STATE AID BUILDING - PROSPECTIVE PROJECT AMORTIZATION
DISTRICT: 600402 NEWARK VALLEY DATE: 09/04/08
******************************************************************************************
PROJECT NUMBER: 0002-007 PROJECT NAME: NATHAN T HALL ELEM SCHOOL
VOTER AUTHORIZATION DATE: 05/15/2001 BLD3
JULY 2003 INTERIM YEARS JULY 2017
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 269,392
CMMSR APP DATE: 05/03/02 DATE CONTRACT SIGNED: 06/24/02 INT RATE: 0.04500 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 08/21/2002
PROJECTS APPROVED BY THE COMMISSIONER PRIOR TO 7/1/2002 BUT AFTER 12/1/2001, THAT HAVE A
CAPITAL OUTLAY BALANCE AS OF 7/1/2002, WILL BE AMORTIZED STARTING 7/1/2004.
CLICK HERE FOR CAPITAL OUTLAY INFORMATION
******************************************************************************************
PROJECT NUMBER: 0002-008 PROJECT NAME: NATHAN T HALL ELEM SCHOOL
VOTER AUTHORIZATION DATE: 12/18/2001 BLD3
JULY 2005 INTERIM YEARS JULY 2019
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 418,106 418,106 418,106
AMORTIZED PRINCIPAL: 4,722,197 CAPITAL OUTLAY: 0
CMMSR APP DATE: 03/09/04 DATE CONTRACT SIGNED: 06/07/04 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 06/13/2005
******************************************************************************************
PROJECT NUMBER: 0002-009 PROJECT NAME: NATHAN T HALL ELEM SCHOOL
VOTER AUTHORIZATION DATE: 08/11/2003 BLD3
JULY 2004 INTERIM YEARS JULY 2019
ASSUMED PAYMENTS: 1 2 1
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 0
CMMSR APP DATE: 08/06/03 DATE CONTRACT SIGNED: 10/27/03 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 04/16/2004
******************************************************************************************
PROJECT NUMBER: 0002-011 PROJECT NAME: NATHAN T HALL ELEM SCHOOL
VOTER AUTHORIZATION DATE: 00/00/0000 BLD
SA-139 HAS NOT BEEN RECEIVED FOR THIS PROJECT
******************************************************************************************
PROJECT NUMBER: 0003-011 PROJECT NAME: MIDDLE SCHOOL
VOTER AUTHORIZATION DATE: 05/15/2001 BLD3
JULY 2003 INTERIM YEARS JULY 2017
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 250,585
CMMSR APP DATE: 05/03/02 DATE CONTRACT SIGNED: 06/24/02 INT RATE: 0.04500 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 08/21/2002
PROJECTS APPROVED BY THE COMMISSIONER PRIOR TO 7/1/2002 BUT AFTER 12/1/2001, THAT HAVE A
CAPITAL OUTLAY BALANCE AS OF 7/1/2002, WILL BE AMORTIZED STARTING 7/1/2004.
CLICK HERE FOR CAPITAL OUTLAY INFORMATION
******************************************************************************************
PROJECT NUMBER: 0003-012 PROJECT NAME: MIDDLE SCHOOL
VOTER AUTHORIZATION DATE: 12/18/2001 BLD3
JULY 2005 INTERIM YEARS JULY 2019
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 482,750 482,750 482,750
AMORTIZED PRINCIPAL: 5,452,307 CAPITAL OUTLAY: 0
CMMSR APP DATE: 03/09/04 DATE CONTRACT SIGNED: 06/07/04 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 06/13/2005
******************************************************************************************
PROJECT NUMBER: 0003-013 PROJECT NAME: MIDDLE SCHOOL
VOTER AUTHORIZATION DATE: 08/11/2003 BLD3
JULY 2004 INTERIM YEARS JULY 2019
ASSUMED PAYMENTS: 1 2 1
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 0
CMMSR APP DATE: 08/06/03 DATE CONTRACT SIGNED: 10/27/03 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 04/16/2004
******************************************************************************************
PROJECT NUMBER: 0007-007 PROJECT NAME: NEWARK VAL SR HIGH SCHOOL
VOTER AUTHORIZATION DATE: 05/15/2001 BLD3
JULY 2003 INTERIM YEARS JULY 2017
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 613,180
CMMSR APP DATE: 05/03/02 DATE CONTRACT SIGNED: 06/24/02 INT RATE: 0.04500 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 08/21/2002
PROJECTS APPROVED BY THE COMMISSIONER PRIOR TO 7/1/2002 BUT AFTER 12/1/2001, THAT HAVE A
CAPITAL OUTLAY BALANCE AS OF 7/1/2002, WILL BE AMORTIZED STARTING 7/1/2004.
CLICK HERE FOR CAPITAL OUTLAY INFORMATION
******************************************************************************************
PROJECT NUMBER: 0007-008 PROJECT NAME: NEWARK VAL SR HIGH SCHOOL
VOTER AUTHORIZATION DATE: 12/18/2001 BLD3
JULY 2005 INTERIM YEARS JULY 2019
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 843,346 843,346 843,346
AMORTIZED PRINCIPAL: 9,524,991 CAPITAL OUTLAY: 0
CMMSR APP DATE: 03/09/04 DATE CONTRACT SIGNED: 06/07/04 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 06/13/2005
******************************************************************************************
PROJECT NUMBER: 0007-009 PROJECT NAME: NEWARK VAL SR HIGH SCHOOL
VOTER AUTHORIZATION DATE: 08/11/2003 BLD3
JULY 2004 INTERIM YEARS JULY 2019
ASSUMED PAYMENTS: 1 2 1
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 0
CMMSR APP DATE: 08/06/03 DATE CONTRACT SIGNED: 10/27/03 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 04/16/2004
******************************************************************************************
PROJECT NUMBER: 0007-010 PROJECT NAME: NEWARK VAL SR HIGH SCHOOL
VOTER AUTHORIZATION DATE: 00/00/0000 BLD
SA-139 HAS NOT BEEN RECEIVED FOR THIS PROJECT
******************************************************************************************
PROJECT NUMBER: 5004-005 PROJECT NAME: BUS GARAGE
VOTER AUTHORIZATION DATE: 05/15/2001 BLD3
JULY 2003 INTERIM YEARS JULY 2017
ASSUMED PAYMENTS: 2 2 2
DEBT SERVICE: 0 0 0
AMORTIZED PRINCIPAL: 0 CAPITAL OUTLAY: 15,143
CMMSR APP DATE: 05/03/02 DATE CONTRACT SIGNED: 06/24/02 INT RATE: 0.04500 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 08/21/2002
PROJECTS APPROVED BY THE COMMISSIONER PRIOR TO 7/1/2002 BUT AFTER 12/1/2001, THAT HAVE A
CAPITAL OUTLAY BALANCE AS OF 7/1/2002, WILL BE AMORTIZED STARTING 7/1/2004.
CLICK HERE FOR CAPITAL OUTLAY INFORMATION
******************************************************************************************
PROJECT NUMBER: 5004-006 PROJECT NAME: BUS GARAGE
VOTER AUTHORIZATION DATE: 05/15/2007 BLD4
JULY 2008 INTERIM YEARS JULY 2023
ASSUMED PAYMENTS: 1 2 1
DEBT SERVICE: 4,600 9,200 4,600
AMORTIZED PRINCIPAL: 103,914 CAPITAL OUTLAY: 100,000
CMMSR APP DATE: 07/06/07 DATE CONTRACT SIGNED: 08/27/07 INT RATE: 0.03875 PPU: 15
CONTRACT DATE NOTIFICATION TO SED (SA-139 RECEIVE DATE): 10/19/2007
******************************************************************************************
NYSED HOME PAGE | STATE AID HOME PAGE | DISTRICT HOME PAGE