SA777 NEW YORK STATE EDUCATION DEPARTMENT 08/22/08
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 240401 --- GENESEO
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0005 FP1 MAIN BUILDING $3,600 SA-4
0005 001 MAIN BUILDING 03/03/87 $220,000 SA-139 PROCESSED
0005 002 MAIN BUILDING 06/24/87 $1,150,000 SA-139 PROCESSED
0005 003 MAIN BUILDING 05/20/87 $63,800 SA-139 PROCESSED
0005 004 MAIN BUILDING 02/01/89 $84,711 SA-139 PROCESSED
0005 005 MAIN BUILDING 05/21/90 $1,537,504 SA-139 PROCESSED
0005 006 MAIN BUILDING 06/01/90 $724,654 SA-139 PROCESSED
0005 008 MAIN BUILDING 10/19/94 $295,000 SA-139 PROCESSED
0005 009 MAIN BUILDING 08/23/96 $516,000 SA-139 PROCESSED
0005 010 MAIN BUILDING 12/07/99 $2,223,000 SA-139 PROCESSED
0005 012 MAIN BUILDING 04/20/05 $9,989,000 SA-139
0005 014 MAIN BUILDING 03/06/08 $1,950,000 SA-139