0002 FP1 MIDDLE SCHOOL/ADDITION $5,450 SA-4
0002 001 MIDDLE SCHOOL 01/11/90 $173,000 SA-139 PROCESSED
0002 003 MIDDLE SCHOOL 04/30/96 $3,574,025 SA-139 PROCESSED
0002 005 MIDDLE SCHOOL/ADDITION 09/14/00 $125,759 SA-139 PROCESSED
0002 006 MIDDLE SCHOOL/ADDITION 10/12/01 $546,200 SA-139 PROCESSED
0002 007 MIDDLE SCHOOL/ADDITION 05/23/03 $40,000 SA-139 PROCESSED
0002 009 MIDDLE SCHOOL/ADDITION 03/03/08 $1,780,000 SA-139
0002 010 MIDDLE SCHOOL/ADDITION 03/03/08 $1,611,842 SA-139
0003 001 JOHN R HARSHAW 01/11/90 $4,164,002 SA-139 PROCESSED
0003 002 JOHN R HARSHAW 09/28/95 $141,500 SA-139 PROCESSED
0003 004 JOHN R HARSHAW 09/14/00 $12,068,640 SA-139 PROCESSED
0003 005 JOHN R HARSHAW 10/12/01 $1,135,500 SA-139 PROCESSED
0003 006 JOHN R HARSHAW 05/23/03 $60,000 SA-139 PROCESSED
0003 007 JOHN R HARSHAW 06/27/05 $34,869 SA-139 PROCESSED
0003 008 JOHN R HARSHAW 03/03/08 $2,510,000 SA-139
0004 002 JR SR HIGH SCHOOL 10/21/88 $20,000 SA-139 PROCESSED
0004 003 JR SR HIGH SCHOOL 01/11/90 $97,550 SA-139 PROCESSED
0004 007 JR SR HIGH SCHOOL 04/30/96 $1,789,493 SA-139 PROCESSED
0004 010 JR SR HIGH SCHOOL 06/22/99 $1,458,000 SA-139 PROCESSED
0004 011 JR SR HIGH SCHOOL 02/22/99 $100,000 SA-139 PROCESSED
0004 012 JR SR HIGH SCHOOL 09/14/00 $1,481,811 SA-139 PROCESSED
0004 013 JR SR HIGH SCHOOL 10/12/01 $2,486,400 SA-139 PROCESSED
0004 014 JR SR HIGH SCHOOL 05/23/03 $215,000 SA-139 PROCESSED
0004 015 JR SR HIGH SCHOOL 05/23/03 $370,000 SA-139 PROCESSED
0004 016 JR SR HIGH SCHOOL 06/27/05 $101,674 SA-139 PROCESSED
0004 017 JR SR HIGH SCHOOL 03/03/08 $3,405,643 SA-139
0004 018 JR SR HIGH SCHOOL 03/03/08 $1,694,118 SA-139
0009 001 C KENYON ELEMENTARY FILE SA-139 $0 SA-4
0009 002 C KENYON ELEMENTARY 01/11/90 $446,750 SA-139 PROCESSED
0009 005 C KENYON ELEMENTARY 07/03/91 $200,000 SA-139 PROCESSED
0009 006 C KENYON ELEMENTARY 07/01/91 $75,000 SA-139 PROCESSED
0013 001 FILE SA-139 $0 SA-4
2005 001 OLD BUS GARAGE FILE SA-139 $169,850 SA-4 N/A
5001 001 BUS GARAGE 09/13/91 $394,000 SA-139 PROCESSED
5001 003 BUS GARAGE 04/30/96 $107,915 SA-139 PROCESSED
5001 005 BUS GARAGE 10/12/01 $731,600 SA-139 PROCESSED
5001 006 BUS GARAGE 03/03/08 $231,849 SA-139
5001 007 BUS GARAGE 10/11/07 $313,000 SA-139
7020 001 XXXNEW PRESS BOX @ HIGH S $47,000 SA-139
7999 001 06/01/97 $1,194,000 SA-139 PROCESSED