SA777                NEW YORK STATE EDUCATION DEPARTMENT              10/10/08      
                            GENERAL AID SERVICES                                    
                          BUILDING PROJECTS ON FILE                                 
                                                                                    
DISTRICT:  131602  ---  SPACKENKILL                                                 
                                                                                    
                                         DATE           TOTAL    PROJ    FINAL      
                                       CONTRACT        PROJECT   COST    COST       
BLDG PROJ  ...... PROJECT NAME .....    SIGNED          COSTS    BASIS   REPORT     
0001  001  MARTHA W LAWRENCE ES        07/28/88       $136,320  SA-139  PROCESSED   
0001  003  MARTHA W LAWRENCE ES        02/22/05       $204,800  SA-139              
0001  004  MARTHA W LAWRENCE ES       FILE SA-139     $135,000  SA-4                
0001  005  MARTHA W LAWRENCE ES        09/29/07       $125,000  SA-139              
0002  FP1  TODD JUNIOR HIGH SCHOOL                      $4,590  SA-4                
0002  001  TODD JUNIOR H. S.           01/24/89        $45,000  SA-139  PROCESSED   
0002  002  TODD JUNIOR H. S.           07/11/89       $233,289  SA-139  PROCESSED   
0002  003  TODD JUNIOR H. S.           07/11/89        $75,664  SA-139  PROCESSED   
0002  004  TODD JUNIOR H. S.           06/11/90        $65,000  SA-139  PROCESSED   
0002  005  TODD JUNIOR HIGH SCHOOL     06/13/94        $34,464  SA-139  PROCESSED   
0002  006  TODD JUNIOR HIGH SCHOOL     07/01/94       $350,343  SA-139  PROCESSED   
0002  007  TODD JUNIOR HIGH SCHOOL     07/22/96        $54,678  SA-139  PROCESSED   
0002  008  TODD JUNIOR HIGH SCHOOL     07/22/96        $88,670  SA-139  PROCESSED   
0002  009  TODD JUNIOR HIGH SCHOOL     02/09/99     $3,989,000  SA-139  PROCESSED   
0002  010  TODD JUNIOR HIGH SCHOOL                     $65,705  SA-4    PROCESSED   
0002  011  TODD JUNIOR HIGH SCHOOL     02/22/05       $860,500  SA-139              
0003  001  NASSAU ROAD SCHOOL         FILE SA-139           $0  SA-4                
0003  002  NASSAU ROAD SCHOOL          12/11/89       $206,442  SA-139  PROCESSED   
0003  003  NASSAU ROAD SCHOOL          07/11/89        $80,110  SA-139  PROCESSED   
0003  004  NASSAU ROAD SCHOOL          06/18/90       $200,000  SA-139  PROCESSED   
0003  005  NASSAU ROAD SCHOOL                          $16,145  SA-4    PROCESSED   
0003  006  NASSAU ROAD SCHOOL          06/13/94        $49,066  SA-139  PROCESSED   
0003  007  NASSAU ROAD SCHOOL          07/10/96       $127,240  SA-139  PROCESSED   
0003  008  NASSAU ROAD SCHOOL          04/17/01       $310,641  SA-139  PROCESSED   
0003  009  NASSAU ROAD SCHOOL          02/22/05       $702,300  SA-139              
0004  FP1  HAGAN ELEMENTARY                             $4,990  SA-4                
0004  001  HAGAN ELEMENTARY            12/11/89       $138,161  SA-139  PROCESSED   
0004  003  HAGAN ELEMENTARY            06/18/90        $43,305  SA-139  PROCESSED   
0004  004  HAGAN ELEMENTARY            02/02/90        $31,853  SA-139              
0004  005  HAGAN ELEMENTARY            07/30/93       $398,000  SA-139  PROCESSED   
0004  006  HAGAN ELEMENTARY            06/13/94        $35,245  SA-139  PROCESSED   
0004  007  HAGAN ELEMENTARY            07/10/96       $100,792  SA-139  PROCESSED   
0004  009  HAGAN ELEMENTARY            04/17/01       $396,935  SA-139  PROCESSED   
0004  010  HAGAN ELEMENTARY            02/22/05     $1,182,400  SA-139              
0005  FP1  HIGH SCHOOL                                  $5,770  SA-4                
0005  001  HIGH SCHOOL                FILE SA-139           $0  SA-4                
0005  003  HIGH SCHOOL                FILE SA-139           $0  SA-4                
0005  004  HIGH SCHOOL                FILE SA-139      $34,840  SA-4    PROCESSED   
0005  005  HIGH SCHOOL                 05/23/90       $165,000  SA-139  PROCESSED   
0005  006  HIGH SCHOOL                 03/11/91        $70,758  SA-139  PROCESSED   
0005  007  HIGH SCHOOL                 06/13/94       $359,397  SA-139  PROCESSED   
0005  008  HIGH SCHOOL                 06/16/95       $327,850  SA-139  PROCESSED   
0005  009  HIGH SCHOOL                 07/10/97        $58,438  SA-139  PROCESSED   
0005  010  HIGH SCHOOL                 07/10/96       $123,351  SA-139  PROCESSED   
0005  011  HIGH SCHOOL                 07/01/97       $258,000  SA-139  PROCESSED   
0005  012  HIGH SCHOOL                 04/17/01       $427,097  SA-139  PROCESSED   
0005  014  HIGH SCHOOL                 06/11/02        $75,000  SA-139  PROCESSED   
0005  015  HIGH SCHOOL                 02/20/07     $2,150,000  SA-139              
0007  001                              07/28/87       $130,000  SA-139  PROCESSED   
0008  001  XXXPORTABLES @ TODD MIDDL   07/28/98       $153,370  SA-139  PROCESSED   
4007  001  BUS GARAGE                 FILE SA-139           $0  SA-4                
4007  002  BUS GARAGE                  12/10/96        $92,104  SA-139  PROCESSED   
7001  002  MARTHA W LAWRENCE ES        04/28/89       $143,117  SA-139  PROCESSED   
7999  001                              04/20/04       $520,450  SA-139  PROCESSED   
8009  003                              04/17/01        $83,873  SA-139  PROCESSED   
                                                                                    
                                                                                    
                                                                                    
                                                                             