DISTRICT:  261401  ---  PITTSFORD                                                   
                                                                                    
                                         DATE           TOTAL    PROJ    FINAL      
                                       CONTRACT        PROJECT   COST    COST       
BLDG PROJ  ...... PROJECT NAME .....    SIGNED          COSTS    BASIS   REPORT     
0002  FP1  JEFFERSON RD SCHOOL                          $4,000  SA-4                
0002  003  JEFFERSON RD SCHOOL         11/05/87        $40,531  SA-139  PROCESSED   
0002  004  JEFFERSON RD SCHOOL         02/02/90       $210,410  SA-139  PROCESSED   
0002  005  JEFFERSON RD SCHOOL         07/28/88       $171,000  SA-139  PROCESSED   
0002  007  JEFFERSON RD SCHOOL         01/03/89        $40,661  SA-139  PROCESSED   
0002  008  JEFFERSON RD SCHOOL         06/13/89        $32,890  SA-139  PROCESSED   
0002  009  JEFFERSON RD SCHOOL         04/02/90        $16,432  SA-139  PROCESSED   
0002  010  JEFFERSON RD SCHOOL         08/20/91       $126,500  SA-139  PROCESSED   
0002  011  JEFFERSON RD SCHOOL         06/16/92        $56,400  SA-139  PROCESSED   
0002  012  JEFFERSON RD SCHOOL         01/11/94        $34,600  SA-139  PROCESSED   
0002  014  JEFFERSON RD SCHOOL         12/19/03     $3,946,640  SA-139              
0002  015  JEFFERSON RD SCHOOL         06/27/00       $126,867  SA-139  PROCESSED   
0002  016  JEFFERSON RD SCHOOL         04/08/02         $7,648  SA-139              
0002  017  JEFFERSON RD SCHOOL         06/06/02       $421,224  SA-139  PROCESSED   
0002  018  JEFFERSON RD SCHOOL         08/27/04       $315,645  SA-139  PROCESSED   
0002  020  JEFFERSON RD SCHOOL        FILE SA-139           $0  SA-4                
0002  021  JEFFERSON RD SCHOOL         05/03/07       $278,696  SA-139              
0003  FP1  SUTHERLAND HIGH                              $8,000  SA-4                
0003  SC1  SUTHERLAND HIGH                             $24,065  SA-4                
0003  001  SUTHERLAND HIGH            FILE SA-139      $85,104  SA-4                
0003  002  SUTHERLAND HIGH            FILE SA-139           $0  SA-4                
0003  003  SUTHERLAND HIGH             11/05/87       $152,441  SA-139  PROCESSED   
0003  004  SUTHERLAND HIGH             02/02/90     $1,435,000  SA-139  PROCESSED   
0003  005  SUTHERLAND HIGH             07/28/88       $156,900  SA-139  PROCESSED   
0003  006  SUTHERLAND HIGH             01/03/89        $98,703  SA-139  PROCESSED   
0003  007  SUTHERLAND HIGH             06/13/89       $484,311  SA-139  PROCESSED   
0003  008  SUTHERLAND HIGH             04/02/90        $60,693  SA-139  PROCESSED   
0003  009  SUTHERLAND HIGH             08/20/91       $408,470  SA-139  PROCESSED   
0003  013  SUTHERLAND HIGH             06/30/97        $25,400  SA-139  PROCESSED   
0003  014  SUTHERLAND HIGH             09/02/04    $29,977,080  SA-139              
0003  017  SUTHERLAND HIGH             04/08/02        $38,158  SA-139  PROCESSED   
0003  019  SUTHERLAND HIGH             06/05/02        $51,914  SA-139  PROCESSED   
0003  021  SUTHERLAND HIGH             08/27/04     $1,685,099  SA-139  PROCESSED   
0004  002  ALLEN CREEK                 11/05/87        $31,515  SA-139  PROCESSED   
0004  003  ALLEN CREEK                 02/02/90       $361,552  SA-139  PROCESSED   
0004  004  ALLEN CREEK                 06/13/89        $92,480  SA-139  PROCESSED   
0004  005  ALLEN CREEK                 01/03/89        $37,965  SA-139  PROCESSED   
0004  006  ALLEN CREEK                 08/20/91       $129,359  SA-139  PROCESSED   
0004  011  ALLEN CREEK                 12/19/03     $4,410,566  SA-139              
0004  012  ALLEN CREEK                 06/27/00       $113,049  SA-139  PROCESSED   
0004  015  ALLEN CREEK                 08/27/04       $258,332  SA-139  PROCESSED   
0005  FP1  MENDON CENTER ELEMENTARY                     $4,000  SA-4                
0005  002  MENDON CENTER ELEMENTARY                    $27,809  SA-4    PROCESSED   
0005  003  MENDON CENTER ELEMENTARY    07/28/88       $384,300  SA-139  PROCESSED   
0005  004  MENDON CENTER ELEMENTARY    01/30/89     $1,477,015  SA-139  PROCESSED   
0005  005  MENDON CENTER ELEMENTARY    01/03/89       $173,392  SA-139  PROCESSED   
0005  007  MENDON CENTER ELEMENTARY   FILE SA-139           $0  SA-4                
0005  008  MENDON CENTER ELEMENTARY                    $92,321  SA-4    PROCESSED   
0005  013  MENDON CENTER ELEMENTARY    12/19/03     $2,716,388  SA-139              
0005  014  MENDON CENTER ELEMENTARY    06/05/02        $42,669  SA-139  PROCESSED   
0005  016  MENDON CENTER ELEMENTARY    08/27/04       $923,020  SA-139  PROCESSED   
0006  FP1  PARK ROAD SCHOOL                             $4,000  SA-4                
0006  003  PARK ROAD SCHOOL            11/05/87        $20,946  SA-139  PROCESSED   
0006  004  PARK ROAD SCHOOL            02/02/90       $106,508  SA-139  PROCESSED   
0006  006  PARK ROAD SCHOOL            01/03/89        $76,560  SA-139  PROCESSED   
0006  007  PARK ROAD SCHOOL            08/20/91        $36,500  SA-139  PROCESSED   
0006  011  PARK ROAD SCHOOL            12/19/03     $4,120,166  SA-139              
0006  013  PARK ROAD SCHOOL            05/28/03       $730,752  SA-139  PROCESSED   
0006  014  PARK ROAD SCHOOL            08/27/04       $840,079  SA-139  PROCESSED   
0007  FP1  BARKER ROAD SCHOOL                          $12,000  SA-4                
0007  SC1  BARKER ROAD SCHOOL                          $23,019  SA-4                
0007  002  BARKER ROAD SCHOOL          11/05/87        $25,692  SA-139  PROCESSED   
0007  003  BARKER ROAD SCHOOL          05/09/89       $271,000  SA-139  PROCESSED   
0007  004  BARKER ROAD SCHOOL          02/02/90       $317,712  SA-139  PROCESSED   
0007  005  BARKER ROAD SCHOOL          01/03/89        $51,636  SA-139  PROCESSED   
0007  006  BARKER ROAD SCHOOL          08/20/91        $63,300  SA-139  PROCESSED   
0007  008  BARKER ROAD SCHOOL          11/29/94     $2,335,631  SA-139  PROCESSED   
0007  010  BARKER ROAD SCHOOL          07/06/07     $4,244,031  SA-139              
0007  013  BARKER ROAD SCHOOL                          $58,300  SA-4    PROCESSED   
0007  014  BARKER ROAD SCHOOL          08/27/04     $2,261,337  SA-139  PROCESSED   
0007  016  BARKER ROAD SCHOOL          04/23/07       $389,400  SA-139              
0007  017  BARKER ROAD SCHOOL         FILE SA-139     $451,000  SA-4                
0008  FP1  THORNELL ROAD SCHOOL                         $8,000  SA-4                
0008  002  THORNEL ROAD SCHOOL         11/05/87        $17,606  SA-139  PROCESSED   
0008  003  THORNEL ROAD SCHOOL         05/23/89       $229,966  SA-139  PROCESSED   
0008  004  THORNEL ROAD SCHOOL         02/02/90       $206,472  SA-139  PROCESSED   
0008  005  THORNEL ROAD SCHOOL         01/03/89        $35,879  SA-139  PROCESSED   
0008  006  THORNEL ROAD SCHOOL         04/02/90        $18,070  SA-139  PROCESSED   
0008  007  THORNEL ROAD SCHOOL        FILE SA-139      $44,000  SA-4                
0008  010  THORNELL ROAD SCHOOL        12/19/03     $2,338,390  SA-139              
0008  012  THORNELL ROAD SCHOOL        08/27/04     $1,033,997  SA-139  PROCESSED   
0009  FP1  PITTSFORD HIGH SCHOOL                        $4,000  SA-4                
0009  SC1  PITTSFORD HIGH SCHOOL                       $24,065  SA-4                
0009  001  PITTSFORD HIGH SCH         FILE SA-139      $83,149  SA-4    PROCESSED   
0009  002  PITTSFORD HIGH SCH          11/05/87       $152,632  SA-139  PROCESSED   
0009  003  PITTSFORD HIGH SCH          05/09/89       $657,112  SA-139  PROCESSED   
0009  004  PITTSFORD HIGH SCH          02/02/90     $1,244,880  SA-139  PROCESSED   
0009  005  PITTSFORD HIGH SCH          01/03/89       $136,796  SA-139  PROCESSED   
0009  006  PITTSFORD HIGH SCH          04/02/90        $18,350  SA-139  PROCESSED   
0009  007  PITTSFORD HIGH SCHOOL       08/20/91       $277,118  SA-139  PROCESSED   
0009  010  PITTSFORD HIGH SCHOOL       01/04/93       $135,000  SA-139              
0009  012  PITTSFORD HIGH SCHOOL       12/19/03     $9,080,204  SA-139              
0009  013  PITTSFORD HIGH SCHOOL       04/08/02        $70,581  SA-139  PROCESSED   
0009  014  PITTSFORD HIGH SCHOOL       06/05/02        $60,258  SA-139  PROCESSED   
0009  016  PITTSFORD HIGH SCHOOL       08/27/04     $1,590,607  SA-139  PROCESSED   
0009  018  PITTSFORD HIGH SCHOOL      FILE SA-139     $310,000  SA-4                
0009  021  PITTSFORD HIGH SCHOOL      FILE SA-139   $2,136,750  SA-4                
0019  001  XXXMANUF BLD #1-SUTHERLAN   06/27/00       $199,080  SA-139  PROCESSED   
0020  001  XXXMANUF BLD #2-SUTHERLAN   06/27/00       $199,080  SA-139  PROCESSED   
0021  001  XXXMANUF BLD #3-SUTHERLAN  FILE SA-139     $100,000  SA-4                
0024  001  XXXMFD BLDG @ PITTSFORD M   06/28/01       $396,290  SA-139  PROCESSED   
0025  SC1  XXXNEW MIDDLE SCHOOL XXX                    $22,050  SA-4                
0025  001  XXXNEW MIDDLE SCHOOL XXX    09/02/04    $34,822,387  SA-139              
1001  001  ADMINISTRATION BLDG        FILE SA-139      $21,000  SA-4       N/A      
1001  003  ADMINISTRATION BLDG         06/27/00       $162,378  SA-139     N/A      
2015  001  STORAGE BLDG               FILE SA-139     $159,800  SA-4       N/A      
2026  001  XXXSTORAGE BLDG @ ALLEN C   12/19/03        $16,000  SA-139     N/A      
2027  001  XXXSTORAGE BLDG @ PARK RD   12/19/03        $16,000  SA-139     N/A      
2028  001  XXXSTORAGE BLDG @ MENDON    12/19/03        $22,000  SA-139     N/A      
2030  001  STORAGE BLDG @ NEW MS XXX  FILE SA-139      $42,000  SA-4       N/A      
2033  001  XXXSTORAGE BLDG @ SUTHERL  FILE SA-139      $22,000  SA-4       N/A      
3012  001  MAINTENANCE BLDG           FILE SA-139      $20,676  SA-4       N/A      
3012  002  MAINTENANCE BLDG           FILE SA-139           $0  SA-4       N/A      
3012  003  MAINTENANCE BLDG           FILE SA-139      $18,000  SA-4       N/A      
5011  001  BUS GARAGE                 FILE SA-139      $45,626  SA-4    PROCESSED   
5011  003  BUS GARAGE                  11/05/87       $124,338  SA-139  PROCESSED   
5011  004  BUS GARAGE                  02/02/90       $127,234  SA-139  PROCESSED   
5011  006  BUS GARAGE                  01/03/89        $27,584  SA-139  PROCESSED   
5011  007  BUS GARAGE                  08/20/91        $86,000  SA-139  PROCESSED   
5011  009  BUS GARAGE                  06/12/96        $94,250  SA-139  PROCESSED   
5011  011  BUS GARAGE                  04/08/04     $2,703,034  SA-139              
5011  067  BUS GARAGE                  08/27/04        $36,360  SA-139              
7029  001  XXXPRESS BOX @ MENDON HS    12/19/03        $30,000  SA-139              
7032  001  XXXPRESS BOX @ SUTHERLAND  FILE SA-139      $30,000  SA-4                
                                                                                    
                                                                                    
                                                                                    
                                                                             