SA777 NEW YORK STATE EDUCATION DEPARTMENT 09/05/08
GENERAL AID SERVICES
BUILDING PROJECTS ON FILE
DISTRICT: 141101 --- SPRINGVILLE-GRIFF
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0000 001 03/08/89 $1,006,964 SA-139 PROCESSED
0001 FP1 SENIOR HIGH SCHOOL $6,000 SA-4
0001 001 SENIOR HIGH SCHOOL FILE SA-139 $0 SA-4
0001 002 SENIOR HIGH SCHOOL FILE SA-139 $0 SA-4
0001 003 SENIOR HIGH SCHOOL FILE SA-139 $0 SA-4
0001 004 SENIOR HIGH SCHOOL 06/23/88 $668,120 SA-139
0001 005 SENIOR HIGH SCHOOL 07/21/88 $341,416 SA-139
0001 006 SENIOR HIGH SCHOOL 05/15/89 $488,727 SA-139 PROCESSED
0001 007 SENIOR HIGH SCHOOL 12/13/90 $749,650 SA-139 PROCESSED
0001 008 SENIOR HIGH SCHOOL 07/29/92 $135,000 SA-139 PROCESSED
0001 010 SENIOR HIGH SCHOOL 04/17/97 $2,093,400 SA-139 PROCESSED
0001 011 SENIOR HIGH SCHOOL 03/18/02 $5,949,373 SA-139 PROCESSED
0004 FP1 ELEMENTARY SCHOOL $12,000 SA-4
0004 001 ELEM SCHOOL FILE SA-139 $0 SA-4
0004 002 ELEM SCHOOL 04/29/87 $85,800 SA-139
0004 003 ELEM SCHOOL 05/15/89 $83,115 SA-139 PROCESSED
0004 004 ELEM SCHOOL 12/13/90 $491,829 SA-139 PROCESSED
0004 005 ELEMENTARY SCHOOL 07/29/92 $75,000 SA-139 PROCESSED
0004 007 ELEMENTARY SCHOOL 04/17/97 $3,795,000 SA-139 PROCESSED
0004 008 ELEMENTARY SCHOOL 03/01/02 $895,250 SA-139 PROCESSED
0005 FP1 COLDEN ELEM SCHOOL $6,000 SA-4
0005 001 COLDEN ELEM SCHOOL FILE SA-139 $0 SA-4
0005 002 COLDEN ELEM SCHOOL 05/15/89 $184,037 SA-139 PROCESSED
0005 003 COLDEN ELEM SCHOOL 06/15/89 $32,500 SA-139 PROCESSED
0005 004 COLDEN ELEM SCHOOL 12/13/90 $170,400 SA-139 PROCESSED
0005 006 COLDEN ELEM SCHOOL 04/17/97 $3,942,600 SA-139 PROCESSED
0005 007 COLDEN ELEM SCHOOL 08/13/98 $426,000 SA-139 PROCESSED
0005 008 COLDEN ELEM SCHOOL 03/18/02 $235,377 SA-139 PROCESSED
0005 009 COLDEN ELEM SCHOOL 10/10/06 $340,000 SA-139
0008 FP1 MIDDLE SCHOOL $6,000 SA-4
0008 001 MIDDLE SCHOOL 01/25/90 $105,194 SA-139 PROCESSED
0008 002 MIDDLE SCHOOL 12/13/90 $97,220 SA-139 PROCESSED
0008 003 MIDDLE SCHOOL 02/28/91 $150,000 SA-139 PROCESSED
0008 004 MIDDLE SCHOOL 07/29/92 $15,000 SA-139 PROCESSED
0008 005 MIDDLE SCHOOL 03/11/93 $750,000 SA-139 PROCESSED
0008 007 MIDDLE SCHOOL 07/10/96 $83,755 SA-139 PROCESSED
0008 008 MIDDLE SCHOOL 04/17/97 $1,131,000 SA-139 PROCESSED
0008 009 MIDDLE SCHOOL 03/18/02 $2,320,000 SA-139 PROCESSED
0008 010 MIDDLE SCHOOL FILE SA-139 $65,766 SA-4
2013 001 GARAGE - TRACTOR FILE SA-139 $0 SA-4 N/A
5010 001 BUS GARAGE FILE SA-139 $0 SA-4
5010 002 BUS GARAGE 11/17/89 $51,680 SA-139 PROCESSED
7007 001 PRESS BOX FILE SA-139 $0 SA-4