILE SA-139 $0 SA-4
0001 004 JEFFERSON ELEMENTARY 08/18/99 $3,246,358 SA-139 PROCESSED
0001 005 JEFFERSON ELEMENTARY 01/22/98 $116,624 SA-139 PROCESSED
0001 007 JEFFERSON ELEMENTARY 03/11/03 $52,938 SA-139 PROCESSED
0001 008 JEFFERSON ELEMENTARY 10/29/07 $4,009,058 SA-139
0001 009 JEFFERSON ELEMENTARY 06/14/07 $143,217 SA-139
0003 003 LOUISVILLE ELEM 04/27/92 $55,440 SA-139 PROCESSED
0003 004 LOUISVILLE ELEMENTARY 02/24/94 $143,471 SA-139 PROCESSED
0003 005 08/15/06 $39,241 SA-139 PROCESSED
0004 002 MADISON ELEMENTARY 05/10/88 $32,355 SA-139 PROCESSED
0004 004 MADISON ELEMENTARY 02/24/94 $39,173 SA-139 PROCESSED
0004 005 MADISON ELEMENTARY 08/18/99 $3,560,482 SA-139 PROCESSED
0004 007 MADISON ELEMENTARY 10/29/07 $4,037,565 SA-139
0005 001 NIGHTENGALE ELEM FILE SA-139 $0 SA-4
0005 004 NIGHTENGALE ELEMENTARY 08/18/99 $3,450,935 SA-139 PROCESSED
0005 005 NIGHTENGALE ELEMENTARY 01/22/98 $21,339 SA-139 PROCESSED
0005 007 NIGHTENGALE ELEMENTARY 11/11/04 $84,155 SA-139 PROCESSED
0005 008 NIGHTENGALE ELEMENTARY 10/29/07 $3,649,548 SA-139
0008 002 MASSENA SENIOR HIGH 04/27/92 $2,800,705 SA-139 PROCESSED
0008 003 MASSENA SENIOR HIGH 08/18/99 $5,993,655 SA-139 PROCESSED
0008 005 MASSENA SENIOR HIGH 03/11/03 $313,225 SA-139 PROCESSED
0008 006 MASSENA SENIOR HIGH 08/15/06 $70,759 SA-139 PROCESSED
0008 007 MASSENA SENIOR HIGH FILE SA-139 $15,857,263 SA-4
0008 008 MASSENA SENIOR HIGH 06/27/07 $3,424,321 SA-139
0011 001 TWIN RIVER ELEM 04/27/92 $21,120 SA-139 PROCESSED
0011 002 TWIN RIVER ELEMENTARY 02/24/94 $162,308 SA-139 PROCESSED
0012 001 LEARY JUNIOR HIGH 05/31/88 $24,817 SA-139 PROCESSED
0012 002 LEARY JUNIOR HIGH 04/27/92 $681,929 SA-139 PROCESSED
0012 003 LEARY JUNIOR HIGH 08/18/99 $4,115,230 SA-139 PROCESSED
0012 004 LEARY JUNIOR HIGH 01/22/98 $133,852 SA-139 PROCESSED
0012 005 LEARY JUNIOR HIGH 11/11/04 $15,845 SA-139 PROCESSED
0012 006 LEARY JUNIOR HIGH 10/29/07 $1,446,566 SA-139
0012 007 LEARY JUNIOR HIGH 07/07/06 $761,200 SA-139
5006 003 BUS GARAGE MAINT 04/27/92 $143,616 SA-139 PROCESSED
5006 005 BUS GARAGE MAINT 03/11/99 $147,456 SA-139 PROCESSED
5006 006 BUS GARAGE MAINT 10/29/07 $2,200,000 SA-139
5006 007 BUS GARAGE MAINT 05/22/08 $280,260 SA-139
5019 001 XXXSHARED TRANS/FUEL DEPO 05/20/02 $3,850,000 SA-139 PROCESSED
7013 001 BROADCAST BOOTH FILE SA-139 $0 SA-4
7014 001 BROADCAST BOOTH/PRESS BOX FILE SA-139 $0 SA-4