DISTRICT: 140207 --- SWEET HOME
DATE TOTAL PROJ FINAL
CONTRACT PROJECT COST COST
BLDG PROJ ...... PROJECT NAME ..... SIGNED COSTS BASIS REPORT
0002 001 DEXTER TERRACE ELEM 06/15/92 $178,000 SA-139 PROCESSED
0002 002 DEXTER TERRACE ELEM $55,000 SA-4 PROCESSED
0002 003 DEXTER TERRACE ELEMENTARY 02/09/00 $7,775,000 SA-139 PROCESSED
0002 004 DEXTER TERRACE ELEMENTARY 09/18/02 $162,500 SA-139 PROCESSED
0002 005 DEXTER TERRACE ELEMENTARY FILE SA-139 $113,988 SA-4
0003 FP1 SWEET HOME HIGH SCHOOL $7,970 SA-4
0003 001 SWEET HOME HIGH SCH 11/04/86 $80,830 SA-139 PROCESSED
0003 002 SWEET HOME HIGH SCH 01/05/90 $225,394 SA-139 PROCESSED
0003 003 SWEET HOME HIGH SCHOOL 06/15/92 $2,221,000 SA-139 PROCESSED
0003 004 SWEET HOME HIGH SCHOOL 04/12/97 $5,525,874 SA-139 PROCESSED
0003 005 SWEET HOME HIGH SCHOOL 09/18/01 $18,490,785 SA-139
0003 006 SWEET HOME HIGH SCHOOL 08/14/02 $632,150 SA-139 PROCESSED
0003 008 SWEET HOME HIGH SCHOOL FILE SA-139 $727,293 SA-4
0006 001 GLENDALE ELEMENTARY 11/04/86 $23,791 SA-139 PROCESSED
0006 003 GLENDALE ELEMENTARY 06/15/92 $1,094,000 SA-139 PROCESSED
0006 004 GLENDALE ELEMENTARY 04/12/97 $1,218,727 SA-139 PROCESSED
0006 005 GLENDALE ELEMENTARY 09/18/01 $3,081,885 SA-139
0006 006 GLENDALE ELEMENTARY 04/04/06 $330,813 SA-139
0006 007 GLENDALE ELEMENTARY FILE SA-139 $652,953 SA-4
0007 001 MAPLEMERE ELEMENTARY 11/04/86 $11,466 SA-139 PROCESSED
0007 003 MAPLEMERE ELEMENTARY 06/15/92 $1,505,000 SA-139 PROCESSED
0007 004 MAPLEMERE ELEMENTARY 04/12/97 $963,379 SA-139 PROCESSED
0007 005 MAPLEMERE ELEMENTARY 09/18/01 $3,383,926 SA-139 PROCESSED
0007 007 MAPLEMERE ELEMENTARY FILE SA-139 $779,331 SA-4
0008 FP1 MIDDLE SCHOOL $14,820 SA-4
0008 001 MIDDLE SCHOOL 11/04/86 $11,466 SA-139 PROCESSED
0008 002 MIDDLE SCHOOL 06/23/89 $270,451 SA-139 PROCESSED
0008 003 MIDDLE SCHOOL 07/10/89 $32,990 SA-139 PROCESSED
0008 004 MIDDLE SCHOOL 06/15/92 $1,402,000 SA-139 PROCESSED
0008 005 MIDDLE SCHOOL 06/15/92 $591,000 SA-139 PROCESSED
0008 006 MIDDLE SCHOOL 04/12/97 $1,638,195 SA-139 PROCESSED
0008 007 MIDDLE SCHOOL 04/04/06 $23,143,370 SA-139
0009 FP1 WILLOW RIDGE ELEMENTARY $10,000 SA-4
0009 001 WILLOW RIDGE ELEM 11/04/86 $11,351 SA-139 PROCESSED
0009 003 WILLOW RIDGE ELEM 06/15/92 $1,315,000 SA-139 PROCESSED
0009 004 WILLOW RIDGE ELEMENTARY 04/12/97 $1,250,175 SA-139 PROCESSED
0009 005 WILLOW RIDGE ELEMENTARY 09/18/01 $2,752,066 SA-139 PROCESSED
0009 007 WILLOW RIDGE ELEMENTARY FILE SA-139 $659,148 SA-4
0012 FP1 HERTIGAGE HTS ELEMENTARY $5,220 SA-4
0012 001 HERTIGAGE HEIGHTS EL FILE SA-139 $14,000 SA-4
0012 003 HERTIGAGE HEIGHTS EL 06/26/89 $179,174 SA-139 PROCESSED
0012 004 HERTIGAGE HTS ELEMENTARY 06/15/92 $812,000 SA-139 PROCESSED
0012 005 HERTIGAGE HTS ELEMENTARY 04/12/97 $1,490,318 SA-139 PROCESSED
0012 006 HERTIGAGE HTS ELEMENTARY 09/18/01 $1,348,988 SA-139 PROCESSED
0012 007 HERTIGAGE HTS ELEMENTARY 04/04/06 $475,817 SA-139
0012 008 HERTIGAGE HTS ELEMENTARY FILE SA-139 $468,342 SA-4
4001 001 SERVICE CENTER 06/15/92 $782,000 SA-139 PROCESSED
4001 002 SERVICE CENTER 10/25/91 $60,000 SA-139 PROCESSED
4001 003 SERVICE CENTER 04/12/97 $166,182 SA-139 PROCESSED
4001 004 SERVICE CENTER 09/18/01 $372,350 SA-139 PROCESSED