DISTRICT: 511101 --- GOUVERNEUR
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0003 002 EAST SIDE ELEM SCHL 08/17/88 $3,340,859 SA-139 PROCESSED
0003 003 EAST SIDE ELEM SCHL 11/14/89 $1,124,451 SA-139 PROCESSED
0003 005 EAST SIDE ELEM SCHOOL 05/22/97 $412,770 SA-139 PROCESSED
0003 006 EAST SIDE ELEM SCHOOL $69,946 SA-4 PROCESSED
0003 007 EAST SIDE ELEM SCHOOL 03/11/02 $1,181,400 SA-139 PROCESSED
0003 008 EAST SIDE ELEM SCHOOL 06/02/08 $2,075,125 SA-139
0004 002 FOWLER ELEM SCHOOL 08/17/88 $288,458 SA-139 PROCESSED
0004 003 FOWLER ELEM SCHOOL 11/14/89 $634,028 SA-139 PROCESSED
0004 005 FOWLER ELEM SCHOOL 05/22/97 $337,220 SA-139 PROCESSED
0004 006 FOWLER ELEM SCHOOL $80,694 SA-4 PROCESSED
0004 007 FOWLER ELEM SCHOOL 03/11/02 $405,763 SA-139 PROCESSED
0004 008 FOWLER ELEM SCHOOL 06/02/08 $1,066,475 SA-139
0004 009 FOWLER ELEM SCHOOL 08/06/07 $45,142 SA-139
0006 001 WEST SIDE ELEM SCHOOL FILE SA-139 $64,850 SA-4 PROCESSED
0006 002 WEST SIDE ELEM SCHL 08/17/88 $837,624 SA-139 PROCESSED
0006 003 WEST SIDE ELEM SCHL 11/14/89 $1,838,836 SA-139 PROCESSED
0006 005 WEST SIDE ELEM SCHOOL 05/22/97 $425,650 SA-139 PROCESSED
0006 006 WEST SIDE ELEM SCHOOL $112,602 SA-4 PROCESSED
0006 007 WEST SIDE ELEM SCHOOL 03/11/02 $1,061,638 SA-139 PROCESSED
0006 008 WEST SIDE ELEM SCHOOL 06/02/08 $1,829,642 SA-139
0007 MD1 SENIOR HIGH SCHOOL $1,440 SA-4
0007 SC1 SENIOR HIGH SCHOOL $5,528 SA-4
0007 001 SENIOR HIGH SCHOOL 08/17/88 $1,480,348 SA-139 PROCESSED
0007 002 SENIOR HIGH SCHOOL $59,510 SA-4 PROCESSED
0007 003 SENIOR HIGH SCHOOL 05/22/97 $713,660 SA-139 PROCESSED
0007 004 SENIOR HIGH SCHOOL $133,809 SA-4 PROCESSED
0007 005 SENIOR HIGH SCHOOL 03/11/02 $7,491,269 SA-139 PROCESSED
0007 006 SENIOR HIGH SCHOOL 06/02/08 $3,632,671 SA-139
0007 007 SENIOR HIGH SCHOOL 08/06/07 $327,141 SA-139
0007 008 SENIOR HIGH SCHOOL 06/02/08 $235,836 SA-139
5011 002 BUS GARAGE 08/17/88 $599,861 SA-139 PROCESSED
5011 003 BUS GARAGE 05/22/97 $192,080 SA-139 PROCESSED
5011 004 BUS GARAGE 03/11/02 $199,926 SA-139 PROCESSED
5011 005 BUS GARAGE 06/02/08 $475,728 SA-139
5011 006 BUS GARAGE 08/06/07 $12,240 SA-139 PROCESSED
NYSED HOME PAGE | STATE AID HOME PAGE | DISTRICT HOME PAGE