SA777 NEW YORK STATE EDUCATION DEPARTMENT 08/29/08
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 261401 --- PITTSFORD
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0002 FP1 JEFFERSON RD SCHOOL $4,000 SA-4
0002 003 JEFFERSON RD SCHOOL 11/05/87 $40,531 SA-139 PROCESSED
0002 004 JEFFERSON RD SCHOOL 02/02/90 $210,410 SA-139 PROCESSED
0002 005 JEFFERSON RD SCHOOL 07/28/88 $171,000 SA-139 PROCESSED
0002 007 JEFFERSON RD SCHOOL 01/03/89 $40,661 SA-139 PROCESSED
0002 008 JEFFERSON RD SCHOOL 06/13/89 $32,890 SA-139 PROCESSED
0002 009 JEFFERSON RD SCHOOL 04/02/90 $16,432 SA-139 PROCESSED
0002 010 JEFFERSON RD SCHOOL 08/20/91 $126,500 SA-139 PROCESSED
0002 011 JEFFERSON RD SCHOOL 06/16/92 $56,400 SA-139 PROCESSED
0002 012 JEFFERSON RD SCHOOL 01/11/94 $34,600 SA-139 PROCESSED
0002 014 JEFFERSON RD SCHOOL 12/19/03 $3,946,640 SA-139
0002 015 JEFFERSON RD SCHOOL 06/27/00 $126,867 SA-139 PROCESSED
0002 016 JEFFERSON RD SCHOOL 04/08/02 $7,648 SA-139
0002 017 JEFFERSON RD SCHOOL 06/06/02 $421,224 SA-139 PROCESSED
0002 018 JEFFERSON RD SCHOOL 08/27/04 $315,645 SA-139 PROCESSED
0002 020 JEFFERSON RD SCHOOL FILE SA-139 $0 SA-4
0002 021 JEFFERSON RD SCHOOL 05/03/07 $278,696 SA-139
0003 FP1 SUTHERLAND HIGH $8,000 SA-4
0003 SC1 SUTHERLAND HIGH $24,065 SA-4
0003 001 SUTHERLAND HIGH FILE SA-139 $85,104 SA-4
0003 002 SUTHERLAND HIGH FILE SA-139 $0 SA-4
0003 003 SUTHERLAND HIGH 11/05/87 $152,441 SA-139 PROCESSED
0003 004 SUTHERLAND HIGH 02/02/90 $1,435,000 SA-139 PROCESSED
0003 005 SUTHERLAND HIGH 07/28/88 $156,900 SA-139 PROCESSED
0003 006 SUTHERLAND HIGH 01/03/89 $98,703 SA-139 PROCESSED
0003 007 SUTHERLAND HIGH 06/13/89 $484,311 SA-139 PROCESSED
0003 008 SUTHERLAND HIGH 04/02/90 $60,693 SA-139 PROCESSED
0003 009 SUTHERLAND HIGH 08/20/91 $408,470 SA-139 PROCESSED
0003 013 SUTHERLAND HIGH 06/30/97 $25,400 SA-139 PROCESSED
0003 014 SUTHERLAND HIGH 09/02/04 $29,977,080 SA-139
0003 017 SUTHERLAND HIGH 04/08/02 $38,158 SA-139 PROCESSED
0003 019 SUTHERLAND HIGH 06/05/02 $51,914 SA-139 PROCESSED
0003 021 SUTHERLAND HIGH 08/27/04 $1,685,099 SA-139 PROCESSED
0004 002 ALLEN CREEK 11/05/87 $31,515 SA-139 PROCESSED
0004 003 ALLEN CREEK 02/02/90 $361,552 SA-139 PROCESSED
0004 004 ALLEN CREEK 06/13/89 $92,480 SA-139 PROCESSED
0004 005 ALLEN CREEK 01/03/89 $37,965 SA-139 PROCESSED
0004 006 ALLEN CREEK 08/20/91 $129,359 SA-139 PROCESSED
0004 011 ALLEN CREEK 12/19/03 $4,410,566 SA-139
0004 012 ALLEN CREEK 06/27/00 $113,049 SA-139 PROCESSED
0004 015 ALLEN CREEK 08/27/04 $258,332 SA-139 PROCESSED
0005 FP1 MENDON CENTER ELEMENTARY $4,000 SA-4
0005 002 MENDON CENTER ELEMENTARY $27,809 SA-4 PROCESSED
0005 003 MENDON CENTER ELEMENTARY 07/28/88 $384,300 SA-139 PROCESSED
0005 004 MENDON CENTER ELEMENTARY 01/30/89 $1,477,015 SA-139 PROCESSED
0005 005 MENDON CENTER ELEMENTARY 01/03/89 $173,392 SA-139 PROCESSED
0005 007 MENDON CENTER ELEMENTARY FILE SA-139 $0 SA-4
0005 008 MENDON CENTER ELEMENTARY $92,321 SA-4 PROCESSED
0005 013 MENDON CENTER ELEMENTARY 12/19/03 $2,716,388 SA-139
0005 014 MENDON CENTER ELEMENTARY 06/05/02 $42,669 SA-139 PROCESSED
0005 016 MENDON CENTER ELEMENTARY 08/27/04 $923,020 SA-139 PROCESSED
0006 FP1 PARK ROAD SCHOOL $4,000 SA-4
0006 003 PARK ROAD SCHOOL 11/05/87 $20,946 SA-139 PROCESSED
0006 004 PARK ROAD SCHOOL 02/02/90 $106,508 SA-139 PROCESSED
0006 006 PARK ROAD SCHOOL 01/03/89 $76,560 SA-139 PROCESSED
0006 007 PARK ROAD SCHOOL 08/20/91 $36,500 SA-139 PROCESSED
0006 011 PARK ROAD SCHOOL 12/19/03 $4,120,166 SA-139
0006 013 PARK ROAD SCHOOL 05/28/03 $730,752 SA-139 PROCESSED
0006 014 PARK ROAD SCHOOL 08/27/04 $840,079 SA-139 PROCESSED
0007 FP1 BARKER ROAD SCHOOL $12,000 SA-4
0007 SC1 BARKER ROAD SCHOOL $23,019 SA-4
0007 002 BARKER ROAD SCHOOL 11/05/87 $25,692 SA-139 PROCESSED
0007 003 BARKER ROAD SCHOOL 05/09/89 $271,000 SA-139 PROCESSED
0007 004 BARKER ROAD SCHOOL 02/02/90 $317,712 SA-139 PROCESSED
0007 005 BARKER ROAD SCHOOL 01/03/89 $51,636 SA-139 PROCESSED
0007 006 BARKER ROAD SCHOOL 08/20/91 $63,300 SA-139 PROCESSED
0007 008 BARKER ROAD SCHOOL 11/29/94 $2,335,631 SA-139 PROCESSED
0007 010 BARKER ROAD SCHOOL 07/06/07 $4,244,031 SA-139
0007 013 BARKER ROAD SCHOOL $58,300 SA-4 PROCESSED
0007 014 BARKER ROAD SCHOOL 08/27/04 $2,261,337 SA-139 PROCESSED
0007 016 BARKER ROAD SCHOOL 04/23/07 $389,400 SA-139
0007 017 BARKER ROAD SCHOOL FILE SA-139 $451,000 SA-4
0008 FP1 THORNELL ROAD SCHOOL $8,000 SA-4
0008 002 THORNEL ROAD SCHOOL 11/05/87 $17,606 SA-139 PROCESSED
0008 003 THORNEL ROAD SCHOOL 05/23/89 $229,966 SA-139 PROCESSED
0008 004 THORNEL ROAD SCHOOL 02/02/90 $206,472 SA-139 PROCESSED
0008 005 THORNEL ROAD SCHOOL 01/03/89 $35,879 SA-139 PROCESSED
0008 006 THORNEL ROAD SCHOOL 04/02/90 $18,070 SA-139 PROCESSED
0008 007 THORNEL ROAD SCHOOL FILE SA-139 $44,000 SA-4
0008 010 THORNELL ROAD SCHOOL 12/19/03 $2,338,390 SA-139
0008 012 THORNELL ROAD SCHOOL 08/27/04 $1,033,997 SA-139 PROCESSED
0009 FP1 PITTSFORD HIGH SCHOOL $4,000 SA-4
0009 SC1 PITTSFORD HIGH SCHOOL $24,065 SA-4
0009 001 PITTSFORD HIGH SCH FILE SA-139 $83,149 SA-4 PROCESSED
0009 002 PITTSFORD HIGH SCH 11/05/87 $152,632 SA-139 PROCESSED
0009 003 PITTSFORD HIGH SCH 05/09/89 $657,112 SA-139 PROCESSED
0009 004 PITTSFORD HIGH SCH 02/02/90 $1,244,880 SA-139 PROCESSED
0009 005 PITTSFORD HIGH SCH 01/03/89 $136,796 SA-139 PROCESSED
0009 006 PITTSFORD HIGH SCH 04/02/90 $18,350 SA-139 PROCESSED
0009 007 PITTSFORD HIGH SCHOOL 08/20/91 $277,118 SA-139 PROCESSED
0009 010 PITTSFORD HIGH SCHOOL 01/04/93 $135,000 SA-139
0009 012 PITTSFORD HIGH SCHOOL 12/19/03 $9,080,204 SA-139
0009 013 PITTSFORD HIGH SCHOOL 04/08/02 $70,581 SA-139 PROCESSED
0009 014 PITTSFORD HIGH SCHOOL 06/05/02 $60,258 SA-139 PROCESSED
0009 016 PITTSFORD HIGH SCHOOL 08/27/04 $1,590,607 SA-139 PROCESSED
0009 018 PITTSFORD HIGH SCHOOL FILE SA-139 $310,000 SA-4
0009 021 PITTSFORD HIGH SCHOOL FILE SA-139 $2,136,750 SA-4
0019 001 XXXMANUF BLD #1-SUTHERLAN 06/27/00 $199,080 SA-139 PROCESSED
0020 001 XXXMANUF BLD #2-SUTHERLAN 06/27/00 $199,080 SA-139 PROCESSED
0021 001 XXXMANUF BLD #3-SUTHERLAN FILE SA-139 $100,000 SA-4
0024 001 XXXMFD BLDG @ PITTSFORD M 06/28/01 $396,290 SA-139 PROCESSED
0025 SC1 XXXNEW MIDDLE SCHOOL XXX $22,050 SA-4
0025 001 XXXNEW MIDDLE SCHOOL XXX 09/02/04 $34,822,387 SA-139
1001 001 ADMINISTRATION BLDG FILE SA-139 $21,000 SA-4 N/A
1001 003 ADMINISTRATION BLDG 06/27/00 $162,378 SA-139 N/A
2015 001 STORAGE BLDG FILE SA-139 $159,800 SA-4 N/A
2026 001 XXXSTORAGE BLDG @ ALLEN C 12/19/03 $16,000 SA-139 N/A
2027 001 XXXSTORAGE BLDG @ PARK RD 12/19/03 $16,000 SA-139 N/A
2028 001 XXXSTORAGE BLDG @ MENDON 12/19/03 $22,000 SA-139 N/A
2030 001 STORAGE BLDG @ NEW MS XXX FILE SA-139 $42,000 SA-4 N/A
2033 001 XXXSTORAGE BLDG @ SUTHERL FILE SA-139 $22,000 SA-4 N/A
3012 001 MAINTENANCE BLDG FILE SA-139 $20,676 SA-4 N/A
3012 002 MAINTENANCE BLDG FILE SA-139 $0 SA-4 N/A
3012 003 MAINTENANCE BLDG FILE SA-139 $18,000 SA-4 N/A
5011 001 BUS GARAGE FILE SA-139 $45,626 SA-4 PROCESSED
5011 003 BUS GARAGE 11/05/87 $124,338 SA-139 PROCESSED
5011 004 BUS GARAGE 02/02/90 $127,234 SA-139 PROCESSED
5011 006 BUS GARAGE 01/03/89 $27,584 SA-139 PROCESSED
5011 007 BUS GARAGE 08/20/91 $86,000 SA-139 PROCESSED
5011 009 BUS GARAGE 06/12/96 $94,250 SA-139 PROCESSED
5011 011 BUS GARAGE 04/08/04 $2,703,034 SA-139
5011 067 BUS GARAGE 08/27/04 $36,360 SA-139
7029 001 XXXPRESS BOX @ MENDON HS 12/19/03 $30,000 SA-139
7032 001 XXXPRESS BOX @ SUTHERLAND FILE SA-139 $30,000 SA-4
NYSED HOME PAGE | STATE AID HOME PAGE | DISTRICT HOME PAGE