SA777 NEW YORK STATE EDUCATION DEPARTMENT 09/05/08
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 220101 --- SOUTH JEFFERSON
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0001 FP1 MAYNARD P WILSON BLDG $3,708 SA-4
0001 001 WILSON ELEMENTARY FILE SA-139 $0 SA-4 PROCESSED
0001 002 WILSON ELEMENTARY FILE SA-139 $0 SA-4
0001 004 WILSON ELEMENTARY 06/15/90 $9,483,195 SA-139 PROCESSED
0001 005 WILSON ELEMENTARY 04/17/90 $193,807 SA-139 PROCESSED
0001 006 MAYNARD P WILSON BLDG 09/24/01 $50,475 SA-139 PROCESSED
0001 007 MAYNARD P WILSON BLDG 09/10/02 $271,410 SA-139 PROCESSED
0004 001 ADAMS ELEMENTARY SCH 08/03/90 $621,634 SA-139 PROCESSED
0004 002 ADAMS ELEMENTARY SCH 04/17/90 $370,867 SA-139 PROCESSED
0004 003 ADAMS ELEMENTARY SCHOOL 09/12/94 $300,000 SA-139 PROCESSED
0004 004 ADAMS ELEMENTARY SCHOOL 09/24/01 $76,675 SA-139 PROCESSED
0005 FP1 GEN BRUCE E CLARKE JR HS $6,327 SA-4
0005 001 GEN BRUCE E CLARKE JR HS 09/20/90 $7,606,131 SA-139 PROCESSED
0005 002 GEN BRUCE E CLARKE JR HS 04/17/90 $24,170 SA-139 PROCESSED
0005 003 GEN BRUCE E CLARKE JR HS 09/24/01 $69,175 SA-139 PROCESSED
0005 004 GEN BRUCE E CLARKE JR HS 09/10/02 $14,393,725 SA-139
0006 001 MANNSVILLE MANOR CSD 08/03/90 $395,836 SA-139 PROCESSED
0006 002 MANNSVILLE MANOR CSD 04/17/90 $102,665 SA-139 PROCESSED
0006 003 MANNSVILLE MANOR ELEM BLD 09/24/01 $39,475 SA-139 PROCESSED
0006 004 MANNSVILLE MANOR ELEM BLD 09/10/02 $5,908,368 SA-139 PROCESSED
4008 001 XXXMANNSVILLE BUS GARAGE 09/10/02 $660,933 SA-139 PROCESSED
5002 001 BUS GARAGE-ADAMS CTR 06/15/90 $32,130 SA-139 PROCESSED
5002 002 BUS GARAGE-ADAMS CTR 07/27/93 $269,500 SA-139 PROCESSED
5002 003 BUS GARAGE-ADAMS CTR 09/21/98 $54,575 SA-139 PROCESSED
5002 004 BUS GARAGE-ADAMS CTR 09/10/02 $445,564 SA-139 PROCESSED